Date |
Text |
2009-08-13 09:14:15 | |
| ENGINEERING PREVIOUSLY LOOKED AT PLANS FOR RIGHT OF WAY |
| ELEMENTS" |
| |
| 08/12/09 |
| REVIEW FOR STORMWATER ELEMENTS AT 233 WENNONAH PLACE |
| STORM WATER CALCULATION WHERE RECEIVED 08/06/09 VIA FAX |
| FROM MR HALEY AS REQUESTED TO PROCEED WITH REVIEW. |
| COMMENTS TO JOHN HALEY, ENGINEER OF RECORD |
| #1 DISCHARGE FROM SITE BEGINS AT ELEV 9.50 (CALCS SHOW |
| AT ELEV 10.61) |
| #2 PROVIDE 100 YEAR STAGE VS BUILDING FINISH FLOOR |
| ELEVATION. |
| #3 PROVIDE PRE CONDITIONS VS POST CONDITION |
| CALCULATIONS. |
| #4 SHEET ONE DOES NOT AGREE WITH THE PLAN SHOWN ON SHT |
| 2 A (NO HANDICAP PARKING SHOWN) |
| #5 SHEET 2B PAVING AND DRAINAGE DETAILS: |
| PRECAST INLET TYPE "C" (OPTION) DETAIL NEEDS TO SHOW OR |
| STATE THAT ROCK UNDER STRUCTURE MUST BE WRAPPED IN |
| FILTER FABRIC |
| #6 SHEET 2B PAVING AND DRAINAGE DETAILS: |
| EXFILTRATION TRENCH DETAIL (OPTION) |
| REVISE NOTE #2 TO INCLUDE "BOTTOM" ALSO. |
| #7 SHEET 2B PAVING AND DRAINAGE DETAILS: |
| ADD TO 12"X12" SUMP A NOTE ADDING SS HARDWARE CLOTH |
| (MESH) AT SUMP ENTRY POINT. |
| #8 SHEET 2B PAVING AND DRAINAGE DETAILS: |
| REVISE NOTE #2 TO INCLUDE "BOTTOM" ALSO. |
| |
| MANUEL JULIAN GONZALEZ |
| ENGINEERING PROJECT COORDINATOR |
| ENGINEERING SERVICES DEPARTMENT |
| 401 CLEMATIS STREET, 4TH FLOOR |
| WEST PALM BEACH, FL 33401 |
| (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402) |
| MAIN PHONE: (561) 822-1200 |
| DIRECT: (561) 494-1085 |
| FAX: (561) 494-1116 |
| MOBILE: (561) 644-7301 |
| EMAIL: [email protected] |
| WWW.WPB.ORG/ENGINEERING |
| |