Date |
Text |
2015-03-06 13:40:50 | 1) NO WINDLOAD CALCULATIONS HAVE BEEN INCLUDED I THE |
| SUBMITTAL. PROVIDE WIND LOAD CALCULATIONS THAT INCLUDE |
| THE LUMINAIRE AND CAMERA INSTALLATION. WPB AMENDMENTS |
| TO THE FBC 107 |
| |
| 2) REVISE THE GROUNDING DETAIL FOR THE BROOKS PULL BOX |
| AND THE LIGHT POLES ON SHEET E-2 TO INDICATE THE |
| EQUIPMENT GROUNDING CONDUCTOR CONNECTING TO THE DRIVEN |
| GROUND ROD. NEC 250.32 |
| |
| 3) REVISE THE DETAILS FOR THE POLES THAT ARE PROPOSED |
| TO SHARE THE LOW VOLTAGE CAMERA WIRING WITH THE HIGH |
| VOLTAGE LIGHTING WIRING. |
| A) THE LIGHTH POLE DETAIL INDICATES A 1" PVC WITH |
| WIRING FOR LIGHTING ONLY, PLEASE CLARIFY. ARE THERE |
| CAMERAS INSTALLED ON THESE POLES? |
| B) THE SECURITY CAMERA DETAIL INDICATES AN ALUMINUM |
| CONDUIT FOR THE CAMERAS BUT ALSO INDICATES IN THE TITLE |
| OF THE DETAIL THESE POLES SHARE THE CIRCUITRY FOR THE |
| LIGHTING BUT DOES NOT INDICATE ANY DETAIL AS TO HOW. |
| C) THE 5FT SECURITY CAMERA POLE DETAIL INDICATES A 1" |
| PVC WITH PULL BOX AND NOTES THAT THERE IS A 120V GFI |
| MOUNTED INSIDE A STAINLESS STEEL CAMERA CABINET BUT |
| AGAIN DOES NOT INDICATE HOW THE POWER AND LIGHTING |
| CIRCUITRY ARE PROPOSED TO BE INSTALLED. |
| THERE IS NO MENTION OF THE ROUTING OR INSTALLATION OF |
| THE SPECIFIC WIRING METHODS AND HOW THEY WILL BE |
| SEPARARTED OR HOW THE BONDING AND GROUNDING WILL BE |
| ACCOMPLISHED. ALL THREE OF THESE DETAILS NEED TO BE |
| REVISED TO SHOW MORE DETAIL THE INSTALLATION AND |
| SEPARATION OF SYSTEMS WIRING AND THE GROUNDING AND |
| BONDING IN ACCORDANCE WITH THE NEC. |
| |
| 4) PROVIDE MANUFACTURER PRODUCT APPROVALS ON ALL CAMERA |
| AND RELATED EQUIPMENT SUCH AS POWER SUPPLIES, STAINLESS |
| STEEL ENCLOSURES AND THE CAMERAS THEMSELVES. |
| |
| 5) THE INTERIOR OF AN UNDERGROUND RACEWAY SHALL BE |
| CONSIDERED A WET LOCATION. ALL CONDUCTORS WITHIN THE |
| RACEWAY SHALL BE LISTED ACCORDINGLY. SUITABILITY FOR |
| INSTALLATION AND USE IN CONFORMITY WITH THE PROVISIONS |
| OF THIS CODE. INDICATE ON THE PLAN AND PROVIDE A |
| SUBMITTALE OF THE FIBER OPTIC CABLE PROPOSED TO BE |
| INSTALLED IN AN UNDERGROUND RACEWAY. NEC 110.3(B) |
| |
| 6) INDICATE HOW THE PROPOSED EXTERIOR LIGHTING IS |
| INTENDED TO COMPLY WITH THE FBC-ENERGY SECTION 505.2.4 |
| EXTERIOR LIGHTING CONTROLS. |
| |
| DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421, |
| 561-805-6717 OR [email protected] |