2007-10-05 14:12:58 | REVIEW #: 1 |
| ACTION: DENIED |
| |
| FBC 2004 CODE FAMILY W/ 2005 AND 2006 SUPPLEMENTS |
| FBC CH.1 AS AMENDED BY THE CITY OF WEST PALM BEACH |
| |
| 1. PG TS: PROJECT INFORMATION, ITEM 4 INDICATES |
| AIR-ZONA SYSTEMS AS THE MEP ENGINEER. HOWEVER, PG MP1.1 |
| IS SIGNED AND SEALED BY YV KULKARNI, PE. PLEASE CORRECT |
| INFORMATION ON FRONT PAGE. AIR-ZONA SYSTEMS |
| ENGINEERING, INC'S CERTIFICATE OF AUTHORIZATION IS |
| LISTED AS NULL AND VOID BY THE STATE OF FLORIDA DBPR. |
| |
| 2. MP1.1: UOTSIDE AIR CALCULATIONS REFERENCE THE 2003 |
| IMC. PLEASE CORRECTLY REFERENCE 2004 FBC,M IN |
| ACCORDANCE WITH FS 553.73. |
| |
| 3. MP1.1: OUTSIDE AIR CALCULATIONS REFERENCE AN EXHAUST |
| SCHEDULE. NO SUCH SCHEDULE COULD BE FOUND ON PLANS. |
| PROVIDE MISSING INFORMATION AS COMPLIANCE WITH FBC,M |
| TABLE 403.3 IS REQUIRED BY FBC,EB 609.1. |
| |
| 4. MP1.1: EXISTING HVAC EQUIPMENT SCHEDULE LISTS A |
| "CHILLED WATER SPLIT SYSTEM." THE EQUIPMENT SHOWN ON |
| PLANS IS EITHER A SPLIT SYSTEM OR PART OF A CHILLED |
| WATER SYSTEM. IT IS NOT BOTH. THE MODEL NUMBER LISTED |
| ON PLAN FOR AH-1 INDICATES THIS IS A CHILLED WATER |
| SYSTEM. THAT WOULD MEAN THAT THERE IS NO EXISTING ROOF |
| MOUNTED CONDENSING UNIT INVOLVED IN THE SCOPE OF THIS |
| WORK. ALSO, THERE IS NO AH-2 SHOWN ON PLANS. IT SHOULD |
| NOT BE ON THE EXISTING EQUIPMENT SCHEDULE. PLEASE MAKE |
| CORRECTIONS AND CLARIFY AS NEEDED TO ACCURATELY REFLECT |
| THE SCOPE OF WORK AND EXISTING CONDITIONS. FBC |
| 106.1.1. |
| NOTE: EXISTING CU-1 IS ALSO SHOWN OP PG E1.1. |
| COORDINATE ANY CORRECTIONS ON THIS PAGE WITH ELECTRICAL |
| PLANS. |
| |
| 5. MP1.1: PLAN SHOWS DUCT SMOKE DETECTOR IN RETURN DUCT |
| FOR UNIT SHUT DOWN. DUCT SMOKE DETECTORS SHALL BE |
| INSTALLED IN SUPPLY AIR SYSTEMS IN ACCORDANCE WITH |
| FBC,M 606.2.1. ALSO, DUCT DETECTOR(S) SHALL BE |
| CONNECTED TO THE BUILDING FIRE ALARM SYSTEM IN |
| ACCORDANCE WITH FBC,M 606.4.1. CONSULT LANDLORD |
| REGARDING CONNECTION TO EXISTING FIRE ALARM SYSTEM. |
| |
| 6. MP1.1: TOILET ROOM EXHAUST FANS SHALL BE |
| INTERCONNECTED WITH AH-1 TO ENSURE ALL AIR SUPPLIED TO |
| THESE SPACES IS EXHAUSTED IN ACCORDANCE WITH FBC,M |
| 403.2.1(3). PROVISIONS SHALL ALSO BE MADE TO ENSURE |
| THAT VENTILATION IS PROVIDED WHENEVER THESE SPACES ARE |
| OCCUPIED IN ACCORDANCE WITH FBC,M 401.3. |
| |
| 7. MP1.1: PROVIDE AIR BALANCE SCHEDULE SHOWING SUPPLY, |
| RETURN AND EXHAUST TOTALS. THE SPACE SHALL BE |
| PRESSURIZED WITH RESPECT TO THE OUTDOORS IN ACCORDANCE |
| WITH FBC 13-409.1.ABC.2. |
| |
| 8. MP1.1: PROVIDE SHUTOFF DAMPER CONTROLS FOR OUTSIDE |
| AIR INTAKE DUCT IN ACCORDANCE WITH FBC |
| 13-409.1.ABC.3.3. |
| |
| 9. MP1.1: CONDENSATE IS SHOWN DISCHARGING INTO A MOP |
| SINK. CONDENSATE DRAINS SHALL DISCHARGE TO AN APPROVED |
| PLACE OF DISPOSAL IN ACCORDANCE WITH FBC,M 307.2.1. A/C |
| CONDENSATE SHALL NOT DISCHARGE INTO THE SANITARY SEWER |
| SYSTEM IN ACCORDANCE WITH WPB MUNICIPAL CODE SECTION |
| 90-125(5). |
| |