Date |
Text |
2014-08-28 10:58:11 | REVIEW OF ELEVATION CERTIFICATE SUBMITTED VIA EMAIL |
| EMAIL SENT TO CONTRACTOR AND SURVEYOR |
| |
| THANK YOU DAVE! |
| |
| OUR RECORDS SHOW THAT THIS IS ACTUALLY ONE BUILDING, |
| NOT TWO. THE TWO BUILDING SECTIONS ARE CONNECTED WITH A |
| COVERED WALKWAY (SEE AERIAL BELOW AND ALSO SURVEYOR'S |
| SURVEY). IT IS NOT CLEAR WHETHER THIS COVERED |
| WALKWAY/PORCH IS ENCLOSED OR NOT, AND I DON'T HAVE AN |
| ELEVATION FOR IT. I THINK THAT IT'S OK TO HAVE TWO |
| SEPARATE ELEVATION CERTIFICATES, ONE FOR EACH PORTION, |
| BUT THE COVERED WALKWAY/PORCH NEEDS TO BE INCLUDED. IF |
| THE ELEVATION OF THE WALKWAY IS LESS THAN 7.5', IT |
| SHOULD BE EITHER OPEN OR HAVE FLOOD OPENINGS. ITEM C2B |
| |
| REGARDING THE ELEVATION CERTIFICATE, GUEST HOUSE: |
| |
| ITEM C2B NEEDS TO INCLUDE AN ELEVATION. THERE IS A NOTE |
| STATING THAT THE SURVEYOR DID NOT HAVE ACCESS TO THE |
| SECOND FLOOR. PER THE ISO AUDITOR, ALL ELEVATIONS MUST |
| BE INCLUDED. IF ONE EC IS DONE FOR THE TWO BUILDING |
| SECTIONS, THE ELEVATION OF THE SECOND FLOOR WOULD NOT |
| BE NEEDED. |
| |
| REGARDING THE ELEVATION CERTIFICATE, MAIN HOUSE: |
| |
| ITEM A8C, THERE ARE NOT ENOUGH FLOOD OPENINGS TO |
| SATISFY NFIP REQUIREMENTS. PLEASE SEE THE FOLLOWING |
| DOCUMENT, "OPENINGS IN FOUNDATION WALLS AND WALLS OF |
| ENCLOSURES," TECHNICAL BULLETIN 1 / AUGUST 2008 FOR |
| PROPER INSTALLATION OF FLOOD VENTS: |
| |
| HTTP://WWW.FEMA.GOV/MEDIA-LIBRARY-DATA/20130726-1502-20 |
| 490-9949/FEMA_TB_1__1_.PDF |
| |
| PAGE 18 EXPLAINS THAT NON-ENGINEERED OPENINGS ARE TO |
| PROVIDE 1 SQUARE INCH OF NET OPEN AREA FOR EACH SQUARE |
| FOOT OF ENCLOSED AREA. IF THE OPENINGS ARE ACTUALLY AN |
| ENGINEERED PRODUCT (SUCH AS SMARTVENT OR SIMILAR |
| PRODUCT), THE ICC EVALUATION REPORT WOULD DICTATE THE |
| OPENINGS REQUIRED. PLEASE VERIFY THAT THE FLOOD VENTS |
| ARE NOT ENGINEERED FLOOD VENTS. IF THEY ARE ENGINEERED |
| (OR AN ENGINEERED PRODUCT WITH AN ICC EVALUATION |
| REPORT), THE ELEVATION CERTIFICATE SHOULD BE REVISED |
| AND THE ICC EVALUATION REPORT ATTACHED TO THE EC. |
| |
| IF YOU VERIFY THAT THE OPENINGS ARE NOT ENGINEERED, |
| EITHER ADDITIONAL OPENINGS SHOULD BE INSTALLED OR THE |
| EXISTING NON-ENGINEERED VENTS COULD BE REPLACED WITH |
| ENGINEERED FLOOD VENTS. TYPICALLY ENGINEERED FLOOD |
| VENTS REQUIRE HALF THE NET OPENINGS THAT NON-ENGINEERED |
| VENTS REQUIRE. |
| |
| IF POSSIBLE, PLEASE INCLUDE PHOTOGRAPHS OF THE EXISTING |
| FLOOD VENTS. PLEASE SEE PAGE 19 OF TECHNICAL BULLETIN |
| 1. VENTS USED FOR AIR VENTILATION WHICH CAN BE CLOSED |
| MANUALLY OR WHICH HAVE COVERS ARE NOT ACCEPTABLE AS |
| FLOOD VENTS. THIS WILL HELP TO AVOID ANY INSPECTION |
| ISSUES. |
| |
| THANK YOU, |
| |
| SAMANTHA |
| |
| |
| |
| |
| SAMANTHA M. HILL |
| BUILDING PLANS EXAMINER |
| BUILDING DIVISION |
| CITY OF WEST PALM BEACH |
| 401 CLEMATIS STREET, 1ST FLOOR |
| WEST PALM BEACH, FL 33401 |
| 561-805-6724 |
| [email protected] |
| |
| |