2015-06-23 11:36:23 | 1ST REVIEW: FBC 2010 MECHANICAL |
| |
| 1) PROVIDE REVISED ENERGY CALCULATIONS SHOWING THE |
| COMPLIANCE DATA FOR THE NEW AC UNITS. |
| 2) SHEET M0.1: PROVIDE THE OUTDOOR AIR CALCULATIONS FOR |
| THE GUEST ROOMS PER TABLE 403.3 FBC-10 MECHANICAL. |
| 3) SHEETS M0.1 & M1.1: THE REQUIRED 108 CFM'S OF |
| OUTDOOR AIR FOR THE GUEST ROOM CORRIDORS SHOWN IN THE |
| SCHEDULE IS NOT BEING SUPPLIED: PLEASE NOTE THE MINI |
| SPLIT SYSTEMS AC-1A AND AC-1B ARE DUCTLESS. |
| 4) M1.1: THE AC-1A &1B CASSETTES APPEAR TO BE MOUNTED |
| IN THE FIRE-RATED CORRIDOR CEILING MEMBRANE. INDICATE |
| HOW THESE OPENINGS ARE GOING TO PROTECTED FROM FIRE AND |
| SMOKE INTRUSION- REFERENCE SECTION 607.6.2 FBC-10 |
| MECHANICAL. |
| 5) M1.1 THE RETURN AIR GRILLS AND SUPPLY DUCTS ABOVE |
| THE EAST AND WEST CORRIDOR FIRE DOORS IN THE CORRIDOR |
| CEILINGS MUST BE PROTECTED WITH FIRE/SMOKE DAMPERS. |
| PROVIDE A SCHEDULE ON THE PLANS INDICATING THE MAKES, |
| MODELS, TYPES, SIZES, AND FIRE-RESISTANCE RATINGS OF |
| THESE DAMPERS, AND ALL REQUIRED DAMPERS TO BE INSTALLED |
| IN THE CORRIDORS AND GUEST ROOMS. NOTE: ALL DAMPER |
| ACCESS DOORS LOCATED IN THE CORRIDOR AND GUEST ROOM |
| CEILINGS SHALL BE FIRE-RATED. PROVIDE DETAILS AND |
| SUBMIT SPECS FOR ALL PRODUCTS REVIEWED AND STAMPED BY |
| THE DESIGN PROFESSIONAL OF RECORD. |
| 6) M1.1: SHOW THE LOCATIONS OF THE CONDENSER UNITS FOR |
| AC-1A & 1B, AND PROVIDE INSTALLATION DETAILS. |
| 7) M1.1: FIRE/SMOKE DAMPERS ARE REQUIRED FOR THE |
| EXHAUST DUCTS PENENTRATING THE EAST AND WEST RATED |
| CORRIDOR WALLS, UNLESS CLAIMING ONE OF THE EXCEPTIONS |
| UNDER SECTION 607.5.3: PLEASE PROVIDE DETAUILS |
| INDICATING COMPLIANCE. |
| 8) M1.1: SHOW THE O/A SUPPLY DUCT FOR AC-2. |
| 9) PROVIDE A NARRATIVE INDICATING HOW THE DUCT SMOKE |
| DETECTORS WILL BE SUPERVISED RELATING TO THE FIRE ALARM |
| SYSTEM AND THE FAN SHUT SEQUENCE OF OPERATION. CLARIFY |
| IS AC-1A & 1B WILL BE LINKED TO THE SYSTEM. |
| 10) PROVIDE PRIMARY AND SECONDARY CONDENSATE DISPOSAL |
| DETAILS FOR ALL OF THE AIR HANDLERS- SECTION 307 FBC-10 |
| MECH. |
| 11) PROVIDE REFRIGERANT PIPING DETAILS INCLUDING PIPING |
| MATERIAL, PIPING INSULATION, PIPING RUNS AND THROUGH |
| PENETRATION FIRE-STOPPING DETAILS. INDICATE THE AMOUNT |
| OF REFRIGERANT CHARGE IN LBS. FOR AC-1. |
| 12) PROVIDE HANGING AND SUPPORT DETAILS FOR THE VAV |
| BOXES AND DUCTS. |
| 13) PROVIDE A SUBMITTAL PACKAGE FROM THE DESIGN |
| PROFESSIONAL OF RECORD THAT INCLUDES THE AC UNITS, THE |
| FIRE/SMOKE DAMPERS, THE DUCT SMOKE DETECTORS, THE |
| MOTORIZED O/A DAMPERS, AND THE VAV BOXES. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |
| |