2010-10-01 13:40:57FBC FUEL GAS 2007 REVIEW #1
 DENIED:
  
 IF FUEL GAS IS INCLUDED WITH PLAN:
 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS ALL
 CUT SECTIONS OF PIPE AND CORRESPONDING LENGTHS PER
 FBC-2007 FUEL GAS.
 2. SHOW TYPE OF PIPING MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, AND THE EDH NUMBER OF CORRUGATED STAINLESS
 STEEL TUBING FOR EACH PIPE SIZE IF BEING USED.
 3. TYPE OF GAS, (LP OR NATURAL).
 4. BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON
 THE SYSTEM. REFER TO THE FBC-2007 FUEL GAS SECS. 401.8
 THRU 402.6.1 AND TABLES 402.4(1) THRU 402.4(35)
 5. SHOW THE DISTANCE FROM THE POINT OF DELIVERY,
 (METER), TO THE MOST REMOTE OUTLET IN THE BUILDING
 AND/OR SYSTEM PER THE FBC-2007 FUEL GAS APPENDIX A ???
 USE OF CAPACITY SECTION A.3.1(4)
 6. SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE
 FBC-2007 FUEL GAS CODE SEC. 304
 7. INDICATE THE DELIVERY PRESSURE (PSI) PER FBC-2007
 FUEL GAS SEC. 402.2. IF NATURAL GAS SPECIFY .5 PSI OR 2
 PSI.
 8. SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE AND
 TERMINATION OF THE GAS VENTS PER FBC-2007 FUEL GAS CODE
 SEC. 502 THRU 505.
 9. SUBMIT MANUFACTURE SHEETS FOR ALL GAS EQUIPMENT TO
 VERIFY COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND
 FBC-2007 FUEL GAS SEC. 402.2
 10. CLEARLY SHOW THE LOCATION AND CAPACITY OF LP
 TANK(S), TYPE OF TANK (DOT OR ASME), THE DISTANCE OF
 THE TANK FROM THE BUILDING AND ADJACENT PROPERTY LINES
 THE DISTANCE OF THE TANK FROM ALL SOURCES OF IGNITION,
 OTHER CONTAINERS, BUILDINGS, AND THE LOCATION OF ANY
 BUILDING OPENINGS BELOW THE RELIEF VALVE OF THE TANK
 PER NFPA 58, TABLE 3-2.2.2.
 11. CLEARLY INDICATE ON THE PLAN IF THE LP TANK IS
 ABOVE OR BELOW GROUND, AND SHOW REQUIRED PROTECTION OF
 THE TANK AND APPURTENANCES PER NFPA 58. IF THE TANK IS
 BELOW GROUND THE CONTAINER SHALL BE SECURELY ANCHORED
 PER NFPA 58 SECTION 3-2.2.7(H).
 12. EMERGENCY HOOD SHUT DOWN SHUT OFF VALVE TO BE BELOW
 CEILING. MANUAL SHUT OFF VALVE TO BE UPSTREAM. UNION TO
 BE DOWN STREAM OF MANUAL VALVE.
 ANY QUESTIONS REGARDING THESE REQUIREMENTS MAY BE
 REFERRED TO:
 CHIEF PLUMBING INSPECTOR (561) 805-6692
 PLUMBING PLANS EXAMINER (561) 805-6721
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved