Plan Review Notes
Plan Review Notes For Permit 12080323
Permit Number 12080323
Review Stop B
Sequence Number 1
Notes
Date Text
2012-08-13 09:53:06SPOKE WITH KRYSTAL. ALTHOUGH THE APPLICATION IS FOR
 TOTAL DEMOLITION, THE PARKING GARAGE IN PHASE ONE WILL
 BE FIRST TO GO. REALIZING THAT PENNY'S WILL CONTINUE TO
 NEED POWER, AN ELECTRICAL PERMIT THAT WILL SAFE EACH
 PHASE OF DEMOLITION WILL NEED TO BE PULLED. ELECTRICAL
 INSPECTIONS CAN THEN SUFFICE FOR RELEASES OF PHASES.
 PARKING GARAGE STILL LIVE ACCORDING TO KRYSTAL.
 A GAS RELEASE FOR THE ENTIRE PROJECT OR HOW PENNY'S
 WILL REMAIN LIVE FOR DEMOLITION SHOULD BE RECEIVED
 PRIOR TO ANY PHASE RELEASE.
 WATER METER RELEASES, THERE WILL BE MANY WATER METERS
 ON THIS JOB THAT NEED TO BE PULLED OR KEPT. THIS CAN BE
 ACCOMPLISHED BY THE PLUMBING CONTRACTOR YET SIGNED ON.
 FIRE SPRINKLERS, NEED TO BE ADDRESSED. HOW WILL PENNY'S
 REMAIN PROTECTED? THIS MAY NEED FIRE TO SIGN OFF.
 NO POLLUTION PREVENTION PLAN IN APPLICATION. ENG. WILL
 NEED THAT.
 PLAN OUT FRONT UNDER "B".