2013-07-24 14:28:23 | PLANNING AND ZONING: ***** FAILED**** |
| |
| 7/24/2013 |
| 1. COPY OF APPROVED EASEMENT VACATION WILL BE REQUIRED |
| FOR ZONING APPROVAL OF THIS PROJECT. |
| |
| 2. THE ZONING OF THE SUBJECT PROPERTY IS SF7. IT |
| APPEARS THERE IS AN ACCESSORY APARTMENT PROPOSED OVER |
| THE GARAGE. ACCESSORY APARTMENTS ARE NOT PERMITTED IN |
| THIS ZONING DISTRICT (ZLDR SEC. 94-303(A)). PLEASE |
| REVISE PLANS TO SHOW COMPLIANCE WITH THIS REQUIREMENT. |
| |
| 3. VISIBILITY SITE TRIANGLE SHOULD BE DEPICTED AT 20' |
| RATHER THAN 12.5' (ZLDR SEC. 94-305(3)). |
| |
| 4. MECHANICAL EQUIPMENT MAY NOT PROJECT MORE THAN 4' |
| INTO A REQUIRED SETBACK (ZLDR SEC. 94-305(B)(4)). |
| PLEASE VERIFY THE SETBACKS FOR THE MECHANICAL EQUIPMENT |
| ALONG THE NORTH AND WEST PROPERTY LINES. |
| |
| 5. PLEASE CLARIFY IF ANY TREES WILL BE REMOVED OR |
| RELOCATED ON THE SITE FOR THE PROPOSED CONSTRUCTION. IF |
| TREES WILL BE REMOVED OR RELOCATED, A TREE ALTERATION |
| PERMIT APPLICATION WILL NEED TO BE SUBMITTED. |
| |
| ADDITIONAL COMMENTS: |
| 1. SUBMIT LANDSCAPE PLAN FOR REVIEW. |
| |
| 2. CONSTRUCTION OF A POOL WILL REQUIRE COMPLIANCE WITH |
| ZLDR SEC. 94-304(D)(2)B., C., AND D. REGARDING FENCING |
| AND SCREENING. IT IS RECOMMENDED THESE ITEMS ARE |
| ADDRESSED WITH THE SITE PLAN/LANDSCAPE PLAN REVIEW. |
| OTHERWISE, COMPLIANCE WITH THESE ITEMS WILL BE REVIEWED |
| WITH THE SUBMITTAL OF THE PERMIT APPLICATION FOR THE |
| POOL. |
| |
| |
| IF YOU HAVE QUESTIONS, PLEASE CONTACT: |
| |
| DANIELLE J. KITTREDGE, AICP |
| SENIOR PLANNER |
| PLANNING & ZONING DIVISION |
| PHONE: (561)-822-1443 |
| EMAIL: [email protected] |
| |
2013-07-22 10:56:50 | 7/22/13 |