2015-01-31 13:25:27 | 1/31/2015 | | PROJECT: FRED GLADSTONE | | PERMIT#: 12050519 REVISION TRACKING #15010085 | | CODE: 2008 EDITION OF THE NEC, 2010 EDITION OF THE FBC | | ,2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1, | | ADMINISTRATION, 2012 FBC SUPPLEMENTS. | | 1ST ELECTRICAL PLAN REVIEW | | ACTION: APPROVED WITH EXCEPTION | | | | 1) SHEET E-E404 ADD THE FOLLOWING NOTETO THE POWER PLAN | | NOTES: | | NEC ARTICLE 680, PART V. FOUNTAINS | | NEC ARTICLE 680.50 THE PROVISIONS OF PART I AND PART V | | OF ARTICLE 680 SHALL APPLY TO ALL PERMANENTLY INSTALLED | | FOUNTAINS AS DEFINED IN 680.2. APPLY THE PROVISIONS OF | | THIS ARTICLE TO THE FOUNTAIN INSTALLATION, AND ALL | | RELATED EQUIPMENT, POWER OUTLETS AND LIGHTING. | | | | DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421, | | 561-805-6717 OR [email protected] | | | | | | |
|