Plan Review Notes
Plan Review Notes For Permit 10070135
Permit Number 10070135
Review Stop P
Sequence Number 1
Notes
Date Text
2010-07-22 15:14:22******PROVISO*******
  
 314.2.1 CONDENSATE DISPOSAL. CONDENSATE FROM ALL
 COOLING COILS AND EVAPORATORS SHALL BE CONVEYED FROM
 THE DRAIN PAN OUTLET TO AN APPROVED PLACE OF DISPOSAL.
  
 608.15.4 PROTECTION BY A VACUUM BREAKER. OPENINGS AND
 OUTLETS SHALL BE PROTECTED BY ATMOSPHERIC-TYPE OR
 PRESSURE-TYPE VACUUM BREAKERS. THE CRITICAL LEVEL OF
 THE VACUUM BREAKER SHALL BE SET A MINIMUM OF 6 INCHES
 (152 MM) ABOVE THE FLOOD LEVEL RIM OF THE FIXTURE OR
 DEVICE.
  
 905.4 VERTICAL RISE OF VENT. EVERY DRY VENT SHALL RISE
 VERTICALLY TO A MINIMUM OF 6 INCHES (152 MM) ABOVE THE
 FLOOD LEVEL RIM OF THE HIGHEST TRAP OR TRAPPED FIXTURE
 BEING VENTED.
  