Date |
Text |
2007-10-25 10:40:40 | 2004 FBC W/2007 REVISIONS |
| REHAB SFR |
| |
| DENIED BY BUILDING |
| |
| 1) A RECORDED COPY OF THE NOTICE OF |
| COMMENCEMENT MUST BE SUBMITTED BEFORE A |
| PERMIT CAN BE ISSUED. |
| |
| 2) SUBMIT 2 COPIES OF THE SCOPE OF WORK DESCRIPTION. |
| FBC 106.1 CITY AMENDMENTS |
| |
| 3) SUBMIT 2 COPIES OF A FLOOR PLAN WITH A CORRESPONDING |
| WINDOW SCHEDULE SHOWING THE LOCATIONS OF THE WINDOWS |
| THAT ARE BEING REPLACED. CITY AMENDMENTS FBC 106.1.1 |
| AND 106.1.2. |
| |
| 4) THE AAMA CERTIFICATION THAT WAS SUBMITTED FOR THE |
| H-R SINGLE HUNG WINDDOWS SHOWS THAT IT EXPIRED ON JUNE |
| 20, 2007. THE REPORT ALSO NOTES THAT ALL CERTIFIED |
| WINDOWS MUST BE GLAZED WITH TEMPERED GLASS. PLEASE |
| CORRECT. FAC RULE 9B-72 |
| |
| 5)SHOW COMPLIANCE WITH FBC EXISTING BUILDING 505.1 |
| GENERAL. |
| MEANS OF EGRESS FOR BUILDINGS UNDERGOING ALTERATION |
| SHALL COMPLY WITH THE REQUIREMENTS OF SECTION 501.1 AND |
| THE SCOPING PROVISIONS OF CHAPTER 1 WHERE APPLICABLE. |
| EXCEPTION: DOOR AND WINDOW DIMENSIONS. IN RESIDENTIAL |
| DWELLINGS AND DWELLING UNITS, A MAXIMUM OF 5 PERCENT |
| REDUCTION IN THE CLEAR OPENING DIMENSIONS OF |
| REPLACEMENT DOORS AND WINDOWS SHALL BE ALLOWED. |
| |
| 6) FBC 507.3 IF REPLACING MORE THAN 25% OF THE |
| AGGREGATE AREA OF THE GLAZED OPENINGS IN THE DWELLING, |
| REQUIRES GLAZED OPENINGS TO BE IMPACT RESISTANT OR |
| PROTECTED WITH AN IMPACT RESISTANT COVERING. SUBMIT |
| PRODUCT APPROVALS FOR STORM PANELS OR IMPACT WINDOWS. |
| IF STORM PANELS WILL BE USED, SUBMIT A KEY PLAN AND |
| INSTALLATION SCHEDULE INDICATING THE MOUNT TYPE, ANCHOR |
| TYPE AND SPACING, EDGE DISTANCE GLASS SEPARATION, SPANS |
| ETC. SEE ATTACHED SAMPLE. |
| |
| 7) SUBMIT THE PRODUCT APPROVALS FOR THE 7 NEW WINDOWS |
| THAT THE OWNER HAS. IF THERE ARE NO PRODUCT APPROVALS |
| FOR THEM THEY CAN NOT BE INSTALLED. SEE FAC RULE |
| 9B-72. |
| |
| - ROBERT MCDOUGAL |
| BLDG. PLAN REVIEW |
| (561)805-6714 |
| [email protected] |
| |
| |