Date |
Text |
2008-09-24 09:21:48 | FAILED FOR FOLLOWING REASONS: |
| |
| 1. PLEASE SHOW ON DRAWINGS THE TURBIDITY DETAILS OF |
| POLLUTION PREVENTION . PLEASE SHOW ON DRAWINGS THE |
| TURBIDITY AROUND CATCH BASINS DURING CONSTRUCTION AND |
| ALL DEMOLITION PHASE. HEIGHT OF TURBIDITY BARRIER FENCE |
| SHOULD BE HIGH ENOUGH PER FDEP TO STOP DUST PARTICLES. |
| |
| 2. PLEASE PROVIDE A COPY OF BOND FOR ORDINANCE NO. |
| 4060-07: |
| |
| ALL DEMOLITION AND NEW CONSTRUCTION PERMITS, WITH |
| EXCEPTION OF SINGLE FAMILY, DUPLEX AND ACCESSORY |
| APARTMENT, SHALL POST BONDS OR DEPOSITS FOR THE |
| FOLLOWING: |
| |
| 1. EROSION CONTROL, AND |
| 2. LAND STABILIZATION |
| |
| THE AMOUNT OF THE EROSION CONTROL AND LAND |
| STABILIZATION BONDS SHALL BE DETERMINED BY THE ENGINEER |
| OF RECORD USING THE CURRENT CITY COST SCHEDULE AND |
| VERIFIED BY THE CITY'S ENGINEERING SERVICES DEPT. |
| PLEASE CONTACT BRIAN MOREE, ENG SERVICES CONSTRUCTION |
| SUPERVISOR, AT 561- 494 -1040 FOR MORE INFORMATION. |
| |
| UPON VERTICAL CONSTRUCTION COMMENCEMENT, PAYMENT IN |
| FULL OF ALL APPLICABLE FEES, AND COMPLIANCE WITH ALL |
| TERMS AND CONDITIONS OF ANY POSTED BOND, THE PERMITTEE |
| MAY REQUEST RELEASE OF THE BONDS OR DEPOSITS. |
| |
| A COPY OF ORDINANCE NO. 4060-07 MAY BE OBTAINED FROM |
| THE CITY CLERK'S OFFICE LOCATED ON THE FIRST FLOOR. |
| |
| 3. PLEASE SHOW ON DRAWINGS DUMPSTER & ITS ENCLOSURE |
| DETAILS PER CITY OF WPB, & LOCATION ON DWG, LOCATION |
| MUST BE ACCESSIBLE FOR PICKUP TRUCK. |
| |
| 4. PLEASE SHOW ON CALCULATION THAT YOU HAVE CONSIDERED |
| FLOOD ZONE AREA, & 5,10, 25, 100 YEAR FLOOD CRITERIA |
| AND CROWN OF THE ROAD WHEN YOU DETERMINE THE FIRST |
| FLOOR ELEVATION. FIRST FLOOR ELEVATION SHOULD BE |
| ATLEAST 1 FOOT HIGHER THAN HIGHEST CROWN OF THE ROAD. |
| |
| 5. PLEASE SHOW ON DRAINAGE DRAWING THE SITE AREA, |
| GREEN, LAKE,PARKING AREA, IMPERVIOUS,PERVIOUS AREA YOU |
| ARE DEVELOPING FOR THIS PROJECT . PLEASE MAKE SURE |
| THESE AREAS SHOWN ON DRAINAGE DRAWINGS MUST MATCH WITH |
| AND USED IN STORM WATER QUALITY CALCULATIONS. PLEASE |
| PROVIDE A COPY OF THESE CALCULATIONS. |
| |
| 6. PLEASE SHOW ALL STORM WATER PIPES AROUND YOUR SITE |
| SO, WE CAN SEE THE LAYOUT OF STORM WATER PIPES FROM ALL |
| OTHER STORM WATER PIPES. PLEASE SHOW DETAIL OF THE |
| CONTROL STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING |
| ELEVATION, ETC ON DRAWINGS, CALCULATION FOR |
| EXFILTRATION TRENCHES, PLEASE SHOW DRY DETENTION/WET |
| DETENTION AREAS IN STORM WATER CALS IF YOU HAVE ALL |
| THESE. PLEASE RESUBMIT GEO-TECH REPORT AND ALL |
| ENVRONMENTAL REPORT. |
| |
| 7. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST, AROUND |
| YOUR SITE FOR STORM WATER DRAIN SO YOUR SITE DO NOT GET |
| FLOODED AND HAVE ENOUGH DRAINS. |
| |
| 8. PLEASE PROVIDE A COPY OF GEO-TECH REPORT & STORM |
| WATER QUALITY CALCULATIONS TO 1000 45TH STREET FOR |
| THEIR APPROVAL BEFORE WE ISSUE A PERMIT. |
| |
| 9. WATER & SEWER PLANS MUST BE APPROVED FROM MANNY G. |
| OF 1000 45TH STREET BEFORE WE ISSUE A PERMIT. |
| |
| PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| PERMITTING PROCESS |
| |
| RASIK CHOKSHI 805-6723 |