2015-01-20 09:05:451) INDICATE ON THE PLANS THE TYPE OF PIPING TO BE
 INSTALLED ( UNDERGROUND & ABOVEGROUND) FOR THE POOL
 HEATER AND THE GENERATOR. WPB AMEND. TO FBC SEC.
 107.2.1.
 2) SUBMIT DETAILS AS TO HOW THE APPLIANCES WILL BE
 ANCHORED TO COMPLY WITH THE WINDLOAD REQUIREMENTS FOR
 THIS WIND ZONE. 2010 FBC, RESIDENTIAL CODE SEC.G2404.6.
 3) INDICATE IF THE STRUCTURE IS LOCATED IN FLOOD HAZARD
 AREA. IF APPLICABLE, THE GAS EQUIPMENT SHALL BE LOCATED
 AT OR ABOVE THE DESIGN FLOOD ELEVATION PER THE 2010
 FBCR SEC. G2404.7 & R322.
 4) INDICATE THE BTU LOAD OF EACH APPLIANCE ON THE
 DRAWING AND THE TOTAL BTU LOAD ON THE SYSTEM. 2010 FBCR
 SEC.G2413.2.
 5) INDICATE ON THE PLANS THE LONGEST DEVELOPED LENGTH
 OF PIPING FROM THE POINT OF DELIVERY TO THE MOST REMOTE
 OUTLET.2010 FBCR SEC. G2413..4.1.
 6) SUBMIT A SITE PLAN/SURVEY THAT SHOWS THE HOUSE AND
 PROPERTY LINES AND THE LOCATION OF THE GENERATOR AND
 POOL HEATER IN RELATION TO THE STRUCTURE.THE GENERATOR
 SHALL BE A MINIMUM OF 5 FEET FROM THE EXTERIOR WALL OF
 THE STRUCTURE PER NFPA 37 SEC.4.1.4.
 7) SUBMIT A SITE PLAN/SURVEY THAT SHOWS THE DISTANCE OF
 THE POOL HEATER AND GENERATOR FROM THE PROPERTY
 LINES.WPB AMEND. TO 2010 FBC SEC. 107.2.1.
 8) INDICATE THE DELIVERY PRESSURE ( PSI) OF THE GAS ON
 THE PLANS.WPB AMEND. TO 2010 FBC SEC. 107.2.1.
 9) SUBMIT 2 COPIES OF THE APPLICABLE SIZING TABLE FROM
 CHAPTER 24 OF THE 2010 FBCR FOR EACH TYPE OF PIPE
 MATERIAL BEING INSTALLED.2010 FBCR SEC.G2413.3.
 10) SHOW THE LOCATION OF ANY MEDIUM PRESSURE
 REGULATORS. WPB AMEND. TO 2010 FBC SEC.107.2.1.
 11) INDICATE THE TYPE OF GAS ( LP OR NATURAL).WPB
 AMEND.TO 2010 FBC SEC.107.2.1.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved