2009-12-30 10:18:55FORMAL SUBMITTAL ACCEPTED AND PASSED
  
 PLEASE PROVIDE THE FOLLOWING INFORMATION REQUIRED FOR
 SITE DEVELOPMENT APPROVAL PRIOR TO COMMENCEMENT OF SITE
 WORK:
  
 1. A COPY OF PERMIT ISSUED BY SOUTH FLORIDA WATER
 MANAGEMENT DISTRICT (SFWMD) AND
  
 2. COPY OF GEOTECHNICAL REPORT INCLUDING STORM WATER
 QUALITY CALCULATIONS AND
  
 3. FDEP NOTICE OF INTENT (NOI) FORM 62-621.300(4)(B)
 AND
  
 4. APPROVED MATERIALS LIST (AML) PER CWPB ENGINEERING
 SERVICES AND SHOP DRAWINGS
  
 5. EROSION CONTROL AND LAND STABILIZATION BOND PER
 ORDINANCE 4060-07 AS IT PERTAINS TO THE EPA'S STORM
 WATER POLLUTION PREVENTION PLAN'S (SWPPP) GUIDELINES.
 THE BOND AMOUNT SHALL BE AT A RATE OF 110% OF THE TOTAL
 OF THE SITE DEVELOPMENT PORTION OF THE CERTIFIED COST
 ESTIMATE PROVIDED BY THE PROJECT CIVIL ENGINEER.
  
 TYPE OF SURETY BONDS ACCEPTED ARE A.) LETTER OF CREDIT
 B.) BOND ISSUED BY A FLORIDA CERTIFIED SURETY COMPANY
 C.) CERTIFIED BANK OR FINANCIAL INSTITUTION CHECK.
  
 THESE ITEMS ARE REQUIRED PRIOR TO THE TIME OF A
 SCHEDULED AND CONFIRMED PRECONSTRUCTION MEETING WITH
 ENGINEERING SERVICES AND CONTINGENT UPON APPROVAL OF
 COMMENCEMENT OF ANY SITE DEVELOPMENT WORK.
  
 PLEASE ADDRESS ANY QUESTIONS TO THE PLAN REVIEWER
 BELOW:
  
 EMERY P. FABIAN
 ENGINEERING PROJECT COORDINATOR
 ENGINEERING SERVICES DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 PHONE: 561-822-1200
 FAX: 561-494-1116
 EMAIL: [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved