Date |
Text |
2008-10-22 09:06:59 | |
| ** DENIED REVIEW** |
| |
| |
| |
| |
| 1) NOTE: PLANS HAVE ONLY BEEN SUBMITTED FOR PLAN REVIEW |
| AND NOT FOR PERMIT. EVEN ONCE ALL COMMENTS HAVE BEEN |
| ADDRESSED AND PERMIT APPLICATION BY A LICENSED |
| CONTRACTOR HAS NOT BEEN MADE THE REVIEW WOULD STILL |
| REMAIN IN A FAILED STATUS. THERE ARE SEVERAL ITEMS FOR |
| LICENSING WHICH IS VERIFIED AT A LATER DATE WHEN |
| APPLICATION HAS BEEN MADE. |
| |
| 2) NOTE: THE PROJECT INFORMATION HAS BEEN SENT TO |
| ADDRESSING FOR REVIEW. THE PLANS DO NOT INDICATE ANY |
| ADDRESS ON THE TITLE BLOCKS AND TWO SEPARATE BUILDINGS |
| ARE BEING CONSTRUCTED. KEEP IN MIND IF THESE TWO |
| SEPARATE STRUCTURES ARE SUBMITTED ON THE SAME PLANS |
| UNDER ONE PERMIT A CERTIFICATE OF OCCUPANCY, |
| INSPECTIONS FINALS ETC WOULD BE FOR BOTH. IT WOULD NOT |
| BE POSSIBLE TO CO ONE WITH OUT THE OTHER. IF TWO PERMIT |
| APPLICATIONS ARE MADE, ONE FOR EACH BUILDING THIS WOULD |
| ALLOW EACH TO CONTAIN A CO ETC. |
| PLEASE BE SURE ONCE THE ADDRESS FOR EACH BUILDING IS |
| ASSIGNED THE TITLE BLOCKS REFLECT EACH. |
| 61G15-23.002, 61G1-16.004 |
| FBC 106.1, 106.5 |
| |
| 3) NOTE: PLEASE SUBMIT ENERGY CALCULATIONS AND LIGHTING |
| PERFORMANCE CALCULATIONS IN COMPLIANCE WITH THE FBC |
| 13-415.2.ABC.1.1, .1.2 AND .1.3. PLEASE SEE 13-400, |
| 13-415 ETC |
| AS NO CALCULATIONS OR PERFORMANCE CALCULATIONS WERE |
| SUBMITTED NO REVIEW OF THESE ITEMS COULD BE DONE. |
| |
| 4) NOTE: PLEASE BE SURE THE FOLLOWING CODES ARE LISTED |
| ON THE ELECTRICAL PLANS. |
| 2004 FBC W/2007 REVISIONS. |
| 2005 NFPA-70 |
| 2003 NFPA-101 |
| 2002 NFPA-110 |
| |
| 5) NOTE: PLEASE KNOW THAT ALL LOW VOLTAGE SYSTEMS ARE |
| REQUIRED TO BE UNDER A SEPARATE PERMIT. IF THE PLANS |
| SHOW ALL OF THE EQUIPMENT THEN THEY MAY BE REFERENCED |
| FOR A TURN AROUND PERMIT ONCE THE BASE BUILDING |
| PERMIT(S) ARE ISSUED. |
| |
| 6) NOTE: PLEASE SUBMIT THE MANUFACTURES SPECS/CUT |
| SHEETS FOR THE GENERATOR, ATS AND OTHER EQUIPMENT SUCH |
| AS THE FUEL TANK. THE FUEL TANKS WILL BE UNDER THE |
| REVIEW OF OTHER TRADES. |
| 110.3, 90.7 |
| FBC 106.1.2 |
| |
| 7) NOTE: PLEASE PROVIDE INFORMATION ON PLANS THAT THE |
| MOTORIZED GATES HAVE A FAIL SAFE OR BACK UP FOR |
| OPERATION IN THE EVENT OF POWER FAILURE. SEE FIRE |
| MARSHAL REVIEW. THIS IS NOTED AS THIS WILL AFFECT THE |
| ELECTRICAL PLANS. |
| |
| 8) NOTE: PLEASE PROVIDE A GROUNDING ELECTRODE |
| RISER/ATTACHMENT LOCATION FOR ALL TRANSFORMERS. |
| 250.66,250.50.250.58 ETC |
| |
| 9) NOTE: PLEASE SEE THE LIGHTING CONTROLS TO MEET FBC |
| 13-415.1.1, .1.2 AND .1.3 ARE IN QUESTION FOR MORE |
