Plan Review Notes
Plan Review Notes For Permit 11030256
Permit Number 11030256
Review Stop ENG-MOT
Sequence Number 1
Notes
Date Text
2011-03-30 08:18:33PASSED WITH PROVISOS:
  
 1. VMS BOARDS WILL GO IN ONE WEEK PRIOR TO BLOCKING THE
 ROAD AND WILL STATE;
 "WATER MAIN CONSTRUCTION ON HIBISCUS FROM 04/11 TO
 04/26 FROM QUADRILLE TO OLIVE"
  
 2. VMS WILL STATE DURING CONSTRUCTION;
 "WEST BOUND TRAFFIC CLOSED ON HIBISCUS, FOLLOW DETOUR"
  
 3. CONES WILL NOT BE USED AS SHOWN ON MOT SUBMITTAL,
 BUT WILL BE WATER FILLED BARRIERS AS WORKED OUT BETWEEN
 CONTRACTOR AND CONSTRUCTION COORDINATOR.
  
 4. ALL CONSTRUCTION WILL STOP AND THE TRAVEL LANES WILL
 BE OPENED FOR SUNFEST (APRIL 27TH THRU MAY 2ND)
  
 5. ALL CLOSED PARKING SPACES WILL NEED TO BE PAID FOR
 THRU THE PARKING SYSTEMS OFFICE. THEY CAN BE CONTACTED
 AT 822-1500. APPOXIMATELY 11 BETWEEN OLIVE AND DIXIE ON
 THE NORTH SIDE AND 14 SPACES BETWEEN QUADRILLE AND
 DIXIE.
  
 6. QUADRILLE TO DIXIE WILL BE COMPLETED, PRIOR TO THE
 START OF CONSTRUCTION BETWEEN DIXIE AND OLIVE.
  
  
  