Date |
Text |
2009-12-30 10:18:55 | FORMAL SUBMITTAL ACCEPTED AND PASSED |
| |
| PLEASE PROVIDE THE FOLLOWING INFORMATION REQUIRED FOR |
| SITE DEVELOPMENT APPROVAL PRIOR TO COMMENCEMENT OF SITE |
| WORK: |
| |
| 1. A COPY OF PERMIT ISSUED BY SOUTH FLORIDA WATER |
| MANAGEMENT DISTRICT (SFWMD) AND |
| |
| 2. COPY OF GEOTECHNICAL REPORT INCLUDING STORM WATER |
| QUALITY CALCULATIONS AND |
| |
| 3. FDEP NOTICE OF INTENT (NOI) FORM 62-621.300(4)(B) |
| AND |
| |
| 4. APPROVED MATERIALS LIST (AML) PER CWPB ENGINEERING |
| SERVICES AND SHOP DRAWINGS |
| |
| 5. EROSION CONTROL AND LAND STABILIZATION BOND PER |
| ORDINANCE 4060-07 AS IT PERTAINS TO THE EPA'S STORM |
| WATER POLLUTION PREVENTION PLAN'S (SWPPP) GUIDELINES. |
| THE BOND AMOUNT SHALL BE AT A RATE OF 110% OF THE TOTAL |
| OF THE SITE DEVELOPMENT PORTION OF THE CERTIFIED COST |
| ESTIMATE PROVIDED BY THE PROJECT CIVIL ENGINEER. |
| |
| TYPE OF SURETY BONDS ACCEPTED ARE A.) LETTER OF CREDIT |
| B.) BOND ISSUED BY A FLORIDA CERTIFIED SURETY COMPANY |
| C.) CERTIFIED BANK OR FINANCIAL INSTITUTION CHECK. |
| |
| THESE ITEMS ARE REQUIRED PRIOR TO THE TIME OF A |
| SCHEDULED AND CONFIRMED PRECONSTRUCTION MEETING WITH |
| ENGINEERING SERVICES AND CONTINGENT UPON APPROVAL OF |
| COMMENCEMENT OF ANY SITE DEVELOPMENT WORK. |
| |
| PLEASE ADDRESS ANY QUESTIONS TO THE PLAN REVIEWER |
| BELOW: |
| |
| EMERY P. FABIAN |
| ENGINEERING PROJECT COORDINATOR |
| ENGINEERING SERVICES DEPARTMENT |
| 401 CLEMATIS STREET, 4TH FLOOR |
| WEST PALM BEACH, FL 33401 |
| PHONE: 561-822-1200 |
| FAX: 561-494-1116 |
| EMAIL: [email protected] |