Date |
Text |
2014-01-21 09:47:31 | 2010 FBC |
| |
| DENIED BY BUILDING |
| |
| 1) THE PLANS THAT WERE SUBMITTED INDICATE THAT THERE IS |
| AN INCREASE IN THE ORIGINAL SCOPE OF WORK. SPECIFY THE |
| INCREASED VALUE FOR THE ADDITIONAL SCOPE OF WORK. NOTE: |
| THE ORIGINAL SCOPE OF WORK WAS TO REMOVE AND REPLACE |
| WATER DAMAGED FLOOR COVERING, DRYWALL, TILE BACKER AND |
| TILE IN THE ROOMS SPECIFIED IN THE SCOPE OF WORK LETTER |
| FROM J.B. KERN. |
| |
| 2) SUBMIT TWO COPIES OF PRODUCT APPROVALS FOR THE GLASS |
| BLOCK THAT WILL BE INSTALLED IN THE FIRST FLOOR BATH. |
| DCA RULE 9N-3 |
| |
| 3) SUBMIT TWO COPIES OF THE PRODUCT APPROVALS FOR THE |
| NEW WINDOW THAT WILL BE INSTALLED IN THE NEW WINDOW |
| OPENING SHOWN ON ELEVATION 4 ON SHEET A-1. IF MULTIPLE |
| WINDOW AND GLASS TYPES ARE SHOWN IN THE PRODUCT |
| APPROVAL, MARK THE ONE THAT WILL BE USED. DCA RULE 9N-3 |
| |
| 4) SUBMIT TWO COPIES OF THE PRODUCT APPROVALS FOR THE |
| IMPACT PROTECTION FOR THE NEW GLAZED OPENINGS. FBC |
| R301.2.1.2 AND DCA RULE 9N-3 |
| |
| 5) THE PRODUCT APPROVALS ARE REQUIRED TO BE REVIEWED |
| AND APPROVED IN WRITING BY THE DESIGNER OF RECORD FOR |
| THE PROJECT. CITY AMENDMENTS 107.3.4.1 |
| |
| NOTE: THIS REVISION WILL NEED TO BE RESUBMITTTED UNDER |
| THE SAME REVISION NUMBER. ADDITIONAL FEES WILL BE |
| CHARGED. EACH PRODUCT APPROVAL WILL BE COUNTED AS A |
| REVISED PAGE. IN ORDER TO SPEED THE PLAN REVIEW |
| PROCESS, PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW |
| EACH OF THE REVIEW ITEMS HAS BEEN ADDRESSED. |
| |
| ROBERT MCDOUGAL |
| BLDG. PLAN REVIEW |
| (561)805-6714 |
| [email protected] |