2015-08-26 15:01:32 | 1ST REVIEW: FBC 2014 MECHANICAL |
| PERMIT #15080312 |
| 8/26/15 |
| |
| 1) SIZING CALCULATIONS REQUIRED FOR WSHP-1. REFER TO |
| C403.2.1 FBC-14 ENERGY CONSERVATION- CALCULATION OF |
| HEATING AND COOLING LOADS. |
| DESIGN LOADS SHALL BE DETERMINED IN ACCORDANCE WITH THE |
| PROCEDURES DESCRIBED IN THE ASHRAE/ACCA STANDARD 183 OR |
| ACCA MANUAL N AND SHALL BE ATTACHED TO THE CODE |
| COMPLIANCE FORM SUBMITTED TO THE BUILDING DEPARTMENT |
| WHEN THE BUILDING IS PERMITTED OR, IN THE EVENT THE |
| MECHANICAL PERMIT IS OBTAINED AT A LATER TIME, THE |
| SIZING CALCULATION SHALL BE SUBMITTED WITH THE |
| APPLICATION FOR THE MECHANICAL PERMIT. HEATING AND |
| COOLING LOADS SHALL BE ADJUSTED TO ACCOUNT FOR LOAD |
| REDUCTIONS THAT ARE ACHIEVED WHEN ENERGY RECOVERY |
| SYSTEMS ARE UTILIZED IN THE HVAC SYSTEM IN ACCORDANCE |
| WITH THE ASHRAEHVAC SYSTEMS AND EQUIPMENT HANDBOOK. |
| ALTERNATIVELY, DESIGN LOADS SHALL BE DETERMINED BY AN |
| APPROVED EQUIVALENT COMPUTATION PROCEDURE, USING THE |
| DESIGN PARAMETERS SPECIFIED IN CHAPTER 3. |
| 2) A SMOKE DETECTOR IS REQUIRED IN THE RETURN AIR |
| SYSTEM OF WSHP-1- REFER TO SECTION 606.2.1 FBC-14 |
| MECHANICAL. RETURN AIR SYSTEMS. |
| SMOKE DETECTORS SHALL BE INSTALLED IN RETURN AIR |
| SYSTEMS WITH A DESIGN CAPACITY GREATER THAN 2,000 CFM |
| (0.9 M3/S) IN THE RETURN AIR DUCT OR PLENUM UPSTREAM OF |
| ANY FILTERS, EXHAUST AIR CONNECTIONS, OUTDOOR AIR |
| CONNECTIONS, OR DECONTAMINATION EQUIPMENT AND |
| APPLIANCES. |
| 3) PROVIDE A NARRATIVE DESCRIPTION AND DIAGRAM |
| DETAILING THE SMOKE DETECTOR CONTROLS OPERATION AND |
| SUPERVISION- SECTIONS 606.4 & 606.4.1. |
| 4) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE SMOKE |
| DETECTOR AND FIRE DAMPER. THE SUBMITTALS SHALL BRE |
| REVIEWED AND APPROVED BY THE DESIGN PROFESSIONAL OF |
| RECORD. |
| 5) SEE SECTION 809.2 FBC-14 EXISITNG BUILDING CODE: |
| ALTERED EXISTING SYSTEMS. |
| IN MECHANICALLY VENTILATED SPACES, EXISTING MECHANICAL |
| VENTILATION SYSTEMS THAT ARE ALTERED, RECONFIGURED, OR |
| EXTENDED SHALL PROVIDE NOT LESS THAN 5 CUBIC FEET PER |
| MINUTE (CFM) (0.0024 M3/S) PER PERSON OF OUTDOOR AIR |
| AND NOT LESS THAN 15 CFM (0.0071 M3/S) OF VENTILATION |
| AIR PER PERSON; OR NOT LESS THAN THE AMOUNT OF |
| VENTILATION AIR DETERMINED BY THE INDOOR AIR QUALITY |
| PROCEDURE OF ASHRAE 62. PLEASE PROVIDE CALCULATIONS AND |
| A VENTILATION SCHEDULE TO VERIFY COMPLIANCE. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |
| |