Date |
Text |
2015-09-16 17:16:12 | 2ND REVIEW: FBC 2010 MECHANICAL |
| PERMIT #15031312 |
| 333 FERN ST. |
| |
| PLEASE REFER TO THE 1ST REVIEW COMMENTS AND THE |
| SUBMITTED NARRATIVE RESPONSE. |
| |
| 1) COMMENT #1 FROM THE 1ST REVIEW, REQUEST FOR AC |
| CALCULATIONS: THE CALCULATIONS HAVE BEEN SUBMITTED |
| HOWEVER, PLEASE REVIEW UPLOADED FILE TITLED "ISIS |
| COMMON AREAS" I AM FINDING SOME OF THE SYSTEM TITLES ON |
| THE CALCS DO NOT MATCH THE SYSTEM TITLES ON THE |
| SCHEDULES I.E. AC 2-2 IS TITLED "ELEVATOR SERVICE" IN |
| THE CALCS BUT LISTED AS 2ND LEVEL VESTIBULE IN THE |
| SCHEDULE, AC-2-5 IN THE CALCS BUT NOT IN THE SCHEDULES. |
| IN ADDITION, I AM NOT FINDING CALCULATIONS FOR RTU-1, |
| AND PACU-1 & 2, AND ALL OF THE MITSUBISHI GROUND FLOOR |
| SYSTEMS HAVE OVERSIZED HEATING CAPACITIES PER THE |
| CALCS- REFER TO SECTION 503.2.2 FBC-10 ENERGY |
| CONSERVATION. |
| 2) COMMENT #2 FROM THE 1ST REVIEW, REQUEST FOR ENERGY |
| CALCS: ENERGY EFFICIENCY FORM 506-2010 HAS BEEN |
| SUBMITTED, HOWEVER THERE ARE A FEW ISSUES CORRELATING |
| THE CALCS WITH THE AC SYSTEMS: A) REFER TO SHEET M4.00 |
| "SPLIT AC UNIT SCHEDULE"- CU'S 4A & 5A ARE NOT IN THE |
| CALCS. B) M4.00 "DUCTLESS SPLIT SYSTEM COMMON AREAS"- |
| THE SCHEDULE INDICATES 2.0 TON/20.7 SEER SYSTEMS FOR |
| RETAIL, HOWEVER THE CALCS INDICATE RETAIL A (40,800 |
| BTU'S/19 SEER) & RETAIL B (19,000 BTU'S/20 SEER). C) |
| M.400 "DUCTLESS SPLIT SYSTEM COMMON AREAS"- THE COOLING |
| AND HEATING CAPACITIES AND SEERS IN THE SCHEDULE DON'T |
| MATCH WITH THE CALCS. D) M4.01 "SPLIT AIR CONDITIONING |
| UNIT SCHEDULE"- THE COOLING AND HEATING CAPACITIES, THE |
| TAG #S, THE SEERS, AND THE LOCATIONS OF THE SYSTEMS AS |
| SHOWN IN THE SCHEDULE DO NOT MATCH THE CALCS. PLEASE |
| REVIEW AND REVISE ACCORDINGLY, AND COMPLETE THE |
| COMPLIANCE CHECKLIST ON PAGE 31- PLACE A CHECK MARK IN |
| EACH APPLICABLE BOX. |
| 3) COMMENT #4 FROM THE 1ST REVIEW: MANUFACTURER'S |
| SPECIFICATIONS FROM CARRIER AND MITSUBISHI HAVE BEEN |
| UPLOADED FOR REVIEW, HOWEVER MANY OF THE SHEETS SHOWING |
| PIPE DIAGRAMS ARE CUT-OFF ON THE RIGHT SIDES OF THE |
| PAGES LEAVING INCOMPLETE DIAGRAMS- PLEASE CORRECT. IN |
| ADDITION, THE SECOND PART OF THE COMMENT REGARDING PIPE |
| PENETRATION SEALS WAS NOT ADDRESSED IN THE RESPONSE |
| NARRATIVE. |
| 4) COMMENT #5: THE O/A CALCULATIONS FOR THE FITNESS |
| CENTERS ARE NOT IN COMPLIANCE WITH TABLE 403.3.- 20 CFM |
| PER PERSON/0.06 CFM PER SQ. FT. REQUIRED. |
| 5) COMMENT #9C: I HAVE REVIEWED SHEET E5.2.1 AND DO NOT |
| SEE ANY DIRECT CORRELATION BETWEEN THE GENERATOR AND |
| THE SMOKE CONTROL SYSTEM. PLEASE INDICATE WHICH OF THE |
| CONNECTED METER CENTERS CONTAINS THE FAN CIRCUITRY. |
| 6) COMMENT #14: REFER TO SHEET M4.07 AND CORRECT THE |
| NOTE SPECIFYING CO LEVEL SETPOINT AT 35PPM TO READ |
| 25PPM PER SECTION 404.1 FBC-10 MECHANICAL. |
| 7) COMMENT #15: REFER TO TABLE 403.3 FOR FITNESS CENTER |
| O/A. THE TABLE INDICATES 20 CFM PER PERSON AND 0.06 PER |
| SQ. FT. PLEASE REVISE THE SCHEDULE AND PLANS. |
| 8) COMMENT #16: PROVIDE SIZING CALCULATIONS FOR THE |
| RETURN AIR PLENUM SMOKE EXHAUST SYSTEM SHOWN ON THE |
| GROUND FLOOR. |
| 9) COMMENT #18: THE REVISED PLAN DOES NOT CLEARLY |
| INDICATE THE REQUIRED 10' CLEARANCE DISTANCE FOR THE |
| GENERATOR EXHAUST TO THE SWITCH GEAR ROOM AIR INTAKE. |
| 10) COMMENT #20: PROVIDE UL TESTED AND APPROVED |
| ASSEMBLY DETAILS FOR CONSTRUCTION OF THE 2HR FIRE-RATED |
| ENCLOSURE HOUSING THE POOL EQUIPMENT COMBUSTION AIR |
| INTAKE. |
| 11) COMMENT #25: PLEASE SUBMIT MANUFACTURER'S |
| SPECIFICATIONS FOR THE DRYERS, AS PREVIOUSLY REQUESTED. |
| 12) COMMENT #26: THE LOUVER NOA #10-0921.10 LISTED IN |
| THE SCHEDULE HAS EXPIRED. PLEASE PROVIDE A CURRENT NOA |
| # AND SUBMITTAL. |
| 13) COMMENT #27: THE REQUESTED WIND LOAD ENGINEERING |
| FOR THE ROOF TOP AC UNITS AND OTHER EQUIPMENT IS |
| INCOMPLETE PENDING STRUCTURAL ENGINEER'S DESIGN |
| CRITERIA AND DETAILS. PLEASE REFER TO M2-9-1 AND |
| PROVIDE TIE-DOWN DETAILS FOR ALL EQUIPMENT AND |
| COMPONENTS INCLUDING THE RTU, PACU'S, AC CONDENSERS AND |
| STANDS, THE SUPPLY AND EXHAUST DUCTWORK, THE STAIRWELL |
| PRESSURIZATION FANS, FAN CURBS, LOUVERS, ETC. |
| 14) PROVIDE AIR DISTRIBUTION SCHEDULES INDICATING THE |
| VARIOUS MAKES AND MODELS OF SUPPLY DIFFUSERS, RETURN |
| AND TRANSFER GRILLS ETC. TO BE UISED IN THE COMMON |
| AREAS AND THE APARTMENTS |
| 15) PROVIDE UL TESTED AND APPROVED ASSEMBLY DETAILS FOR |
| CONSTRUCTION OF THE 2HR FIRE-RATED ENCLOSURES HOUSING |
| THE STAIRWELL PRESSURIZATION DUCTS ON THE GROUND FLOOR. |
| 16) SMOKE CONTROL RATIONAL ANALYSIS: REFER TO THE |
| SECTION ENTITLED "SYSTEM IMPLEMENTATION REQUIREMENTS" |
| AND PROVIDE PRODUCT DATA SHEETS FOR THE SMOKE CONTROL |
| FANS WITH REVIEW AND APPROVAL STAMPS AND SIGNATURES |
| FROM THE ENGINEER OF RECORD. B) PROVIDE ON THE |
| MECHANICAL PLANS AIR EQUIPMENT SCHEDULES FOR ALL |
| COMPONENTS OF THE SMOKE CONTROL SYSTEM INCLUDING DUCTS, |
| DIFFUSERS, RETURN GRILLS, DAMPERS ETC, SMOKE DETECTORS |
| ETC. PLEASE INCLUDE NOTES FOR ITEMIZING ALL REQUIRED |
| TESTING PROCEDURES AS OUTLINED IN THE RATIONAL ANALYSIS |
| INCLUDING LEAK TESTING OF DUCTWORK AND DAMPERS PURSUANT |
| TO THE SYSTEM REQUIREMENTS. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |
| |
| |