2008-05-09 13:48:10 | FAILED FOR FOLLOWING REASONS: |
| |
| 1. YOUR NOTICE OF INTENT (NOI). IS O.K. |
| |
| 2. PLEASE SHOWSILT FENCE AROUND THE WHOLE SITE NOT |
| JUSTPARTIAL SITE. |
| |
| 3. PLEASE PROVIDE A COPY OF BOND FOR ORDINANCE NO. |
| 4060-07: |
| |
| ALL DEMOLITION AND NEW CONSTRUCTION PERMITS, WITH |
| EXCEPTION OF SINGLE FAMILY, DUPLEX AND ACCESSORY |
| APARTMENT, SHALL POST BONDS OR DEPOSITS FOR THE |
| FOLLOWING: |
| |
| 1. EROSION CONTROL, AND |
| 2. LAND STABILIZATION |
| |
| THE AMOUNT OF THE EROSION CONTROL AND LAND |
| STABILIZATION BONDS SHALL BE DETERMINED BY THE ENGINEER |
| OF RECORD USING THE CURRENT CITY COST SCHEDULE AND |
| VERIFIED BY THE CITY'S ENGINEERING SERVICES DEPT. |
| PLEASE CONTACT BRIAN MOREE, ENG SERVICES CONSTRUCTION |
| SUPERVISOR, AT 561- 494 -1040 FOR MORE INFORMATION. |
| |
| UPON VERTICAL CONSTRUCTION COMMENCEMENT, PAYMENT IN |
| FULL OF ALL APPLICABLE FEES, AND COMPLIANCE WITH ALL |
| TERMS AND CONDITIONS OF ANY POSTED BOND, THE PERMITTEE |
| MAY REQUEST RELEASE OF THE BONDS OR DEPOSITS. |
| |
| A COPY OF ORDINANCE NO. 4060-07 MAY BE OBTAINED FROM |
| THE CITY CLERK'S OFFICE LOCATED ON THE FIRST FLOOR. |
| |
| 4. PLEASEPROVIDE STORM WATER QUALITYCALCULATION & |
| GEOTECH REPORT TO 45 STREET, MR. JONATHAN BRAMLEY,P.E. |
| DIRECTOR,ENGINEERING SERVICES FOR THEIR APPROVAL |
| BEFORE WE ISSUE A PERMIT.PLEASE MAKE SURE YOU INCLUDE |
| IN CALCULATION THAT YOU HAVE CONSIDERED FLOOD ZONE |
| AREA, & 5,10, 25, 100 YEAR FLOOD CRITERIA AND CROWN OF |
| THE ROAD WHEN YOU DETERMINE THE FIRST FLOOR ELEVATION. |
| FIRST FLOOR ELEVATION SHOULD BE ATLEAST 1 FOOT HIGHER |
| THAN HIGHEST CROWN OF THE ROAD. |
| |
| PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| PERMITTING PROCESS |
| |