2012-01-19 08:17:37 | 2007 FBC W/2009 REVISIONS |
| |
| 1) SUBMIT TWO COPIES OF ENERGY CALCULATIONS FOR THE |
| RENOVATED BUILDING AS REQUIRED BY 2007 ENERGY GLITCH |
| AMENDMENTS SECTION N1100.0.1. |
| |
| 2) THE COVER SHEET SPECIFIES THAT THE WIND DESIGN IS |
| FOR EXPOSURE CATEGORY C, HOWEVER, THE WINDOW AND DOOR |
| COMPONENT AND CLADDING PRESSURES ON SHEET 1.2 ARE FOR |
| EXPOSURE B. PLEASE CORRECT. SEE FBC R301.2.1. |
| |
| 3) PLEASE SUBMIT TWO COPIES OF THE PRODUCT APPROVALS |
| FOR THE NEW EXTERIOR DOOR AS REQUIRED BY DC A RULE |
| 9N-3. |
| |
| 4) THE PRODUCT APPROVALS SUBMITTED FOR THE SINGLE HUNG |
| WINDOWS ARE EXPIRED. PLEASE SUBMIT TWO COPIES OF |
| CURRENT PRODUCT APPROVALS FOR THE NEW SINGLE HUNG |
| WINDOWS AS REQUIRED BY DCA RULE 9N-3. |
| |
| 5) FBC R301.2.1.2 REQUIRES GLAZED OPENINGS TO HAVE |
| LARGE MISSILE IMPACT PROTECTION. IF STORM PANELS ARE |
| EXISTING PROVIDE PROOF THAT THEY WERE PERMITTED AND |
| INSPECTED. OTHERWISE SUBMIT TWO COPIES OF PRODUCT |
| APPROVALS, KEY PLANS AND INSTALLATION SCHEDULES FOR |
| STORM PANELS. INSTALLATION SCHEDULE IS AVAILABLE AT HTT |
| P://WWW.WPB.ORG/CONSTRUCTION/PDF/SCHEDULE_FOR_INSTALLAT |
| ION.PDF |
| |
| 6) PRODUCT APPROVALS ARE REQUIRED TO BE REVIEWED AND |
| APPROVED IN WRITING BY THE DESIGNER OF RECORD PER CITY |
| AMENDMENT 106.3.3. |
| |
| 7) PLEASE SUBMIT TWO COPIES OF THE PRODUCT APPROVALS |
| FOR THE ROOING MATERIALS AS REQUIRED BY DC A RULE 9N-3. |
| SPECIFY THE METHOD OF ATTACHMENT THAT WILL BE USED TO |
| INSTALL THE ROOF TILE ON THE PRODUCT APPROVAL. IF AN |
| ADHESIVE OR MORTAR SET SYSTEM IS USED SUBMIT PRODUCT |
| APPROVALS FOR THE PRODUCT THAT WILL BE USED. IF YOU |
| CHOOSE NOT TO SUBMIT THE ROOFING INFORMATION AT THIS |
| TIME, A SEPARATE PERMIT, APPLICATION AND REVIEW WILL BE |
| REQUIRED FOR THE ROOFING. |
| |
| 8) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH |
| OF THE REVIEW COMMENTS HAS BEEN ADDRESSED. |
| |
| ROBERT MCDOUGAL |
| BLDG. PLAN REVIEW |
| (561)805-6714 |
| [email protected] |