Date |
Text |
2016-12-15 11:44:45 | 1ST REVIEW FBC-2014 MECHANICAL |
| PERMIT #15020937 |
| 12/15/16 |
| |
| 1) PLEASE CLARIFY OR CORRECT THE FOLLOWING CONFLICTS |
| CONCERNING THE HEATING CAPACITIES FOR THE AHU'S: |
| |
| A) THE ENERGYGAUGE COMPLIANCE DATA FORM INDICATES |
| 136520 BTUH ELECTRIC FURNACE CAPACITIES FOR AHU 1-1 AND |
| 1-2 , HOWEVER NO ELECTRIC DATA IS LISTED IN THE |
| SCHEDULES FOR THE UNITS ON M4.2, AND DUCT HEATERS AT 40 |
| KW EACH ARE SPECIFIED FOR BOTH SYSTEMS. |
| |
| B) THE AC LOAD CALCULATIONS INDICATE 87,461 BTUH |
| (25.6KW) HEATING REQUIRED FOR AHU 1-1, AND 24,624 BTUH |
| (7.2KW) FOR AHU 1-2 WHICH INDICATES THE DUCT HEATERS |
| HAVE BEEN OVERSIZED. |
| |
| C) THE HEATING CAPACITIES FOR AHU'S 1-4 & 2-1 ARE |
| OVERSIZED BASED ON THE CALCULATED LOADS. |
| |
| 2) PROVIDE COMPLIANCE DATA FOR THE CHILLER IN THE |
| ENERGYGAUGE SUBMITTAL- SEE TABLE C403.2.3(7) FBC-14 |
| ENERGY CONSERVATION. |
| |
| 3) M5.2: PROVIDE THE WIND LOAD DESIGN CRITERIA FOR |
| ATTACHMENT OF THE CHILLER- SEE SECTION 301.15. |
| |
| 4) PROVIDE WIND LOAD ENGINEERING AND DESIGN CRITERIA |
| FOR ATTACHMENT OF THE ROOFTOP FGI GRAVITY INTAKE HOOD. |
| |
| 5) SHOW THE REQUIRED CLEARANCES FOR THE GRAVITY INTAKE |
| ON THE ROOF PER SECTION 401.4, AND INDICATE HOW THE |
| OPENING WILL BE PROTECTED PER SECTION 401.5. |
| |
| 6) INDICATE THE REQUIRED CLEARANCE DISTANCE |
| MEASUREMENTS FOR THE EXHAUST OUTLETS PER SECTION |
| 501.3.1 AND SUBMIT A FL. PRODUCT APPROVAL OR MIAMI-DADE |
| NOA FOR THE LOUVER- RULE 9N-3 DEPT. OF COMMUNITY |
| AFFAIRS. |
| |
| 7) PROVIDE SUBMITTALS FOR THE FIRE DAMPERS AND O/A |
| MOTORIZED DAMPERS, AND PROVIDE INSTALLATION DETAILS ON |
| THE PLANS. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |