2015-01-15 05:13:03 | 1) THE REPLACEMENT WATER HEATER IS 39,100 BTU'S MORE | | THAN THE EXISTING GAS WATER HEATER. SUBMIT A COMPLETE | | GAS RISER DRAWING SHOWING THE BTU LOAD OF EACH | | CONNECTED APPLIANCE TO THE GAS SYSTEM, THE TOTAL BTU | | LOAD ON THE SYSTEM, THE TOTAL DEVELOPED LENGTH FROM THE | | GAS METER TO THE MOST REMOTE OUTLET, AND THE PSI OF THE | | GAS BEING DELIVERED TO THE APPLIANCES.THIS WILL ALLOW | | ME TO CHECK THE ENTIRE SYSTEM TO MAKE SURE IT IS | | PROPERLY SIZED AND WILL NOT CREATE A CODE VIOLATION OR | | SAFETY HAZARD. WPB AMEND. TO 2010 FBC SEC. 107.2.1. | | | | PLUMBING PLAN REVIEW | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | 561-805-6692 | | [email protected] | | | | | 2015-01-14 11:49:29 | ROUTED TO PLUMBING LESS THAN $5000 |
|