Date |
Text |
2015-08-07 11:02:12 | FAILED |
| |
| PLEASE PROVIDE WRITTEN RESPONSE TO COMMENTS. |
| |
| 1) THE BUILDING APPEARS TO BE TALLER THAN THE 110 FEET |
| PERMITTED BY THE TRADITIONS PHASE II APPROVALS |
| (ORIGINALLY ORD. NO. 4110-08, CURRENT RES. NO. 49-13). |
| THE WEST PALM BEACH ZONING AND LAND DEVELOPMENT |
| REGULATIONS STATE, "...THE HEIGHT SHALL BE MEASURED AS |
| THE VERTICAL DISTANCE FROM THE AVERAGE ELEVATION OF THE |
| FINISHED GRADE OF THE BUILDING TO THE HIGHEST POINT OF |
| THE TOP OF THE STRUCTURE OF A FLAT ROOF...". SECTION |
| 94-306 ALLOWS CERTAIN HEIGHT EXCEPTIONS AS FOLLOWS: |
| "HEATING, VENTILATION, AND AIR CONDITIONING EQUIPMENT; |
| CHURCH STEEPLES, BELL TOWERS, FLAG POLES, CHIMNEYS, |
| PARAPETS, STAIR ENCLOSURES, TANKS, DECORATIVE FEATURES, |
| ELEVATOR HOISTWAYS OR EQUIPMENT, TELEVISION OR RADIO |
| ANTENNAS, AND RELATED MECHANICAL OR FUNCTIONAL FEATURES |
| MAY EXCEED DISTRICT HEIGHT REQUIREMENTS BY TEN |
| PERCENT." THE ELEVATION DRAWINGS SHALL BE AMENDED TO |
| INCLUDE THE FOLLOWING DIMENSION LINES: |
| |
| A. THE BASE MEASURE SHALL BE FROM THE AVERAGE ELEVATION |
| OF THE FINISHED GRADE OF THE BUILDING. IT APPEARS THAT |
| THE ELEVATIONS PROVIDED ARE USING FINISHED FLOOR OR TOP |
| OF THE SLAB. THE STRUCTURAL DRAWINGS INDICATE THAT THE |
| FOUR (4) INCH SLAB IS ON GRADE, NOT AT GRADE, WHICH |
| WOULD MAKE IT FOUR (4) INCHES HIGHER THAN THE AVERAGE |
| ELEVATION OF THE FINISHED GRADE (THIS IS ALSO INDICATED |
| ON THE BUILDING SECTION DRAWINGS). PLEASE CLARIFY. |
| B. EXTEND THE DIMENSION LINE TO THE HIGHEST POINT OF |
| THE BUILDING. STAFF HAS SCALED THE DRAWING AND IT |
| APPEARS THAT THE HIGHEST POINTS ON THE BUILDING ARE 123 |
| FEET. SECTION 94-306 ALLOWS THE HEIGHT EXCEPTION FOR |
| THIS BUILDING TO EXTEND TO 121 FEET (HEIGHT WAIVER TO |
| 110 FEET X 10% = 11 FEET ADDITIONAL HEIGHT EXCEPTION). |
| |
| 2) PLEASE CLARIFY IF THE RETAINING WALL IS INCLUDED AS |
| PART OF THIS PERMIT. THE SITE AND CIVIL PLANS SHOW THE |
| MAJORITY OF THE RETAINING WALL AREA AS PART OF THIS |
| PERMIT. THE FOUNDATION PLAN SHOWS MOST OF THE WALL NOT |
| INCLUDED. PRESUMABLY THE BALANCE OF THE RETAINING WALL |
| WOULD BE INCLUDED WITH THE DINING ROOM PERMIT. WHY |
| SPLIT UP THE RETAINING WALL AND NOT BUILD IT UNDER ITS |
| OWN PERMIT? |
| |
| 3) THE NEW RETAINING WALL IS SHOWN IN DIFFERENT |
| LOCATIONS ON THE PLANS LISTED BELOW. PLEASE EXPLAIN WHY |
| DIFFERING WALL LOCATIONS ARE SHOWN. |
| |
| COTLEUR & HEARING PLANS |
| MICHAEL B. SCHORAH & ASSOCIATES, INC. PLANS |
| ONM&J PARTIAL FOUNDATION PLANS |
| PERKINS EASTMAN ARCHITECTURAL PLANS |
| |
| 4) THE LANDSCAPE PLANS CALL FOR LITTORAL PLANTING TO |
| THE WEST OF THE OVERLOOK PORTION OF THE RETAINING WALL. |
| PLEASE EXPLAIN HOW THIS WILL OCCUR GIVEN THE DEPTH AND |
| SLOPE THAT ARE BEING PROPOSED. |
| |
| 5) THE SITE PLANS SHOW A DIFFERENT ORIENTATION FOR THE |
| BICYCLE RACK AND AREA BETWEEN THE BUILDINGS THAN THE |
| APPROVED PLANS. THE CHANGES SHALL BE REFLECTED ON A |
| MINOR PD AMENDMENT. PLEASE NOTE THAT MORSELIFE |
| CURRENTLY HAS ONE UNDER REVIEW THAT COULD BE MODIFIED |
| TO INCLUDE THE CHANGES. |
| |
| 6) SHEET G101 SHOWS NOTE REFERENCING A 17 FOOT CLEAR |
| FIRE TRUCK ACCESS ROAD (SOUTH OF POOL WALL). THE |
| APPROVED SITE PLAN SHOWS THIS AS A 20 FOOT WIDE |
| DRIVEWAY. PLEASE CORRECT SHEET G101. THIS CHANGE IS |
| ALSO SHOWN ON SHEET L101 |
| |
| 7) SHEET C101 SHOWS THE 20 FOOT FIRE DEPARTMENT ACCESS |
| DRIVE ON THE EAST SIDE OF THE BUILDINGS AS NOT INCLUDED |
| WITH THE CONSTRUCTION THE INITIAL TOWER. THIS WAS A |
| REQUIREMENT OF THE FIRE DEPARTMENT TO SERVICE THE |
| BUILDING AND THUS SHALL BE PROVIDED FOR PHASE 1. |
| |
| 8) THE PARKING LOT, CONSTRUCTION ACCESS ROADWAY AND |
| DRIVE, IRRIGATION, LANDSCAPING, SITE LIGHTING, |
| GENERATOR BUILDING, BICYCLE RACKS, COMPACTOR ENCLOSURE, |
| COOLING TOWER AREA, AND FENCES/GATES REQUIRE SEPARATE |
| PERMIT SUBMITTALS, WITH PLANS. PLEASE DO NOT RESUBMIT |
| THESE SHEETS. PLEASE NOTE THAT THE ROW OR PARKING TO |
| THE NORTH OF THE 20 FOOT FIRE DEPARTMENT ACCESS AREA |
| SHALL BE TERMINATED BY THE REQUIRED TREE IN PHASE 1. |
| |
| 9) TREE ALTERATION PERMIT IS REQUIRED PRIOR TO THE |
| APPROVAL OF THE TEMPORARY ACCESS DRIVE TREE REMOVAL. |
| |
| 10) NOTE: THE FUTURE TRACT LINE DOES NOT MATCH UP WITH |
| THE DOORWAY AS SHOWN ON SHEET L101. THE FUTURE TRACT |
| LINE SHALL NOT CUT THROUGH THE CORRIDOR AT AN |
| UNPROTECTED POINT. |
| |
| 11) PLEASE REMEMBER THE DEADLINE FOR THE PLAT APPROVAL |
| APPROVED BY ROBERT BROWN, BUILDING OFFICIAL. |
| |
| 12) PLEASE NOTE THAT THE TRADITIONS PHASE II SHALL HAVE |
| MET THE COMMENCEMENT OF DEVELOPMENT DATE OF NOVEMBER 3, |
| 2015, IN ACCORDANCE WITH ITS FINAL EXTENSION. |
| |
| CONTACT ERIC SCHNEIDER @ (561) 822-1446. |
| |
| |