| INFORMATION. WHAT DOES THE SWITCH 1 DO? THE NOTE ON THE |
| PLANS MENTIONS OPERATION HOWEVER DOES THIS DEVICE STILL |
| CONTAIN AN AUTOMATED OPERATION TO TURN LIGHTING OFF |
| ONCE AN OCCUPANT IS NO LONGER IN THE SPACE? |
| PLEASE SEE THE BREAK ROOMS AND OTHER ROOMS SUCH AS |
| TRAINING ROOMS MUST MEET 13-415.1.ABC.1.2. ( AREAS 114, |
| 115 ETC) |
| IN LOCATIONS SUCH AS MULIT0GNAG BATH ROOMS PLEASE |
| INDICATE THE AUTOMATED DEVICES FOR LIGHTING CONTROLS |
| WITH DUAL TECHNOLOGY. IF DEVICE WAS MOTION ONLY THIS |
| WOULD AFFECT OTHER AREAS IN THE SAME BATHROOMS WHICH |
| MAY BE OCCUPIED YET NO MOTION COULD BE DETECTED. |
| |
| 10) NOTE: PLEASE INDICATE THE CIRCUITING FOR THE |
| EMERGENCY BATTERY BACK UP IN ROOM 117 (LADIES |
| BATHROOM). 700.12F |
| |
| 11) NOTE: PLEASE SUBMIT PHOTO-METRICS FOR EGRESS PATHS |
| UNDER EMERGENCY BACK UP CONDITIONS. THE LIGHTING LEVELS |
| UNDER NORMAL ARE NOT NEEDED AS THEY ARE CLEARLY |
| SUFFICIENT HOWEVER THE LIGHTING LEVELS UNDER EMERGENCY |
| IN SOME AREAS ARE IN QUESTION. PLEASE SEE NFPA-101 |
| 7.9.1 WHICH PERMITS 1FT CANDLE UNDER EMERGENCY |
| CONDITIONS. |
| FBC 106.1.1, 106.1.2 FOR ADDITIONAL INFORMATION AND |
| CLARIFICATION. |
| |
| 12) NOTE: PLEASE VERIFY ALL DISCONNECTING MEANS AT THE |
| DETACHED ROOF STRUCTURE PER 225.31-225.39. |
| ( MAY BE A SNAP SWITCH) |
| GROUNDING REQUIRED PER 250.32 ALREADY SHOWN. |
| |
| 13) NOTE: PLEASE CLARIFY THE SERVER ROOM. IF THIS IS AN |
| IT ROOM PLEASE BE SURE ALL ITEMS LISTED IN 645.2 ARE |
| MET IN ORDER FOR WIRING METHODS PERMITTED IN 645 TO BE |
| USED. IF THESE ITEMS ARE NOT MET THE WIRING METHODS |
| WHICH ARE PERMITTED IN 645 ARE NOT PERMITTED TO BE USED |
| AND THIS MAY AFFECT FUTURE EQUIPMENT INSTALLATION AND |
| WIRING. PLEASE PLACE NOTE ON PLANS THAT WILL STATE: |
| *THIS IS NOT AN IT ROOM AND WIRING METHODS OF NEC 645 |
| ARE NOT PERMITTED*. OR WORDS TO THAT AFFECT. |
| |
| 14) NOTE: PLEASE BE SURE LIGHT POLES ARE STATING THE |
| WIND LOAD RATINGS AS NOTED IN THE FBC. THE LIGHT POLE |
| CALCULATIONS WILL BE UNDER BUILDING/STRUCTURAL REVIEW. |
| THIS IS NOTED FOR INFORMATION ONLY. |
| |
| 15) NOTE: PLEASE COMPLETE ALL ROOM AND AREA |
| DESIGNATIONS ON PLANS. THIS MAY BE ALPHA OR NUMERIC. |
| MOST AREAS SHOW BOTH AT THIS TIME. |
| PLEASE BE SURE THE PANEL SCHEDULES ARE SPECIFIC TO |
| ROOMS AND AREAS IN WHICH THEY FEED. FOR EXAMPLE SIMPLY |
| STATING *RECEPTACLES* OR * LIGHTING* IS NOT ACCEPTABLE. |
| PLEASE SEE THE CHANGE IN THE 2005 NEC (HANDBOOK) WHICH |
| EXPLAINS THE CHANGE IN 408.4 FOR MORE SPECIFIC |
| DESIGNATIONS. THIS IS NOT ONLY FOR ON-SITE HOWEVER ALSO |
