2016-02-16 12:15:12 | MECHANICAL PROVISOS: |
| PERMIT #15031312 |
| 333 DOWNTOWN |
| 2/16/16 |
| |
| 1) PRIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY, |
| AIR DISTRIBUTION SYSTEM TESTING, ADJUSTING AND |
| BALANCING IS REQUIRED IN ACCORDANCE WITH SECTION |
| 503.2.9 FBC-10 ENERGY CONSERVATION. |
| 503.2.9.1: AIR DISTRIBUTION SYSTEM TESTING, ADJUSTING |
| AND BALANCING. |
| CONSTRUCTION DOCUMENTS SHALL REQUIRE THAT A WRITTEN |
| BALANCE REPORT BE PROVIDED TO THE OWNER OR THE |
| DESIGNATED REPRESENTATIVE OF THE BUILDING OWNER FOR |
| HVAC SYSTEMS SERVING ZONES WITH A TOTAL CONDITIONED |
| AREA EXCEEDING 5000 SQUARE FEET (465 M2). AIR |
| DISTRIBUTION SYSTEMS SHALL BE TESTED, ADJUSTED, AND |
| BALANCED BY A LICENSED ENGINEER OR A COMPANY OR |
| INDIVIDUAL HOLDING A CURRENT CERTIFICATION FROM A |
| RECOGNIZED TESTING AND BALANCING AGENCY ORGANIZATION IN |
| ACCORDANCE WITH GENERALLY ACCEPTED ENGINEERING |
| STANDARDS. |
| EXCEPTIONS: |
| A) BUILDINGS WITH COOLING OR HEATING SYSTEM CAPACITIES |
| OF 15 TONS OR LESS PER SYSTEM MAY BE TESTED AND |
| BALANCED BY A MECHANICAL CONTRACTOR LICENSED TO DESIGN |
| AND INSTALL SUCH SYSTEM(S). |
| B) BUILDINGS WITH COOLING OR HEATING SYSTEM CAPACITIES |
| OF 65,000 BTU/H OR LESS PER SYSTEM ARE EXEMPT FROM THE |
| REQUIREMENTS OF THIS SECTION. |
| |
| 2) THE PERMIT IS BEING ISSUED WITHOUT APPROVED |
| SUBMITTALS FOR MECHANICAL EQUIPMENT AND COMPONENTS |
| INCLUDING ROOF TOP HVAC STANDS AND CURBS, EXTERIOR |
| LOUVERS, FIRE AND FIRE/SMOKE DAMPERS, OUTSIDE AIR |
| MOTORIZED DAMPERS, SMOKE DETECTORS, C0 AND NITROGEN |
| DETECTORS, REFRIGERANT PIPING INSULATION, AC EQUIPMENT |
| ETC. PLEASE REVIEW THE FOLLOWING: |
| DEFERRED SUBMITTAL: 107.3.4.2 DEFERRED SUBMITTALS. FOR |
| THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| SUBMITTED AT THE TIME OF THE |
| APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| REVIEW BY THE BUILDING OFFICIAL. |
| |
| DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| OFFICIAL. |
| DEFERRED SUBMITTAL. 2010 FBC 107.3.4.1 PRODUCT |
| APPROVALS. THOSE PRODUCTS WHICH ARE REGULATED BY THE |
| DCA RULE 9N-03 SHALL BE REVIEWED AND APPROVED IN |
| WRITING BY THE DESIGNER OF RECORD PRIOR TO SUBMITTAL |
| FOR JURISDICTIONAL APPROVAL. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |
| |
| |
| |