Date |
Text |
2015-06-10 08:46:11 | 3RD REVIEW: FBC 2010 MECHANICAL |
| |
| 1) SHEET M1.02 & M4.00: PROVIDE VENTILATION |
| CALCULATIONS FOR THE CORRIDOR AND ELEVATOR LOBBY ON THE |
| SOUTH END OF THE BUILDING, AND SHOW A MEANS ON THE |
| PLAN.- TABLE 403..3 FMC-10 |
| 2) M4.01: PROVIDE A VESTIBULE FOR THE MAINTENANCE ROOM |
| PER SECTION 305.3.2 FBC-10 FUEL GAS, OR SUBMIT SPECS |
| FOR THE HEATER SHOWING COMPLIANCE WITH SECTION 305.3.2 |
| (EXCEPTION) FBC-10 FUEL GAS. |
| 3) M4.01: THE L1 INTAKE OPENING, AND THE COMBUSTION AIR |
| INTAKE FOR THE POOL HEATER MUST BE RELOCATED A MINIMUM |
| 10' AWAY FROM THE PARKING AREA PER SECTION 401.4.1 |
| FMC-10 MECH. |
| 4) M4.02: INDICATE CONTROLS OPERATION AND SUPERVISION |
| FOR THE RTU DUCT SMOKE DETECTORS- SECTIONS 606.4 AND |
| 606.4.1 FMC-10 MECH: NOTE THEY ARE NOT SHOWN IN THE FA |
| SYSTEM RISER- SEE SHEET E-5.03. PLEASE PROVIDE THE |
| CORRECT NUMBER LABELS ON THE SHAFT DETAIL FOR RTU'S |
| 2,3, & 4. |
| 5) M4.04 & M4.05: THE LOCATION OF THE ROOF HATCH IS NOT |
| SHOWN. PLEASE SUBMIT A FL. PRODUCT APPROVAL OR |
| MIAMI-DADE NOA FOR THE UNIT, AND PROVIDE DETAILS FOR |
| THE ROOF LADDER SHOWN ON SHEET A5.00. |
| 6) AC LOAD CALCULATIONS: A) CALCULATIONS FOR RTU'S 1-5 |
| NOT SUBMITTED. B) THE FITNESS CENTER IS CALCULATED AT |
| APPROXIMATELY 3-TON COOLING, HOWEVER THE EQUIPMENT |
| SCHEDULE IS INDICATING A 5-TON SYSTEM- SHEET M1.02. |
| 7) ENERGY CALCULATIONS: A) AHU-6 IS LISTED AT 34.4 BTUH |
| IN THE CALCS AND 57.5 IN THE SCHEDULE. B) AHU-4 IS |
| LISTED AS 57.5 IN THE CALCS AND 23.4 IN THE SCHEDULE. |
| C) AHU-4A NOT IN THE CALCS. |
| 8) PLEASE PROVIDE AN EQUIPMENT SCHEDULE FOR THE FIRE |
| DAMPERS AND FIRE/SMOKE DAMPERS: INCLUDE MAKES AND |
| MODELS, FIRE-RESISTANCE RATINGS. SUBMIT SPECS AND |
| PROVIDE TYPICAL INSTALLATION DETAILS ON THE PLAN. |
| |
| CHRISTOPHER COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |
| |