2009-07-03 15:48:43 | |
| ** DENIED |
| |
| ** BASED ON THE COMMENTS BELOW. IF A PERMIT ONLY FOR |
| UNDERGROUND CONDUIT INSTALLATIONS WOULD ALLEVIATE ANY |
| DELAYS IN THE PROJECT START DATE THIS MAY BE DONE UNDER |
| SEPARATE PERMIT APPLICATION(S). |
| GAVE INFORMATION TO CONTRACTOR AS THIS MAY BE AN OPTION |
| TO GET STARTED. |
| |
| |
| 1) NOTE: TWO PERMIT APPLICATIONS WERE SUBMITTED FOR |
| 09060658 AND 09060657. BOTH FOR THE SAME LOCATION |
| ADDRESS OF * @151 S FLAGLER*. PER THE PLANS THERE ARE |
| TWO SERVICE POINTS WHICH NEED TO CONTAIN SEPARATE |
| ADDRESSES. |
| AN E-MAIL WAS SENT TO ADDRESSING REVIEWER TO |
| ADJUSTMENTS. PLEASE BE SURE ADDRESS IS NOTED ON PLANS. |
| FOR ANY SHEETS WHICH DO NOT NEED TO BE REVISED FOR CODE |
| COMMENTS MAY HAVE NEW ADDRESS PLACED NEATLY ON TITLE |
| BLOCKS. |
| FAC 61G15-23.002, FBC 106.5 FOR RECORD DOCUMENTS. |
| |
| 2) NOTE: PLEASE SEE RISER. THERE IS AN EQUIPMENT |
| GROUNDING CONDUCTOR SHOWN FROM FPL METER TO THE FIRST |
| MEANS OF DISCONNECT. AS THE NEC REQUIRES THE FIRST |
| MEANS OF DISCONNECT TO BE BONDED IF AN EQUIPMENT |
| GROUNDING CONDUCTOR IS INSTALLED THIS WOULD CREATE A |
| PARALLEL PATH WITH THE GROUNDED/NEUTRAL CONDUCTOR. THIS |
| COULD CREATE OBJECTIONABLE CURRENT WHICH IS NOT |
| PERMITTED. |
| PLEASE SEE 250.24, 250.6. |
| |
| 3) NOTE: THE RISER INDICATES TAPS FROM THE SECONDARY |
| SIDE OF THE TRANSFORMER GOING INTO A GUTTER THEN BEING |
| TAPPED AGAIN TO GO TO EACH OF THE PANELS. THIS WOULD BE |
| TAPPING A TAP CONDUCTOR WHICH IS NOT PERMITTED. |
| EACH SET OF TAPPED CONDUCTORS MAY GO TO EACH PANEL |
| HENCE EACH TERMINATING IN OVER CURRENT PROTECTION AS |
| REQUIRED. |
| 240.21,310.16,240.4 |
| |
| 4) NOTE: RISER ONLY INDICATES ONE GROUND ROD. PLEASE |
| SEE 250.56. PLEASE EXPLAIN HOW THE REQUIRED RESISTANCE |
| WILL BE OBTAINED IN SPECIFIC SOIL CONDITIONS BASED ONLY |
| ON THE ONE 10FT GROUND ROD. |
| |
| 5) NOTE: SPOKE TO CONTRACTOR. WIND LOAD CALCULATIONS |
| ARE TO BE SUBMITTED. PLEASE BE SURE CALCULATIONS |
| COORDINATE WITH BOTH TYPE OF POLE SUBMITTED AND SHOWN |
| ON PLANS. |
| |
| 6) NOTE: PLEASE KNOW THAT PART OF A PROVISO WHICH MAY |
| BE SET UP IS FOR THE PANEL SCHEDULE TO BE SPECIFIC TO |
| LOCATIONS. STATING *RECEPTACLES*, UPPER/LOWER ETC IS |
| NOT SPECIFIC. ALPHA/NUMERICAL DESIGNATIONS MAY USED AT |
| LATER DATE. |
| 408.4 |
| |
| 7) NOTE: PLEASE VERIFY THE RISER WHICH INDICATE 4 |
| PANELS YET ONLY THREE PANEL SCHEDULES WERE SUBMITTED |
| AND SHOWN. 215.5,408.4, 240.4, 240.21, 310.16. |
| CAN NOT VERIFY CODE COMPLIANCE IF THERE IS GOING TO BE |
| ANOTHER PANEL. |
| |
| 8) NOTE: PLEASE CLARIFY THE AIC RATING OF EACH PANEL. |
| STATES 10K, HOWEVER IS THIS FOR MAIN, BRANCH BREAKERS |
| OR BOTH? |
| |
| 9) NOTE: SERVICE EQUIPMENT SHALL BE ABOVE THE BASE |
| FLOOD ELEVATION. PLEASE OBTAIN THE BFE BASED ON FEMA |
| CHARTS. THIS IS FLOOD ZONE A. |
| |
| 10) NOTE: RISER SHOWS A 2-POLE SINGLE PHASE |
| INSTALLATION TO THE TRANSFORMER AND THE SAME TO THE |
| PANELS. ( GUTTER AS SHOWN). PLEASE EXPLAIN THE |
| GROUNDED/NEUTRAL CONDUCTORS BEING INSTALLED FROM THE |
| MAIN TO THE TRANSFORMER IF THIS IS A SEPARATELY DERIVED |
| SYSTEM? |
| 250.20,250.30,250.50,250.66 ETC |
| |
| |
| |
| IF THERE ARE ANY QUESTIONS; OR IF COMMENTS ARE NOT |
| TYPED IN A CLEAR MANNER PLEASE DO NOT HESITATE TO |
| CONTACT THIS REVIEWER. |
| |
| DEWEY PALMER |
| ELECTRICAL PLAN REVIEW II |
| CONSTRUCTION SERVICES DEPARTMENT |
| CITY OF WEST PALM BEACH |
| 561-805-6717 |
| [email protected] |
| |