Date |
Text |
2012-09-20 15:31:11 | FAILED |
| |
| PLEASE RESPOND IN WRITING. PLEASE NOTE THAT THE PLANS |
| HAVE BEEN MARKED WITH THE COMMENTS. ALL CORRECTIONS |
| SHALL BE REFLECTED ON ALL PLANS, REGARDLESS IF THEY |
| INCLUDE NOTES. |
| |
| 1) SITE LAYOUT AND ELEVATIONS HAVE CHANGED. THE FINAL |
| AS-BUILT PLANS NEED TO BE SUBMITTED AS A MINOR SITE |
| PLAN AMENDMENT TO THE PLANNING DIVISION. |
| |
| 2) THE RELOCATED SIDEWALK, SOUTH OF THE VISITOR |
| BUILDING LEADING TO THE MAIN POWER BLOCK, HAS BEEN |
| SHIFTED TO THE WEST FROM THE ORIGINALLY APPROVED PLANS. |
| THIS RESULTS IN THE INTERIOR LANDSCAPE ISLANDS NOT |
| HAVING SUFFICIENT WIDTH TO SUPPORT THE REQUIRED TREES. |
| |
| 3) HOW WILL THE FOOTER AND SUPPORT POST ALLOW FOR THE |
| INSTALLATION OF THE REQUIRED TREES IN THE TERMINAL |
| PARKING ISLANDS? THE ACCURATE DIMENSIONS NEED TO BE |
| SHOWN ON THE SITE AND LANDSCAPE PLANS. THE SUPPORT |
| POSTS SHOWN ON SHEET 710-A5-101 DO NOT MATCH THE |
| FOOTPRINT ON THE SITE PLAN. |
| |
| 4) HOW WILL THE AIR CONDITION UNITS BE SCREENED? |
| |
| 5) CHECK THE DIMENSIONS IN THE NORTHEAST CORNER OF THE |
| PARKING LOT. THEY DO NOT SEEM TO SCALE WITH WHAT IS |
| SHOWN. |
| |
| 6) WHAT IS THE 16 FOOT MEASUREMENT SHOWING AT THE |
| PHOTOVOLTAIC CARPORTS? |
| |
| 7) LIGHT POLE LOCATIONS SHALL NOT INTERFERE WITH |
| PARKING LOT TREES. STAFF WILL NOT APPROVE THE SITE |
| LIGHTING UNTIL THE LANDSCAPE PLAN IS SUBMITTED FOR |
| REVIEW TO ENSURE NO CONFLICTS. PLEASE NOTE THAT SITE |
| LIGHTING REQUIRES A SEPARATE PERMIT. |
| |
| 8) SIGNAGE AND PARKING LOT STRIPING REQUIRE SEPARATE |
| PERMITS. |
| |
| CONTACT ERIC SCHNEIDER @ (561) 822-1446 |
| |
| |
| |