Plan Review Notes For Permit 10060706 |
Permit Number |
10060706 |
|
Review Stop |
B |
Sequence Number |
2 |
|
Notes |
Date |
Text |
2010-06-28 09:05:07 | RE-ROOF BUILDING REVIEW SECOND CHECKLIST. | | | | 1- ENGINEER TO CLARIFY RAS 117 CALCULATIONS SUBMITTED. | | SCOPE OF ACTIVITIES IDENTIFIES NAIL SPACING 9" O/C @ | | LAPS & 4 ROWS 10" O.C., 6" O/C @ LAPS & 6 ROWS 6" O.C., | | AND 4" O/C @ LAPS & 9 ROWS 4" O.C. PROVIDE SKETCH | | SHOWING HOW IS THIS PROPOSED NAIL ENHANCING GOING TO BE | | INSTALLED. | | ***NOTE: ENGINEER TO TAKE INTO CONSIDERATION THAT THE | | MINIMUM FASTENER SEPARATION SHALL NOT BE LESS THAN 4" | | O.C. SEE SEC. 8.1 OF RAS 117 CALCULATIONS. | | | | 2- ENGINEER TO PROVIDE THE ENGINEERING FIRM CERTIFICATE | | OF AUTHORIZATION NUMBER AS REQUIRED BY SEC. | | 61G-15-23.002(2) OF FLORIDA ADMINISTRATIVE CODE AND | | SEC. 471 OF FLORIDA STATUTE. | | | | JULIO GOMEZ | | COMMERCIAL COMBINATION PLANS EXAMINER | | (561)805-6712 |
|