Plan Review Notes
Plan Review Notes For Permit 14090256
Permit Number 14090256
Review Stop ENG
Sequence Number 1
Notes
Date Text
2014-09-26 09:28:31ENGINEERING/PUBLIC WORKS DEPT.
  
 AS MENTIONED DURING THE PPRC REVIEW, AN ENGINEERING
 DEVELOPMENT PERMIT APPLICATION IS REQUIRED FOR THIS
 PROJECT. CONSTRUCTION DETAILS OF THE WATER, SEWER,
 STORMWATER, TRAFFIC CIRCULATION, AND SOLID WASTE
 COLLECT WILL BE REVIEWED AS PART OF THAT APPLICATION
 PROCESSES. THE APPLICATION FORM AND CITY STANDARD
 CONSTRUCTION DETAILS CAN BE DOWNLOADED AT
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/
  
 1. INDICATE THE LOCATIONS OF THE DUMPSTERS INTENDED TO
 BE SERVICE BY THE CITY OF WEST PALM BEACH SANITATION
 DEPARTMENT. DUMPSTERS MUST BE EASILY ACCESSIBLE BY THE
 CITY EQUIPMENT AND MANPOWER. INCLUDE AN ESTIMATE OF THE
 SOLID WASTE YARDAGE ANTICIPATED TO BE GENERATED BY THE
 EXPANDED FACILITY.
  
 2. DEMONSTRATE THAT THE PROJECT WILL PROVIDE ADEQUATE
 DRAINAGE AND STORMWATER MANAGEMENT. COMPLIANCE WITH
 CHAPTER 40E-4 WILL DEMONSTRATE COMPLIANCE WITH THIS
 PROVISION [SECTIONS 90-201, 94-35(C )(11), AND 94-307
 OF THE CODE OF ORDINANCES]. THE PROPOSED WET DETENTION
 LOCATIONS DO NOT MEET SFWMD?S DIMENSIONAL/SIZE CRITERIA
 FOR WET DETENTION. THE CALCULATIONS SHOULD DEMONSTRATE
 THAT THE RUNOFF WILL ACTUALLY BE DETAINED IN THE DRY
 DETENTION AREAS (RATHER THAN IN THE CANALS AND DITCHES)
 IF THEY ARE CONSIDERED TO PROVIDE WATER QUALITY
 TREATMENT. THE DESIGN ALSO APPEARS TO ALLOW UNTREATED
 RUNOFF TO ENTER THE PERIMETER CANAL FROM THE OUTSIDE
 LANE OF THE PROPOSED ACCESS ROAD.
  
 3. SHOW THAT ALL POTABLE WATER, STORMWATER, AND
 SANITARY SEWER CROSSINGS MEET THE SEPARATION
 REQUIREMENTS OF RULES 62-555.314 AND 62-604 FAC
  
 4. PLEASE CLARIFY WHETHER OR NOT THE PLANT SUPPLY WATER
 IS POTABLE OR NON-POTABLE.
  
 5. SEE THE FIRE DEPARTMENT COMMENTS FOR THE
 REQUIREMENTS FOR FIRE SUPPLY LINES, WHICH WILL INCLUDE
 THE PROPOSED POTABLE WATER LINE IF A SEPARATE FIRE LINE
 IS NOT PROVIDED.
  
 6. INDICATE THE MATERIAL PROPOSED FOR THE NEW POTABLE
 WATER, SANITARY, AND STORMWATER LINES. WATER LINES MUST
 MEET THE REQUIREMENTS OF RULE 62-555.340 FAC.
  
 7. REVISE THE PLANS TO MEET THE DOUBLE VALVE
 REQUIREMENTS AND IDENTIFY THE SOURCE OF WATER. SHOW THE
 SIZE, LOCATION OF METER, BACKFLOW PREVENTERS ON THE
 PLANS. (SECTIONS 90-32 AND 90-33 OF THE CODE OF
 ORDINANCES)
  
 8. SUBMIT A HYDRAULIC ANALYSIS OF THE PROPOSED WATER
 DISTRIBUTION SYSTEM.
  
 9. REVISE THE PLANS TO INCLUDE APPLICABLE CITY
 ENGINEERING STANDARD DETAILS. INDICATE THE YARD PIPING
 DESIGN STANDARDS (MINIMUM COVER, HORIZONTAL AND
 VERTICAL CLEARANCES), AND WHICH JOINTS ARE TO BE
 MECHANICALLY RESTRAINED.
  
 10. INDICATE WHERE THE RUNOFF FROM THE ROOF DRAINS WILL
 BE DIRECTED.
  
 11. THE SUBMITTED DESIGN PLANS WERE NOT SIGNED OR
 SEALED BY A LICENSED PROFESSIONAL (ARCHITECT, CIVIL
 ENGINEER, AND/OR LANDSCAPE ARCHITECT). PLEASE SUBMIT
 SIGNED AND SEALED PLANS. (FAC 61G15-23.002, FS 481.221
 AND 481.321)
  
 12. THE SUBMITTED PLAN SET WAS MISSING PAGES C-PGD 13,
 14, AND 16 AS WELL AS PAGE YPP-21.
  
 KELLY CRANFORD, P.E.
 LAND DEVELOPMENT ENGINEER
 ENGINEERING & PUBLIC WORKS DEPARTMENT
 CITY OF WEST PALM BEACH
 [email protected]
 561-494-1098 (OFFICE)
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved