Date |
Text |
2014-03-18 13:15:32 | 1- PLEASE CLEARLY INDICATE COMPLIANCE WITH THE REQUIRED |
| SETBACK, AS MEASURED FROM THE BACK OF CURB CLOSER TO |
| THE BUIDLING FACADE. |
| 2- DRAWINGS INDICATE A POLE TO REMIAN ON THE NW CORNER |
| OF 6TH STREET AND OLIVE. IS THERE ANY REASON WHY THIS |
| POLE CANNOT BE REMOVED? |
| 3- BACK FLOW PREVENTORS LOCATED OUTSIDE THE LOADING |
| AREA SHALL BE RELOCATED. PROPOSED LOCATION WILL |
| PRECLUDE ANY LANDSCAPE TO BE PLANTED AT THAT LOCATION, |
| EXPOSIGN THE PARKING GARAGE FACADE. |
| 4- PHASE II INDICATES THE BUS STOP ON DIXIE HWAY TO BE |
| RELOCATED. WHERE IS IT GOING? |
| 5- PLEASE INCLUDE DETAILS ON THE EXISTING STREETSCAPE |
| ON OLIVE AVENUE AND HOW IT IS GOING TO BE MODIFIED WITH |
| THE PROJECT. THE GENERAL STREETSCAPE DESIGN ON OLIVE |
| SHALL REMAIN CONSISTENT WITH THE REST OF THE STREET. |
| FURTHER DISCUSSION IS NECESSARY. |
| 6- PARKING SPACES ON OLIVE AVE ARE DIFFERENT THAN SITE |
| PLAN, PLEASE DISCUSS CHANGES. (MISSING CURB LINE ON |
| SHEET SP-1) |
| 7- NEW CURB ON NORTH SIDE OF 6TH STREET SHALL MATCH THE |
| BUB OUT ON OLIVE. CURRENTLY SHOWN WITH A SMALL ANGLE TO |
| MATCH. |
| 8- PLEASE INCLUDE DETAILS ON PROPOSED TRAFFIC CALMING |
| ON 6TH STREET. IT NEEDS APPROVAL FROM THE ENGINEERING |
| DEPARTMENT (TRANSPORTATION ENG - BRIAN COLLINS). |
| 9- SHEET SP-1 SHOWS DIFFERENT CURB LOCATION ON 6TH |
| STREET THAN CIVIL DRAWINGS. PLEASE CORRECT FOR |
| CONSISTENCY. |
| 10- BUILDING COLUMN AT PARKING ENTRANCE ON 6TH STREET |
| IS ENCROACHING INTO THE REQUIRED SETBACK. |
| 11- MAIN ENTRNACE ON DIXIE HWAY WAS REMOVED. SITE PLAN |
| APPROVAL SHOW A MAIN ENTRANCE FROM DIXIE HWAY, AS |
| INDICATED BY THE MAIN BUIDLING FEATURES (ENTRY PORCH). |
| 12- A NEW COLUMN IS NOW SHOWN IN THE WALK UP UNITS. |
| SETBACK SHALL BE MEASURED TO THAT COLUMN IF IT IS |
| CLOSER TO THE CURB. |
| 13- PARKING DETAIL SHALL COMPLY WITH CITY STANDARD |
| STRIPING DETAIL. |
| FOR ADDITIONAL INFORMATION PLEASE CONTACT ANA MARIA |
| APONTE AT 561-822-1439. |
2014-02-24 14:07:46 | 2/24/14 |