Plan Review Notes
Plan Review Notes For Permit 13070994
Permit Number 13070994
Review Stop E
Sequence Number 1
Notes
Date Text
2013-09-19 14:02:18#13070994
 455 HIBISCUS
 MARRIOTT RESIDENCE INN
  
 PLEASE REVISE THE PLANS IN RESPONSE TO THE FOLLOWING
 REVIEW COMMENTS.
  
 E1.1
 PROVIDE A DESIGNATED CLEAR WORKING SPACE AROUND THE
 ELECTRICAL SERVICE EQUIPMENT AND PANEL BOARDS. NEC
 215.5, 110.26
  
 PROVIDE A SAFETY LABELING SCHEDULE FOR FLASH PROTECTION
 AND FOR THE PANEL BOARDS AND MAIN DISCONNECTING MEANS.
 NEC 110.22, 110.16, 110.22
  
 VERIFY THE FIRE PUMP CIRCUIT CONDUCTORS ARE PROPERLY
 PROTECTED. NEC 695.6
  
 VERIFY THE FIRE PUMP OVER CURRENT PROTECTIVE DEVICES
 HAVE BEEN SELECTED TO CARRY INDEFINITELY THE SUM OF THE
 LOCKED-ROTOR CURRENT OF THE FIRE PUMP EQUIPMENT. NEC
 694.4
  
 PROVIDE A SIGN AT THE SERVICE-ENTRANCE EQUIPMENT
 INDICATING TYPE AND LOCATION OF THE ON-SITE EMERGENCY
 POWER SOURCES. NEC 700.8
  
 PROVIDE SIGNAGE DETAIL FOR ALL FIRE PUMP DISCONNECTS
 AND CONTROLLERS. NEC 695.4
  
 VERIFY THE POWER SOURCE SUPPLIED BY THE ON-SITE
 GENERATOR TO THE FIRE PUMP CONNECTS TO A DEDICATED
 DISCONNECTING MEANS SEPARATE FORM THE OTHER GENERATOR
 DISCONNECTING MEANS. NEC 695.4
  
 VERIFY THE EMERGENCY CIRCUIT WIRING IS FULLY PROTECTED.
 NEC 695.14, 700.9
  
 VERIFY THAT ALL WIRING FROM THE EMERGENCY SOURCE HAS
 BEEN KEPT ENTIRELY INDEPENDENT OF ALL OTHER WIRING AND
 EQUIPMENT INCLUDING CONTROL CONDUCTORS TO THE
 GENERATOR. NEC 695.14 700.9(B)
  
 PROVIDE LISTING AND SPECIFICATIONS ON THE EMERGENCY
 ELEVATOR RECALL TRANSFER SWITCH. NEC 110.3
  
 PROVIDE A LOAD SUMMARY FOR THE GENERATOR BRANCH WHICH
 SUPPORTS ITS SELECTION TO PROVIDE EMERGENCY POWER TO
 'EDP', 'E1' AND THE FIRE PUMP. NEC 215.2, 220.40
  
 VERIFY THE GENERATOR HAS DUAL FUEL SUPPLIES. NEC
 700.12(B)
  
 VERIFY THE EMERGENCY SYSTEM HAS THE CAPACITY TO CONNECT
 TO A PORTABLE OR TEMPORARY ALTERNATE SOURCE OF POWER
 WHEN THE GENERATOR IS OUT OF SERVICE FOR MAJOR REPAIR.
 NEC 700.5 B
  
  
 E1.2
  
 FIRE PUMP FEEDER APPEARS TO BE UNDERSIZED BASED ON THE
 SELECTED 100 HP FIRE PUMP WITH PRESSURE MAINTENANCE
 PUMPS. NEC 695.6
  
 VERIFY EQUIPMENT GROUND SELECTION FOR PANEL 'DBP'. NEC
 T250.122
  
 E1.3
 PROVIDE DETAIL FOR FIRE STOPPING OF ALL FLOOR AND WALL
 PENETRATIONS. NEC 300.21
  
 E1.4
 CLARIFY PANEL S2 FED FROM DPX ? WHAT IS DPX?
  
 CLARIFY LOCATION OF PANEL C (100 AMP) NOT SHOWN ON
 MSB-B
  
 VERIFY ELEVATOR PIT AND LIGHT FED FROM PANEL 'L' IS NOT
 CONSIDERED AN EMERGENCY LOAD.
  
 VERIFY THE SUMP PUMP FED FROM PANEL 'L' IS NOT
 CONSIDERED AN EMERGENCY LOAD.
  
 E 2.2
 VERIFY THE FIRE PUMP HAS BEEN LOCATED WITHIN A ROOM
 THAT HAS A 2 HOUR RATED FIRE RESISTIVE SEPARATION. FBC
 913.2.1
  
 INDICATE THE PROPOSED WIRING METHOD AND CLASSIFICATION
 FOR THE POOL EQUIPMENT AREA. NEC 505.5
  
 E2.3
 VERIFY THE TRANSFORMER VAULT HAS A 3 HOUR FIRE
 RESISTIVE CONSTRUCTION . NEC 450.42
 VERIFY THE ELECTRIC DRINKING FOUNTAIN HAS GFCI
 PROTECTION. NEC 422.52
  
 E2.5, E2.8, E2.9
  
 LIGHTING TIMERS REQUIRE BACKUP PROTECTION. FBC-EC
 505.2.4
  
 VERIFY THE LIGHTING SCENES, SEQUENCING AND CONTROLS
 MEET THE REQUIREMENTS OF FBC ENERGY CODE. FBC-EC 505.2
  
 PROVIDE LIGHTING POWER DENSITY COMPLIANCE CERTIFICATION
 ON ELECTRICAL PLANS. FBC-EC 505.503
  
 SEPARATE PERMIT WITH PLANS AND WIND LOAD ENGINEERING
 FOR POLES WITH LIGHT ASSEMBLY REQUIRED FOR
 CONSTRUCTION. FBC 1604.1, ASCE 7/10
  
 E3.1
 PROVIDE SAFE WORKING CLEARANCE DETAIL/DIMENSIONS ON
 PLANS FOR ALL GUEST ROOM PANEL BOARDS. NEC 110.26
  
 E5.1
 PROVIDE A SUMMARY LOAD CALCULATION FOR THE ELECTRICAL
 SERVICE, INCLUDING DISTRIBUTION AND GUEST ROOMS. NEC
 230.31
  
  
 NOTE: SEPARATE PERMITS AND PLANS REQUIRED FOR SWIMMING
 POOL, FIRE ALARM SYSTEM, SITE LIGHTING, LOW VOLTAGE
 SYSTEMS, ETC.
  
 DOUG HARVEY
 [email protected]
 561-805-6740
  
  
  
  