2015-04-13 14:31:24 | PLAN REVIEW COMMENTS |
| |
| 1ST REVIEW: FBC 2010 |
| ROBERT MCDOUGAL, CBO |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| (561) 805-6714 |
| [email protected] |
| |
| DENIED BY MECHANICAL |
| PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| |
| 1) FBC-R - M1401.3 SIZING. HEATING AND COOLING |
| EQUIPMENT SHALL BE SIZED BASED ON BUILDING LOADS |
| CALCULATED IN ACCORDANCE WITH ACCA MANUAL J OR OTHER |
| APPROVED HEATING AND COOLING CALCULATION METHODOLOGIES. |
| PROVIDE EQUIPMENT SIZING CALCULATIONS. THE MECHANICAL |
| EQUIPMENT LISTED IN THE SCHEDULE ON SHEET 3 IS REQUIRED |
| TO MATCH THE SIZING CALCULATIONS. |
| |
| 2) FBC-R - M 1602.4 PROVIDE BALANCED AIR RETURN AT |
| BEDROOMS. SPECIFY THE SIZES OF THE RETURN AIR TRANSFER |
| GRILLS ON THE MECHANICAL PLAN. TRANSFER GRILLES SHALL |
| USE 50 SQUARE INCHES (OF GRILLE AREA) TO 100 CFM (OF |
| SUPPLY AIR) FOR SIZING THROUGH-THE-WALL TRANSFER |
| GRILLES AND USING AN UNRESTRICTED 1 INCH UNDERCUTTING |
| OF DOORS TO ACHIEVE PROPER RETURN AIR BALANCE. |
| HABITABLE ROOMS ONLY SHALL BE REQUIRED TO MEET THESE |
| REQUIREMENTS FOR PROPER BALANCED RETURN AIR EXCLUDING |
| BATHROOMS, CLOSETS, STORAGE ROOMS AND LAUNDRY ROOMS, |
| EXCEPT THAT ALL SUPPLY AIR INTO THE MASTER SUITE SHALL |
| BE INCLUDED. |
| |
| 3) FBC 107.2.1 - INFORMATION ON CONSTRUCTION DOCUMENTS. |
| ALL INFORMATION, DRAWINGS, SPECIFICATIONS AND |
| ACCOMPANYING DATA SHALL BEAR THE NAME AND SIGNATURE OF |
| THE PERSON RESPONSIBLE FOR THE DESIGN. |
| |
| 4) THE PLANS SHOW THE AIRHANDLER LOCATED IN A CLOSET. |
| IF THE RETURN IS THROUGH A LOUVERED DOOR, SPECIFY THAT |
| ON THE PLANS. FBC 107.2 |
| |
| |