2014-10-27 16:13:30 | ** FAILED ** |
| |
| PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE |
| COMMENTS IN WRITING AND/OR ON THE PLANS WHERE |
| APPLICABLE: |
| |
| 1.) REPEAT COMMENT (7/2/14): A NEW A/C UNIT HAS BEEN |
| DETECTED IN THE FLOOR PLANS. PROVIDE AN UPDATED SURVEY |
| OF THE PROPERTY AND ILLUSTRATE THE LOCATION OF THE A/C |
| UNIT IN RELATIONSHIP TO THE PROPERTY LINE(S). |
| |
| 2.) REPEAT COMMENT (7/2/14): THE A/C UNIT SHALL NOT |
| PROJECT MORE THAN 4 FT. INTO ANY SETBACK. THE SETBACK |
| OF THE PROPOSED A/C UNIT CANNOT BE DETERMINED WITHOUT A |
| SURVEY OF THE PROPERTY. (ZLDR S.94-305(B)(4)) |
| |
| 3.) REPEAT COMMENT (7/2/14): THE VALUE OF THE |
| CONSTRUCTION ($28,000) EXCEEDS 50 PERCENT OF THE |
| STRUCTURE'S VALUE ($31,348 IN 2013 AND $52,720 IN 2014) |
| ACCORDING TO THE P.B.C. PROPERTY APPRAISER'S OFFICE; |
| THEREFORE, PURSUANT TO SECTION 94-441(C)(2) OF THE |
| ZONING AND LAND DEVELOPMENT REGULATIONS (ZLDR), THE |
| LANDSCAPE ON THE SITE SHALL BE IN COMPLIANCE WITH ALL |
| APPLICABLE REGULATIONS FOUND IN ARTICLE XIV OF THE |
| ZLDR. IF THE SITE CONFORMS TO ARTICLE XIV, THEN TWO (2) |
| COPIES OF A LANDSCAPE PLAN DEMONSTRATING COMPLIANCE |
| SHALL BE INCLUDED WITH THE PERMIT RE-SUBMITTAL. IF THE |
| SITE DOES NOT CONFORM TO ARTICLE XIV, THEN PRIOR TO THE |
| ZONING APPROVAL OF THIS PERMIT A SEPARATE LANDSCAPE |
| PERMIT SHALL BE SUBMITTED SHOWING MATERIAL TO BRING THE |
| SITE INTO CONFORMITY. |
| |
| 4.) THE LATEST REVISION, SHOWING A DIFFERENT LOCATION |
| FOR THE PROPOSED A/C UNIT IS NOT CONSISTENT WITHIN THE |
| FLOOR PLANS; THERE SEEMS TO BE MORE THAN ONE (1) |
| POSSIBLE LOCATION FOR THE A/C UNIT. PLEASE ADDRESS FOR |
| CONSISTENCY. |
| |
| PLEASE NOTE THAT ANY CHANGES ON THE RESUBMITTED PLANS |
| MAY RESULT IN ADDITIONAL COMMENTS. CONTACT LINDA LOUIE |