Plan Review Notes
Plan Review Notes For Permit 15010651
Permit Number 15010651
Review Stop B
Sequence Number 4
Notes
Date Text
2015-06-13 15:53:37****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
 EOR: THOMAS ROGERS, PE (ONM&J)
 ARCHITECT: WILLIAM A. HANSER (LEO A DALY)
  
 PLEASE CONTACT ME AS SOON AS POSSIBLE IF YOU WISH TO
 HAVE THIS REVIEW PASSED WITH PROVISO, OR IF REVISED
 SHEETS A000 AND S9.1 ARE AVAILABLE FOR IMMEDIATE
 SUBMISSION.
  
 1. THRESHOLD INSPECTION PLAN IS PENDING DECISION FROM
 BUILDING OFFICIAL AND CHIEF BUILDING INSPECTOR; PLAN
 HAS A DATE OF JUNE 22.
  
 2. INFORMATIONAL ONLY - AS THIS IS A THRESHOLD JOB,
 THREE SETS OF ALL DOCUMENTS REQUIRED.
  
 3-7. OK
  
 8A. FBC 705.8, PREVIOUS COMMENT WAS PARTIALLY
 ADDRESSED. THE DIMENSION FROM THE PROPOSED GARAGE TO
 ASSUMED PROPERTY LINE HAS BEEN PROVIDED ON THE PLAN AS
 30FT. SEE FBC 705.3:
  
 WHERE A NEW BUILDING IS TO BE ERECTED ON THE SAME LOT
 AS AN EXISTING BUILDING, THE LOCATION OF THE ASSUMED
 IMAGINARY LINE WITH RELATION TO THE EXISTING BUILDING
 SHALL BE SUCH THAT THE EXTERIOR WALL AND THE OPENING
 PROTECTION OF THE EXISTING BUILDING MEET THE CRITERIA
 AS SET FOR THE IN SECTIONS 705.5 AND 705.8.
  
 REVISE THE PLAN TO SHOW COMPLIANCE FOR THE EXISTING
 BUILDING (APPEARS TO BE 12 FT FROM THE ASSUMED PROPERTY
 LINE). THIS APPLIES ONLY TO THE PORTIONS OF THE
 BUILDINGS WHICH DIRECTLY FACE THE OTHER BUILDING.
  
 IF ASSUMED PROPERTY LINE IS RELOCATED, SHOW COMPLIANCE
 FOR EACH BUILDING AS APPLICABLE (FBC 705.5 AND 705.8).
  
 3RD REVIEW, ARCHITECT HAS A RESPONSE WHICH REFERS TO A
 NEW ASSUMED PROPERTY LINE AND REVISED INFORMATION, BUT
 THE SAME SHEET (AS000 DATED 5/18/2015 REVISION 3) WAS
 SUBMITTED. IT APPEARS THAT THE ARCHITECT ADDRESSED THE
 COMMENT AND REVISED THE SHEET BUT THE SHEET WAS NOT
 SUBMITTED.
  
 IN THE EVENT THAT IS NOT THE CASE AND THE PREVIOUS
 COMMENT WAS NOT CLEAR; TO CLARIFY, EACH BUILDING
 (PROPOSED GARAGE AND EXISTING CONVENTION CENTER) IS TO
 SHOW COMPLIANCE TO THE ASSUMED PROPERTY LINE BETWEEN
 THE TWO BUILDINGS. LINE ON THE PLAN DATED 5/18 IS SHOWN
 30FT FROM THE PROPOSED GARAGE, BUT ARCHITECT REFERS IN
 THE RESPONSE LETTER TO AN EXCEPTION FOR PARKING GARAGES
 WHICH ALLOWS UNLIMITED OPENINGS IF THE DISTANCE IS
 GREATER THAN 10 FT. THEREFORE IT APPEARS THAT THE LINE
 COULD BE RELOCATED TO SLIGHTLY OVER 10FT, THEN IT
 APPEARS THAT THE DISTANCE FROM THE EXISTING CONVENTION
 CENTER WOULD THEN BE OVER 30FT. PLEASE REVISE THE PLAN
 ACCORDINGLY AND INCORPORATE THE EXCEPTION INTO THE
 PLAN.
  
 9-13. OK
  
 14. PER CONVERSATION WITH ENGINEER, PLEASE REVISE S9.1
 SECTION 1, TO SHOW CONTINUOUS WATERPROOFING AT THE
 FOOTING, FBC 1805.3.3.
  
 3RD REVIEW, THE RESPONSE LETTER STATES THAT THIS WAS
 REVISED BUT THE SAME SHEET DATED 5/18/15 WAS SUBMITTED
 (THEREFORE THE DETAIL WAS NOT REVISED). IT APPEARS THAT
 THE SHEET WAS REVISED BUT NOT SUBMITTED, AS WAS
 POSSIBLY THE CASE WITH SHEET AS000.
  
 3RD REVIEW, WATERPROOFING SPEC SHEETS WERE SUBMITTED
 BUT LACK THE SHOP DRAWING REVIEW STAMP OR COVER LETTER.
 THIS SUBMITTAL IS ACCEPTED BUT IN THE FUTURE PLEASE
 HAVE ALL SUBMITTALS INCLUDE A SHOP DRAWING REVIEW STAMP
 OR LETTER. PLEASE NOTE THAT THE RESPONSE LETTERS ARE
 NOT TYPICALLY INCORPORATED INTO THE PERMIT RECORD.
  
 15. OK
  
 16. ADVISORY ONLY - CONSTRUCTION HOURS ARE 7AM - 7PM
 MONDAY THROUGH FRIDAY; 8AM - 8PM WEEKENDS, CITY OF WEST
 PALM BEACH MUNICIPAL CODE SECTION 34-72. A WRITTEN
 EXCEPTION MAY BE GRANTED BY THE BUILDING OFFICIAL;
 PLEASE SUBMIT ANY SUCH REQUESTS (IF NEEDED) TIMELY TO
 [email protected], CC [email protected] AND [email protected].
  
 18. SEE PREVIOUS LIST: PER CONTRACTOR, NO ELECTRICAL
 WORK IS A PART OF THIS PHASE. BE ADVISED THAT, PRIOR TO
 FIRST POUR, THE BUILDING INSPECTOR WILL REQUIRE
 INFORMATION FROM THE ELECTRICAL ENGINEER OR ARCHITECT
 WHICH VERIFIES THAT BUILDING GROUNDING IS NOT A PART OF
 THIS PHASE. IN ORDER TO AVOID FIELD DELAYS, DESIGNER IS
 ENCOURAGED TO SUBMIT THIS INFORMATION AT THIS TIME.
  
 VERIFICATION THAT LIGHTNING PROTECTION IS NOT A PART OF
 THE FOUNDATION PERMIT WILL ALSO BE REQUIRED TO BE
 SUBMITTED TO THE BUILDING INSPECTOR PRIOR TO FIRST
 POUR.
  
 3RD REVIEW, PER ARCHITECT, SHEETS F EE201 AND F EE 202
 WERE TO BE SUBMITTED TO ADDRESS THIS COMMENT. THEY WERE
 NOT INCLUDED IN THIS SUBMISSION. IT IS AT CONTRACTOR'S
 RISK THAT AN ELECTRICAL PERMIT IS NOT ISSUED WITH THE
 BUILDING PERMIT. BASED ON THE ELECTRICAL REVIEWER'S
 PRELIMINARY CURSORY REVIEW OF THE ELECTRICAL AND
 LIGHTNING PROTECTION PLANS PROVIDED WITH THE BUILDING
 PERMIT 15060144, IT APPEARED THAT SOME ELECTRICAL OR
 LIGHTNING PROTECTION WORK MAY BE REQUIRED IN THIS
 PHASE.
  
  
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved