Plan Review Notes
Plan Review Notes For Permit 13030782
Permit Number 13030782
Review Stop P
Sequence Number 2
Notes
Date Text
2013-06-25 15:03:24****PROVISO****
  
 1. THE AAV'S SHOWN ON P-1.2 & P2.1 WILL BE REQUIRED TO
 BE VENTED AS THEY ARE NOT WITHIN THE TOP FOUR BRANCH
 INTERVALS.
 FBC PLUMBING 917.3.1
  
 2. THE CONNECTIONS TO THE SOVENT HORIZONTAL LINE AFTER
 THE DEAERATOR ON P1.2S, P1.3N, P1.3S, AND P2.1 ARE TO
 CONNECT ABOVE THE CENTER LINE. SEE DETAIL # 16 ON P0.3
 SOVENT RULE B3:
 SOIL AND WASTE CONNECTIONS BETWEEN
 THE CENTER LINE OF THE
 SOVENT STACK AND TERMINATION
 POINT IN THE BUILDING DRAIN IS ALLOWED.
 CONNECTIONS MUST BE
 MADE ABOVE THE CENTER LINE OF THE
 BUILDING DRAIN, OR THE CONNECTIONS
 CAN BE MADE 10 STACK PIPE DIAMETERS
 DOWN STREAM. (DWG. 101-6B)