Plan Review Notes
Plan Review Notes For Permit 08090166
Permit Number 08090166
Review Stop B
Sequence Number 2
Notes
Date Text
2008-11-06 11:39:04ELECTRICAL POLE BUILDING REVIEW SECOND CHECKLIST.
 REVIEW UNDER FBC 2004 WITH 2007 REVISIONS.
  
  
 ***NOTE: NONE OF THE COMMENTS FROM FIRST CHECKLIST WERE
 ADDRESSED. SEE COMMENTS BELOW:
  
 1- PROVIDE THE LIGHT POLE ENGINEERED CALCULATIONS AS
 REQUIRED BY NOTE ON LIGHT POLE DETAIL AND BY SEC. 1609
 OF FBC 2004.
  
 2- PROVIDE COMPLETE SPECIFICATIONS FOR PRE-STRESSED
 CONCRETE POLE TO VERIFY COMPLIANCE WITH THE ENGINEERED
 CALCULATIONS REQUIRED ON ITEM #1 ABOVE.
  
 3- VALUATION DECLARED IN THE PERMIT APPLICATION IS TOO
 LOW. NEED TO UPDATE PERMIT VALUATION TO INCLUDE ALL
 ENGINEERING FEES AND ALL CONTRACTOR LABOR AND MATERIALS
 AS REQUIRED BY SEC. 108.3 CITY AMENDMENTS TO FBC 2004.
  
 JULIO GOMEZ
 BUILDING PLANS EXAMINER
 (561)805-6712