2015-07-04 06:52:56 | 1) THE PIPING PLAN SHOWS UNDERGROUND GAS PIPING & |
| SLEEVE TO TWO DRYERS. GAS PIPING IS PROHIBITED PER THE |
| 2010 FBC-R SEC. G2415.4. THE INSTALLATION OF GAS PIPNG |
| BENEATH BUILDINGS IS PERMITTED WHEN THERE IS NO OTHER |
| WAY TO INSTALL THE PIPING. SUBMIT A FLOOR PLAN SHOWING |
| THE LOCATION OF ALL ALL GAS APPLIANCES IN RELATION TO |
| THE GAS METER. THE DRYERS SHALL NOT BE PIPED UNDER THE |
| SLAB UNLESS THAT IS THE ONLY ALTERNATIVE. |
| 2) SUBMIT MANUFACTURER'S SPECIFICATION SHEETS FOR ALL |
| GAS APPLIANCES & EQUIPMENT. ALL APPLIANCES & EQUIPMENT |
| SHALL BE LISTED PER THE 2010 FBC-R SEC.G2404.3. |
| 3)THE FOLLOWING ITEMS SHALL BE IDENTIFIED ON BOTH |
| DRAWINGS FOR THE INSTALLATION OF THE GAS PIPING UNDER |
| THE BUILDING SLAB IF IT IS ALLOWED. THE INSTALLATION |
| UNDER THE SALB IS CONTINGENT UPON THE LOCATION OF THE |
| GAS DRYERS. |
| A) INDICATE THE TYPE OF SLEEVE MATERIAL FOR THE PIPING |
| FOR THE DRYERS ON THE PLAN. THE MATERIAL SHALL COMPLY |
| WITH 2010 FBC-R SEC.G2415.12. |
| B) THE TERMINATION OF THE CONDUIT INDOOR AND OUTDOOR |
| SHALL COMPLY WITH 2010 FBC-R SEC. G2415.12.1. |
| C) INDICATE ON THE PLAN HOW THE ANNULAR SPACE BETWEEN |
| THE GAS PIPING AND THE SLEEVE IS TO BE SEALED. BE |
| SPECIFIC. |
| D) INDICATE THE TYPE OF GAS PIPING TO BE INSTALLED TO |
| THE DRYERS. PE PIPING CAN ONLY BE INSTALLED OUTSIDE |
| UNDERGROUND PER THE 2010 FBC-R SEC. G2415.15.1. |
| 4) INDICATE THE APPLICABLE SIZING TABLES USED FOR THE |
| SIZING OF THE PE LINE AND ALSO THE PIPING TO THE |
| DRYERS.2010 FBC-R SEC. G2413.3. |
| 5) SUBMIT MANUFACTURER'S SPECIFICATION SHEETS FOR THE 2 |
| PSI REGULATORS. REGULATORS SHALL COMPLY WITH 2010 FBC-R |
| SEC.G2421.1 & G2421.2. |
| |
| PLUMBING PLAN REVIEW |
| TIM LARGE |
| CHIEF PLUMBING INSPECTOR |
| 561-805-6692 |
| [email protected] |
| |