Plan Review Notes
Plan Review Notes For Permit 10060054
Permit Number 10060054
Review Stop P
Sequence Number 1
Notes
Date Text
2010-06-09 14:42:09PLUMBING REVIEW
 DENIED:
  
 SHEETS A-1 & A-2:
 WATER CLOSETS IN STALLS IN ACCESSIBLE STALLS SHALL
 COMPLY WITH FIGURE 30E
 FBC 2007 11-4.1.3(11) TOILET FACILITIES. IF TOILET
 ROOMS ARE PROVIDED, THEN EACH PUBLIC AND COMMON USE
 TOILET ROOM SHALL COMPLY WITH SECTION 11-4.22.
 WATER CLOSETS IN ACCESSIBLE STALLS SHALL COMPLY WITH
 FIGURE 30E
  
 SHEET P-1
 1. FBC 2004 WPB AMENDMENTS106.3.5.1.3 : DOMESTIC WATER
 RISER DIAGRAM REQUIRED.
  
 2. A VENT IS REQUIRED BETWEEN THE 2 SHOWERS- FBC 2007
 PLUMBING 901.2.1 VENTING REQUIRED. EVERY TRAP AND
 TRAPPED FIXTURE SHALL BE VENTED IN ACCORDANCE WITH ONE
 OF THE VENTING METHODS SPECIFIED IN THIS CHAPTER.
  
 3. THE VERTICAL DRY VENT BETWEEN THE SHOWERS MAY SERVE
 AS THE CURCUIT VENT FOR THE 4 WATER CLOSETS ON THE
 SECOND FLOOR
 911.2 VENT CONNECTION. THE CIRCUIT VENT CONNECTION
 SHALL BE LOCATED BETWEEN THE TWO MOST UPSTREAM FIXTURE
 DRAINS. THE VENT SHALL CONNECT TO THE HORIZONTAL BRANCH
 AND SHALL BE INSTALLED IN ACCORDANCE WITH SECTION 905.
 THE CIRCUIT VENT PIPE SHALL NOT RECEIVE THE DISCHARGE
 OF ANY SOIL OR WASTE.
  
 4. A URINAL ON THE 2ND FLOOR IS LABELED AS SINK.
  
 5. THE SOIL STACK SERVING THE 2ND FLOOR REQUIRES A
 CLEANOUT.
  
 6. 911.3 THE WASTE FROM THE 2ND FLOOR IS NOT PERMITTED
 TO FLOW THROUGH THE 1ST FLOOR CURCUIT VENT. ATTACH THE
 2ND FLOOR DOWNSTREAM OF THE 1ST WATER CLOSET ON THE 1ST
 FLOOR.
  
 7. A DRY VERTICAL CURCUIT VENT IS REQUIERED BETWEEN THE
 TWO MOST UPSTREAM WATER CLOSETS ON THE FIRST FLOOR.
  
 8. 20 FIXTURE UNITS ARE MAXIMUM FOR A 3" BRANCH. 4"
 PIPE IS REQUIRED UP TO THE BRANCHES BEFORE THE WATER
 CLOSETS ON THE SECOND FLOOR.
  
 REVIEW BY LARRY WAGNER
 CHIEF PLUMBING INSPECTOR
 (561) 805-6692
 FAX (561) 653-2692
 E-MAIL [email protected]
  
  