Plan Review Notes
Plan Review Notes For Permit 15010981
Permit Number 15010981
Review Stop B
Sequence Number 2
Notes
Date Text
2015-03-06 08:24:59ADDITIONAL REVIEW AND INSPECTION NOTES.
  
 2/11/15, BUILDING INSPECTOR ART LANGE ISSUED A STOP
 WORK ORDER ON THIS JOB FOR WORK COMMENCING PRIOR TO
 ISSUANCE OF A PERMIT, A COMPLAINT WAS CALLED IN
 INDICATING THAT RAUL VARAS WAS IN THE UNIT AND WORK WAS
 ONGOING.
  
 2/12/15, VARAS IS ISSUED A CEASE AND DESIST ORDER BY
 FIELD INVESTIGATOR JEFF HOLLAND OF THE DBPR FOR
 CONTRACTING WITHOUT A LICENSE FOR PREVIOUS WORK.
  
 2/13/15 DISCUSSIONS I HAD WITH STUART AND THE ORIGINAL
 CONTRACTOR OF RECORD, MARK JENKINS, CGC1543481 REVEALED
 THEY WERE NOT ACQUAINTED WITH ONE ANOTHER PRIOR TO
 2/12/15 AND THAT VARAS HAD ORCHESTRATED THE SUBMITTAL
 OF THE ORIGINAL PERMIT APPLICATION AND THEREAFTER THE
 ORIGINAL REQUESTED CONTRACT, IT WAS APPARENT THAT
 STUART AND VARAS HAD CONTRACTED FOR THE WORK AS THE
 ORIGINAL CONTRACT WAS SIGNED BY VARAS AS CONTRACTOR AND
 STUART. JENKINS CONFIRMED ON 2/13/15, THAT VARAS WAS
 NOT HIS EMPLOYEE AND NOT AUTHORIZED TO SIGN CONTRACTS
 FOR HIM.
  
 2/17/15 A NEW APPLICATION AND CONTRACT WAS DELIVERED BY
 THE OWNER CAROL STUART AND RAUL VARAS . DOUG HARVEY AND
 I MET WITH THEM. THE APPLICATION AND CONTRACT WERE
 SIGNED BY CAROL STUART AND STEPHEN C. THOMAS,
 CGC1505934.THE APPLICATION WAS IN THE SAME FORM AS THE
 ORIGINAL APPLICATION AND VARAS EXPLAINED HE GOT THEM
 OFF THE INTERNET. HARVEY EXPLAINED TO STUART THAT VARAS
 IS AN UNLICENSED CONTRACTOR, THE CONTRACT SUBMITTED WAS
 DEFICIENT, AND THAT THE NEXT STEP IS A DISCUSSION WITH
 THOMAS. VARAS AND STUART LEFT.
  
 2/17/15 HARVEY AND I HAD A TELEPHONE DISCUSSION WITH
 THOMAS. THERE WAS SOME QUESTION AS TO HIS DESIRE FOR
 CONTINUED INVOLVEMENT IN THE PROJECT GIVEN THE C&D TO
 VARAS AND THE DEFICIENT CONTRACT VARAS SUBMITTED . HE
 INDICATED THAT VARAS HAD APPROACHED HIM IN THE MATTER.
  
 2/27/15 CHIEF PLUMBING INSPECTOR TIM LARGE ISSUED A
 STOP WORK ORDER FOR PLUMBING WORK IN PROGRESS WITHOUT A
 PLUMBING PERMIT. A COMPLAINT WAS CALLED IN INDICATING
 THRE WAS A PLUMBING EMERGENCY AT THE BUILDING. LARGE
 DETERMINED THE UNLICENSED AND UNPERMITTED PLUMBING WORK
 IN PROGRESS LED TO A LEAK WHICH EARLIER THAT DAY CAUSED
 DAMAGE TO THE UNIT AND SEVERAL OTHER ADJACENT UNITS.
  
 3/2/15, THOMAS INFORMED ME HE WILL WITHDRAW HIS
 APPLICATION.
  
 3/3/15 THOMAS AND STUART INFORMED ME THAT THOMAS WOULD
 REMAIN THE CONTRACTOR OF RECORD. I SCHEDULED A SITE
 MEETING WITH STUART, THOMAS, LARGE, AND HOLLAND FOR
 3/6/15 AT 9:30AM. THE PURPOSE OF THE MEETING WILL TO
 DETERMINE THE ALTERATION LEVEL OF THE WORK, THE EXTENT
 OF COMPLETED WORK, THE EXISTENCE OF CODE VIOLATIONS,
 AND THE CONTRACTORS WHO PERFORMED THE WORK.
  
 3/6/15 FBC 110.2 PRELIMINARY INSPECTION. SUBJECT TO THE
 LIMITATIONS OF F.S. CHAPTER 553, BEFORE ISSUING A
 PERMIT, THE BUILDING OFFICIAL IS AUTHORIZED TO EXAMINE
 OR CAUSE TO BE EXAMINED BUILDINGS, STRUCTURES AND SITES
 FOR WHICH AN APPLICATION HAS BEEN FILED.
 *****TO BE SUPPLEMENTED AFTER INSPECTION*****
  
 3/6/15 PRESENT AT 9:30 AM WITH ME WAS STUART, THOMAS,
 LARGE, AND HOLLAND. UPON INSPECTION, THE DETERMINATION
 WAS MADE THAT THE UNPERMITTED WORK IN PROGRESS
 CONSTITUTES A LEVEL II ALTERATION. THE WORK IN PROGRESS
 CONSISTS OF REPLACEMENT OF VARIOUS CABINETS, TOPS,
 PLUMBING & ELECTRICAL FIXTURES, AND FLOORING. WORK ALSO
 INCLUDES SOME RE-CONFIGURATION BY REMOVAL OF A DOOR AND
 SMALL PARTITION AT THE ENTRY TO THE EAST BED/BATH AREA,
 AND THE ALREADY COMPLETED RECONFIGURATION OF THE WEST
 BATHROOM TUB/SHOWER TO A SHOWER ELIMINATING THE TUB.
 THOMAS INDICATED HE WAS NOT RESPONSIBLE FOR ANY OF THE
 PREVIOUSLY COMPLETED WORK BUT THAT HE WILL BE
 RESPONSIBLE TO REPAIR ANY VIOLATIONS AND TO PERMIT AND
 COMPLETE THE WORK. ADDITIONALLY HE WILL AMEND THE
 APPLICATION TO INCLUDE THE REMOVAL OF THE PREVIOUSLY
 COMPLETED SHOWER RECONFIGURATION. STUART REPORTED THE
 SHOWER RECONFIGURATION WAS COMPLETED BY GEORGE
 HERNANDEZ WHOM SHE HIRED THROUGH VARAS IN LATE JANUARY
 OR EARLY FEBRUARY. SHE STATED THAT WORK WAS DONE AT
 THAT TIME. STUART COULD NOT SUBSTANTIATE THAT ANY OF
 THE WORK WAS DONE BY PROPERLY LICENSED ENTITIES. SHE
 INDICATED SHE HAD NO CONTRACT FOR THE SHOWER WORK. IT
 WAS NOTED UPON CLOSE INSPECTION BY LARGE THAT A JOINT
 IN AN EXISTING PLUMBING SUPPLY LINE IN THE WALL CAVITY,
 ADJACENT TO THE RECONFIGURED SHOWER AND ABOVE THE
 REMOVED WATER CLOSET, HAD COME LOOSE. STUART INDICATED
 THIS WAS THE SOURCE OF WATER DAMAGE TO HER UNIT AND
 SEVERAL OTHER UNITS. STUART FURTHER INDICATED THAT SHE
 REPORTED THE LOOSE JOINT TO THE POLICE AS AN ACT OF
 VANDALISM AND ALLEGED THAT AN UNKNOWN VANDAL CUT A
 SMALL HORIZONTAL HOLE IN THE WALL, FIT THEIR HANDS IN
 THE WALL AND PULLED A GLUED PVC JOINT APART BY APPLYING
 PRESSURE IN OPPOSITE VERTICAL DIRECTIONS. JENKINS
 DISCUSSED ISSUES RELATED TO CONTRACTING IN VIOLATION OF
 FS 489 WITH STUART. THE INSPECTION CONCLUDED AT
 APPROXIMATELY 10:00AM.
  
 STEVEN KENNEDY, CBO
 CHIEF PLANS EXAMINER
 (561) 805-6710
 [email protected]
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved