2016-01-25 10:49:06 | FAILED |
| |
| PROVIDE WRITTEN RESPONSE. |
| |
| 1) REPEAT COMMENT: PROVIDE VERIFICATION THAT THE |
| DEVELOPMENT CONDITIONS FROM RESOLUTION NO. 144-11 |
| LISTED BELOW HAVE BEEN SATISFIED: |
| |
| A. GRANT TO THE CITY A TEMPORARY ACCESS EASEMENT FOR |
| USE OF TUXEDO AND COCONUT LANES UNTIL THE ROADS ARE |
| RELOCATED; EXISTING UTILITIES UNTIL RELOCATED; AND |
| EXISTING DRAINAGE UNTIL RELOCATED, IN FORM ACCEPTABLE |
| TO THE CITY. THIS HAS NOT BEEN COMPLETED. |
| |
| B. GRANT TO THE CITY A DRAINAGE AND FLOWAGE EASEMENT |
| FOR ALL ON-SITE DRAINAGE AND FLOWAGE THROUGH THE |
| BIOSWALE [OR CURRENT ITERATION]. PBDA SHALL BE |
| RESPONSIBLE FOR MAINTENANCE OF ALL ON-SITE DRAINAGE. |
| THIS HAS NOT BEEN COMPLETED. |
| |
| E. RECORD A PLAT FOR THE ENTIRE PBDA CAMPUS. PRIOR TO |
| RECORDATION, THE PLAT SHALL BE SUBMITTED FOR REVIEW |
| THROUGH THE MINOR SUBDIVISION PROCESS TO INCLUDE ALL |
| REQUIRED EASEMENTS. THE RELOCATION AND/OR ABANDONMENT |
| OF EASEMENTS WILL REQUIRE APPLICATIONS TO BE FILED WITH |
| THE ENGINEERING SERVICES DIVISION. THIS HAS NOT BEEN |
| COMPLETED. |
| |
| H. THE PBDA SHALL PROVIDE A TEMPORARY ACCESS, UTILITY |
| AND DRAINAGE EASEMENT, APPROVED BY THE ENGINEERING |
| SERVICES DEPARTMENT, IN FAVOR OF THE CITY AT THE TIME |
| OF THE RECORDATION OF THE PBDA PLAT. THIS HAS NOT BEEN |
| COMPLETED. |
| |
| 2) REPEAT COMMENT: PROVIDE VERIFICATION THAT THE |
| FOLLOWING CONDITIONS OUTLINED IN RESOLUTION NO. 341-10 |
| HAVE BEEN MET: |
| |
| A. PALM BEACH DAY ACADEMY SHALL RECORD A PLAT FOR THE |
| ENTIRE CAMPUS. PRIOR TO RECORDATION, THE PALM BEACH DAY |
| ACADEMY SHALL MAKE APPLICATION TO THE PLANNING AND |
| ZONING DEPARTMENT FOR THE REVIEW OF THE PLAT THROUGH |
| THE MINOR SUBDIVISION PROCESS WITH FINAL PLAT APPROVAL |
| THROUGH AN APPLICATION SUBMITTED TO THE CITY'S |
| ENGINEERING SERVICES DEPARTMENT. ALL REQUIRED EASEMENTS |
| SHALL BE PROVIDED EITHER BY PLAT OR SEPARATE |
| INSTRUMENT, IN A FORM ACCEPTABLE TO THE CITY. THIS HAS |
| NOT BEEN COMPLETED. |
| |
| B. IN THE EVENT THE UTILITIES ARE RELOCATED TO ANOTHER |
| AREA OF THE PALM BEACH DAY ACADEMY CAMPUS, THE PALM |
| BEACH DAY ACADEMY SHALL GRANT TO THE CITY A UTILITY |
| EASEMENT OVER, UNDER AND THROUGH SUCH AREA OF THE |
| CAMPUS. THIS HAS NOT BEEN COMPLETED. |
| |
| C. PALM BEACH DAY ACADEMY SHALL SUBMIT AN APPLICATION |
| TO THE ENGINEERING SERVICES DEPARTMENT FOR THE |
| REALIGNMENT OF THE TUXEDO AND COCOANUT LANES AND THE |
| RELOCATION OF ANY CITY UTILITIES. AFTER THE ENGINEERING |
| SERVICES DEPARTMENT APPROVAL, THE PALM BEACH DAY |
| ACADEMY SHALL, AT ITS OWN COST AND EXPENSE, REALIGN THE |
| INTERSECTION OF TUXEDO AND COCOANUT LANES AND RELOCATE |
| ANY AND ALL UTILITY LINES LOCATED WITHIN THE ABANDONED |
| RIGHT-OF-WAY. THE PALM BEACH DAY ACADEMY SHALL POST A |
| BOND TO THE CITY IN THE AGREED AMOUNT OF THE ESTIMATED |
| COSTS ASSOCIATED WITH THE RELOCATION OF THE ROADWAY AND |
| THE UTILITY LINES PRIOR TO THE RECORDATION OF THE PALM |
| BEACH DAY ACADEMY PLAT. THIS HAS NOT BEEN COMPLETED. |
| |
| D. PALM BEACH DAY ACADEMY SHALL PROVIDE TO THE CITY A |
| TEMPORARY ACCESS EASEMENT, AND TEMPORARY UTILITIES AND |
| DRAINAGE EASEMENTS OVER AND ACROSS THE ABANDONED |
| RIGHT-OF-WAY, IN FORM APPROVED BY THE OFFICE OF THE |
| CITY ATTORNEY, AT THE TIME OF THE RECORDATION OF THE |
| PALM BEACH DAY ACADEMY PLAT. THIS HAS NOT BEEN |
| COMPLETED. |
| |
| E. PALM BEACH DAY ACADEMY SHALL TENDER AND DELIVER |
| $11,000 TO THE CITY AS COMPENSATION FOR THE VALUE OF |
| THE RIGHT-OF-WAY AND ASSOCIATED DEVELOPMENT RIGHTS. |
| THIS HAS NOT BEEN COMPLETED. |
| |
| 3) REPEAT COMMENT: PROVIDE VERIFICATION THAT THE |
| FOLLOWING CONDITIONS OUTLINED IN RESOLUTION NO. 342-10 |
| HAVE BEEN MET: |
| |
| A. PALM BEACH DAY ACADEMY SHALL RECORD A PLAT FOR THE |
| ENTIRE CAMPUS. PRIOR TO RECORDATION, THE PALM BEACH DAY |
| ACADEMY SHALL MAKE APPLICATION TO THE PLANNING AND |
| ZONING DEPARTMENT FOR THE REVIEW OF THE PLAT THROUGH |
| THE MINOR SUBDIVISION PROCESS WITH FINAL PLAT APPROVAL |
| THROUGH AN APPLICATION SUBMITTED TO THE CITY'S |
| ENGINEERING SERVICES DEPARTMENT. ALL REQUIRED EASEMENTS |
| SHALL BE PROVIDED EITHER BY PLAT OR SEPARATE |
| INSTRUMENT, IN A FORM ACCEPTABLE TO THE CITY. THIS HAS |
| NOT BEEN COMPLETED. |
| |
| B. PALM BEACH DAY ACADEMY SHALL SUBMIT AN APPLICATION |
| TO THE ENGINEERING SERVICES DEPARTMENT FOR THE |
| REALIGNMENT OF THE TUXEDO AND COCOANUT LANES AND THE |
| RELOCATION OF ANY CITY UTILITIES. AFTER THE ENGINEERING |
| SERVICES DEPARTMENT APPROVAL, THE PALM BEACH DAY |
| ACADEMY SHALL, AT ITS OWN COST AND EXPENSE, REALIGN THE |
| INTERSECTION OF TUXEDO AND COCOANUT LANES AND RELOCATE |
| ANY AND ALL UTILITY LINES LOCATED WITHIN THE ABANDONED |
| RIGHT-OF-WAY. THE PALM BEACH DAY ACADEMY SHALL POST A |
| BOND TO THE CITY IN THE AGREED AMOUNT OF THE ESTIMATED |
| COSTS ASSOCIATED WITH THE RELOCATION OF THE ROADWAY AND |
| THE UTILITY LINES PRIOR TO THE RECORDATION OF THE PALM |
| BEACH DAY ACADEMY PLAT. THIS HAS NOT BEEN COMPLETED. |
| |
| C. IN THE EVENT THE UTILITIES ARE RELOCATED TO ANOTHER |
| AREA OF THE PALM BEACH DAY ACADEMY CAMPUS, THE PALM |
| BEACH DAY ACADEMY SHALL GRANT TO THE CITY A UTILITY |
| EASEMENT OVER, UNDER AND THROUGH SUCH AREA OF THE |
| CAMPUS. THIS HAS NOT BEEN COMPLETED. |
| |
| D. PALM BEACH DAY ACADEMY SHALL PROVIDE TO THE CITY |
| TEMPORARY UTILITIES AND DRAINAGE EASEMENTS OVER AND |
| ACROSS THE ABANDONED RIGHT-OF-WAY, IN FORM APPROVED BY |
| THE CITY ATTORNEY'S OFFICE, AT THE TIME OF THE |
| RECORDATION OF THE PALM BEACH DAY ACADEMY PLAT. THIS |
| HAS NOT BEEN COMPLETED. |
| |
| E. PALM BEACH DAY ACADEMY SHALL TENDER AND DELIVER |
| $24,000 TO THE CITY AS COMPENSATION FOR THE VALUE OF |
| THE RIGHT-OF-WAY AND ASSOCIATED DEVELOPMENT RIGHTS. |
| THIS HAS NOT BEEN COMPLETED. |
| |
| 4) REPEAT COMMENT: THE SURVEY INCLUDED WITH THE PERMIT |