| FOR RECORD PLANS. |
| THIS WOULD INCLUDE THE CIRCUIT FOR ROLL UP DOOR AT |
| MAINT BUILDING. |
| FBC 106.1.1, 106.5 |
| |
| 16) NOTE: PLEASE SEE THE PLANS SHOW A CIRCUIT TO |
| GENERATOR ENCLOSURE HOWEVER BUT NOT FOR A PARTICULAR |
| PURPOSE. THE PLANS ALSO SHOW AT THE GENERATOR A |
| DESIGNATION TO THE PANEL HOWEVER NOT THE CIRCUIT. IF |
| THIS CIRCUIT IS FOR A BATTERY CHARGER, BLOCK HEATER ETC |
| PLEASE CHECK WITH THE MANUFACTURE OF ANY PARTICULAR |
| GENERATOR AS THEY ARE USUALLY DEDICATED CIRCUITS. BLOCK |
| HEATERS CAN BE AS HIGH AS 1500WATTS WHICH WOULD NOT |
| PERMIT THE BATTERY CHARGER TO BE ON THE SAME CIRCUIT. |
| 408.4, 220 ETC |
| FBC 106.1.2, 106.1.1 |
| |
| 17) NOTE: PLEASE SEE ELECTRICAL ROOM 109 AS THIS STATES |
| A LINE NOTE FROM THE TRANSFORMER TO *LP-OP2* HOWEVER |
| BASED ON RISER AND DESIGNATION ALREADY USED FOR |
| TRANSFORMER IN ROOM 113 THIS IS CONFUSING. |
| PLEASE CLARIFY HOW BOTH HAVE THE SAME DESIGNATION? |
| FBC 106.1.1, |
| NEC 230,450,215 ETC GENERAL COORDINATION |
| |
| 18) NOTE: PLEASE SUBMIT LOAD CALCULATIONS FOR THE |
| MDP-OP. AS NO LOADS ARE SHOWN IT IS NOT POSSIBLE TO |
| DETERMINE CODE COMPLIANCE FOR ALL EQUIPMENT INCLUDING |
| THE LOAD ON THE GENERATOR AND WHETHER OR NOT THE |
| GENERATOR IS OF SUFFICIENT SIZE. |
| 220, 702.5 ETC |
| FBC 106.1.1, 106.1.2 |
| PLEASE BE SURE TO INDICATE ALL CONTINUOUS LOADS AND |
| LARGEST MOTOR LOADS AT 125%. |
| 215.3,230.42 |
| |
| 19) NOTE: PLEASE KNOW AS THERE IS INFORMATION NOT YET |
| SUBMITTED FOR REVIEW THERE MAY VERY WELL BE NEW |
| COMMENTS ON THE FOLLOWING REVIEW WHICH CAN NOT BE MADE |
| AT THIS TIME. |
| |
| |
| |
| |
| |
| **IMPORTANT** |
| ONCE AUDIT/REVIEWS ARE COMPLETE AND PLANS ARE PICKED UP |
| FOR CORRECTIONS, PLEASE BE SURE TO COMPLETELY REMOVE |
| ALL OLD/VOIDED SHEETS AND ONLY INSERT NEW REVISED |
| SHEETS INTO TWO COMPLETE SETS FOR REVIEW AND STAMPING. |
| DO NOT LEAVE ANY OLD/VOIDED SHEETS IN SETS. |
| PLEASE DO NOT ATTACH SUPPORTING DOCUMENTS TO PLANS. ANY |
| ADDITIONAL DOCUMENTATION SUCH AS PRODUCT APPROVALS, |
| SPEC/CUT SHEETS, CALCULATIONS ETC SHOULD BE PLACED INTO |
| TWO SETS/FOLDERS/BINDERS ETC. |
| PLEASE KNOW ONLY ONE SET OF THE OLD/VOIDED SHEETS |
| SHOULD BE SUBMITTED FOR REFERENCE. |
| THIS WILL HELP IN THE AUDIT/REVIEW PROCESS AND AVOID |
| ANY DELAYS. |
| |
| |
| IF THERE ARE ANY QUESTIONS; OR IF COMMENTS ARE NOT |
| TYPED IN A CLEAR MANOR PLEASE DO NOT HESITATE TO |
| CONTACT THIS REVIEWER. |
| |
| |
| |
| DEWEY PALMER |
| ELECTRICAL PLAN REVIEW II |
| CONSTRUCTION SERVICES DEPARTMENT |
| CITY OF WEST PALM BEACH |
| 561-805-6717 |
| [email protected] |
| |