2013-09-11 08:15:12 | THIRD COURTESY REVIEW VIA EMAIL: |
| |
| ****CORRECTIONS**** |
| |
| SAMANTHA HILL |
| BUILDING PLANS EXAMINER |
| [email protected] |
| 561-805-6724 |
| |
| AS IT APPEARS FROM MANUFACTURER'S EMAIL THAT THIS |
| PRODUCT HAS NOT ACTUALLY BEEN TESTED TO THE STANDARD |
| LISTED IN THEIR LITERATURE, EITHER HAVE THE PRODUCT |
| TESTED (ASTM E-84, SEE PREVIOUS COMMENT LISTS) OR |
| SUBMIT ENGINEERING AND/OR TEST REPORTS FBC 104.11 |
| ALTERNATIVE MATERIALS AND METHODS: |
| |
| 104.11 ALTERNATIVE MATERIALS, DESIGN AND METHODS OF |
| CONSTRUCTION AND EQUIPMENT. THE PROVISIONS OF THIS CODE |
| ARE NOT INTENDED TO PREVENT THE INSTALLATION OF ANY |
| MATERIAL OR TO PROHIBIT ANY DESIGN OR METHOD OF |
| CONSTRUCTION NOT SPECIFICALLY PRESCRIBED BY THIS CODE, |
| PROVIDED THAT ANY SUCH ALTERNAT IVE HAS BEEN APPROVED. |
| AN ALTERNATIVE MATERIAL, DESIGN OR METHOD OF |
| CONSTRUCTION SHALL BE APPROVED WHERE THE BUILDING |
| OFFICIAL FINDS THAT THE PROPOSED DESIGN IS SATISFACTORY |
| AND COMPLIES WITH THE INTENT OF THE PROVISIONS OF THIS |
| CODE, AND THAT THE MATERIAL, METHOD OR WORK OFFERED IS, |
| FOR THE PURPOSE INTENDED, AT LEAST THE EQUIVALENT OF |
| THAT PRESCRIBED IN THIS CODE IN QUALITY, STRENGTH, |
| EFFECTIVENESS, FIRE RESISTANCE, DURABILITY AND SAFETY. |
| WHEN ALTERNATE LIFE SAFETY SYSTEMS ARE DESIGNED, THE |
| SFPE ENGINEERING GUIDE TO PERFORMANCE-BASED FIRE |
| PROTECTION ANALYSIS AND DESIGN OF BUILDINGS, OR OTHER |
| METHODS APPROVED BY THE BUILDING OFFICIAL MAY BE USED. |
| |
| THE BUILDING OFFICIAL SHALL REQUIRE THAT SUFFICIENT |
| EVIDENCE OR PROOF BE SUBMITTED TO SUBSTANTIATE ANY |
| CLAIM MADE REGARDING THE ALTERNATIVE. |
| |
| 104.11.1 RESEARCH REPORTS. SUPPORTING DATA, WHERE |
| NECESSARY TO ASSIST IN THE APPROVAL OF MATERIALS OR |
| ASSEMBLIES NOT SPECIFICALLY PROVIDED FOR IN THIS CODE, |
| SHALL CONSIST OF VALID RESEARCH REPORTS FROM APPROVED |
| SOURCES. |
| |
| 104.11.2 TESTS. WHENEVER THERE IS INSUFFICIENT EVIDENCE |
| OF COMPLIANCE WITH THE PROVISIONS OF THIS CODE, OR |
| EVIDENCE THAT A MATERIAL OR METHOD DOES NOT CONFORM TO |
| THE REQUIREMENTS OF THIS CODE, OR IN ORDER TO |
| SUBSTANTIATE CLAIMS FOR ALTERNATIVE MATERIALS OR |
| METHODS, THE BUILDING OFFICIAL SHALL HAVE THE AUTHORITY |
| TO REQUIRE TESTS AS EVIDENCE OF COMPLIANCE TO BE MADE |
| AT NO EXPENSE TO THE JURISDICTION. TEST METHODS SHALL |
| BE AS SPECIFIED IN THIS CODE OR BY OTHER RECOGNIZED |
| TEST STANDARDS. IN THE ABSENCE OF RECOGNIZED AND |
| ACCEPTED TEST METHODS, THE BUILDING OFFICIAL SHALL |
| APPROVE THE TESTING PROCEDURES. TESTS SHALL BE |
| PERFORMED BY AN APPROVED AGENCY. REPORTS OF SUCH TESTS |
| SHALL BE RETAINED BY THE BUILDING OFFICIAL FOR THE |
| PERIOD REQUIRED FOR RETENTION OF PUBLIC RECORDS. |
| |
| SEE ALSO: |
| |
| FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE |
| BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL |
| INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID |
| DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED |
| TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. |
| |
| SEE 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM |
| E 84 OR UL 723. |
| |
| |