| APPLICATION IS FROM 2010 AND DOES NOT REFLECT THE |
| CURRENT CONDITIONS, ESPECIALLY ON THE WESTERN HALF OF |
| THE SITE. AN ACCURATE RECENT SURVEY IS REQUIRED. |
| |
| 5) REPEAT COMMENT: THE INTERIM SITE LAYOUT REQUIRES A |
| MINIMUM OF 61 PARKING SPACES. THE CURRENTLY SUBMITTED |
| INTERIM PLAN ONLY SHOWS 59 SPACES. THE TWO SPACES ON |
| THE SOUTH SIDE OF THE BUILDING ARE BUS PARKING SPACES, |
| NOT REGULAR PARKING SPACES. |
| |
| 6) REPEAT COMMENT: SHEET G1.1 DOES NOT MATCH THE CIVIL |
| PLANS SUBMITTED AS PART OF THE PERMIT APPLICATION OR |
| THE PLANS SUBMITTED AS PART OF THE MINOR PLANNED |
| DEVELOPMENT AMENDMENT. ALL PLANS SHALL SHOW CONSISTENT |
| CONDITIONS AND BE APPROVED THROUGH THE MINOR PLANNED |
| DEVELOPMENT AMENDMENT PROCESS. |
| |
| 7) REPEAT COMMENT: ON SHEET A4.1, THE MECHANICAL SCREEN |
| WALL ELEVATION IS SHOWN AT 130 FEET, YET THE TOP OF THE |
| WALL IS ALSO 130 FEET. PLEASE CORRECT THE ELEVATION. |
| |
| 8) A RIGHT-OF-WAY PERMIT IS REQUIRED FOR THE WORK |
| WITHIN FLAGLER DRIVE, TUXEDO LANE AND COCOANUT LANE. |
| |
| 9) SEPARATE PERMITS, WITH PLANS, WILL BE REQUIRED FOR: |
| |
| A. LANDSCAPE |
| B. AWNINGS AND CANOPIES |
| C. SIGNS |
| D. PARKING AND SIDEWALKS |
| E. BICYCLE RACKS, BENCHES, FLAGPOLE, TRASH CANS AND |
| OTHER SITE AMENITIES |
| F. FENCES, WALLS AND GATES (TO INCLUDE THE SITE WALLS |
| AND RETAINING WALLS) - PLEASE NOTE THAT STAFF IS |
| UNCLEAR WHERE THE SPECIFIC WALLS AND FENCES WILL BE |
| LOCATED BASED ON LACK OF DETAIL ON THE SITE PLANS. THE |
| PLANS SHALL CLEARLY SHOW THE SETBACKS OF THE |
| WALLS/FENCES TO VERIFY THAT THEY DO NOT EXCEED THE |
| MAXIMUM HEIGHT. |
| G. SITE LIGHTING |
| H. THE PUBLIC ARE FIGURES ON TOP OF THE CANOPY. |
| |
| 10) PLEASE REMEMBER THAT DURING CONSTRUCTION THE |
| FOLLOWING SITE SECURITY ITEMS SHALL BE IMPLEMENTED: |
| |
| I. THE APPLICANT, AFTER SITE CLEARING AND PLACEMENT OF |
| CONSTRUCTION TRAILERS, SHALL INSTITUTE SECURITY |
| MEASURES TO REDUCE OR ELIMINATE OPPORTUNITIES FOR |
| THEFT. THE MANAGEMENT PLAN SHALL INCLUDE, BUT NOT BE |
| LIMITED TO, TEMPORARY LIGHTING, SECURITY PERSONNEL, |
| VEHICLE BARRIERS, CONSTRUCTION/VISITOR PASS, |
| REDUCE/MINIMIZE ENTRY/EXIT POINTS, ENCOURAGE |
| SUBCONTRACTORS TO SECURE MACHINERY AND TOOLS AT END OF |
| WORK DAY, FENCING WITH SCREENING, AND/OR ANY OTHER |
| MEASURE DEEMED APPROPRIATE TO PROVIDE A SAFE AND SECURE |
| WORKING ENVIRONMENT. |
| |
| II. THE SECURITY MANAGEMENT PLAN SHALL BE MAINTAINED |
| THROUGHOUT THE CONSTRUCTION PHASE OF THE PROJECT. |
| NON-COMPLIANCE WITH THE APPROVED PLAN SHALL RESULT IN A |
| STOP-WORK ORDER FOR THE ENTIRE PLANNED DEVELOPMENT. |
| |
| III. "NO TRESPASSING" SIGNS SHALL BE POSTED EVERY 500 |
| FEET AROUND THE PERIMETER OF THE CONSTRUCTION SITE. |
| |
| 11) PRIOR TO C.O. FOR THE ACADEMIC BUILDING, ANY |
| OFF-SITE SIGNAGE OR TRAFFIC CONTROL AIDES SHALL BE |
| INSTALLED BY THE PBDA. |
| |
| CONTACT ERIC SCHNEIDER @ (561) 822-1446. |
| |