Plan Review Notes For Permit 15070555 |
Permit Number |
15070555 |
|
Review Stop |
M |
Sequence Number |
1 |
|
Notes |
Date |
Text |
2015-07-17 16:10:05 | 1ST REVIEW: FBC 2014 MECHANICAL | | PERMIT #15070555 | | | | 1) PROVIDE COOLING AND HEATING LOAD CALCULATIONS FOR | | THE NEW AC SYSTEM IN ACCORDANCE WITH ACCA MANUAL N OR | | THE ACCA/ASHRAE STANDARD 183- SECTION C403.2.1 FBC | | FIFTH EDITION 2014 ENERGY CONSERVATION CODE. | | 2) DUCT SMOKE DETECTORS SHALL BE INSTALLED IN THE | | RETURN DUCT OF THE NEW AHU, AND THE RETURN DUCTS OF THE | | EXISTING AHU'S- REFER TO SECTIONS 606.2.1 & 606.2.2 | | FBC- 2014 MECHANICAL. SHOW THE LOCATIONS OF THE DEVICES | | ON THE PLANS AND INDICATE HOW THEY WILL BE SUPERVISED | | PER SECTION 606.4.1. | | 3) INDICATE THE TYPE AND DIAMETER OF THE CONDENSATE | | PIPE PER TABLE 307.2.2, AND PROVIDE DETAILS FOR | | SECONDARY DISPOSAL: A) PAN DIMENSIONS, DEPTH, AND GAGE | | OF STEEL. B) TYPE AND SIZE OF PAN DRAIN PIPE AND | | TERMINATION LOCATION- REFER TO SECTION 307.2.3 FOR | | ADDITIONAL INFORMATION. | | 4) THE SCOPE OF WORK NOTE #1 ON THE CONTRACT INDICATES | | A 12X24 FT. MOUNTING PAD FOR THE CONDENSER, HOWEVER THE | | PLAN INDICATES A 4X34 FT. PAD: PLEASE CLARIFY AND | | PROVIDE STRUCTURAL DETAILS FOR THE PAD, AND WIND LOAD | | TIE DOWN ENGINEERING FOR MOUNTING THE CONDENSER TO THE | | PAD. | | | | CHRISTOPHER L. COLE | | MECHANICAL PLANS EXAMINER | | 561-805-6719 | | [email protected] | | | | |
|