2007-12-01 10:38:45 | DENIED |
| REFERENCE: FBC-2004 PLUMBING |
| FBC-2004 BUILDING |
| FBC-2004 CHAPTER 1 |
| FBC-2004 CHAPTER 11 |
| |
| PLAN REVIEW ONLY |
| |
| 1. SHT A-1 ROOM FINISH SCHEDULE FOR ROOMS 113, 115 & |
| 116. WALLS WITHIN 2 FEET OF WATER CLOSETS & URINALS |
| SHALL HAVE A SMOOTH, HARD, NONABSORBENT SURFACE PER |
| SECTION 1210.2. EPOXY PAINT OVER GWB IS NOT CONSIDERED |
| A HARD SURFACE. PLEASE SHOW COMPLIANCE. |
| |
| 2. SHT A-1 INDICATE TYPE OF WORK WILL BE DONE IN THE |
| WORKSHOP AND TYPE AND AMOUNT OF STORAGE IN THE STORAGE |
| AREA. SECTION 106.1.2. |
| |
| 3. SHT A-7 SHOW COMPLIANCE WITH THE FOLLOWING: ___FOR |
| THE URINAL: |
| A. 11-4.18.4 FLUSH CONTROLS (HEIGHT) |
| ___FOR LAVS: |
| A. 11-4.19.5 FAUCETS |
| ___FOR THE SHOWERS: |
| A. 11-4.21.3 SEAT HEIGHT |
| B. 11-4.21.5 CONTROLS |
| C. 11-4.21.7 CURBS (MAX 1/2") |
| |
| 4. SHT A-8 SHOW COMPLIANCE WITH THE FOLLOWING: ___FOR |
| SINKS: |
| A. 11-4.24.4 SINK DEPTH |
| B. 11-4.24.5 CLEAR FLOOR SPACE (FORWARD APPROACH |
| REQUIRED). |
| C. 11-4.24.6 EXPOSED PIPES & SURFACES |
| D. 11-4.24.7 FAUCETS |
| |
| 5. PER SECTION 11-4.1.3(10)(B) WHERE MORE THAN ONE |
| DRINKING FOUNTAIN IS PROVIDED, AT LEAST 50% SHALL BE |
| ACCESSIBLE. 3 DRINKING FOUNTAINS ARE SHOWN, 2 SHALL BE |
| ACCESSIBLE. |
| |
| 6. SHT P-1 THERE IS A NOTE THAT STATES 3" PVC PIPE FOR |
| FUTURE USE. SEE CONT. ON CIVIL DRAWINGS. THE PIPE IS |
| NOT SHOWN ON THE CIVIL PLANS. PLEASE CLARIFY WHAT THE |
| PIPE WILL BE DRAINING AND TO WHERE. SECTION 106.1.2 |
| (MORE INFORMATION REQUIRED). |
| |
| 7. SHT P-2 SANITARY RISER DIAGRAM DOES NOT REFLECT THE |
| FLOOR PLAN. THE STACK WITH THE DRINKING FOUNTAIN AND |
| SINK IN THE STORAGE/WORKSHOP AREA SHOWS 3 FIXTURES |
| CONNECTING TO THE STACK ON THE FLOOR PLAN, BUT ONLY TWO |
| FIXTURES, (P-9 & P-7), ON THE RISER DIAGRAM.--THE |
| FLOOR DRAIN IN THE JANITOR ROOM IS NOT SHOWN ON THE |
| RISER DIAGRAM BUT IS SHOWN ON THE FLOOR PLAN. PLEASE |
| CLARIFY AND CORRELATE THE RISER WITH THE FLOOR PLAN. |
| SECTION 106.1.1. |
| |
| 8. SHT P-2 AN RPZV BACKFLOW IS REQUIRED ON THE WATER |
| SERVICE TO THE BUILDING. INDICATE THE BACKFLOW ON THE |
| WATER RISER DIAGRAM PRIOR TO ENTERING THE BUILDING. |
| SECTION 608.13.2. |
| |
| 9. THERMAL EXPANSION CONTROL IS REQUIRED PER SECTION |
| 607.3.2. INDICATE METHOD. |
| |
| WHEN RESUBMITTING PLANS PLEASE INDICATE |
| THE REVISION & REMOVE & REPLACE ANY |
| PAGES AS NECESSARY. A TRANSMITTAL LETTER |
| LISTING THE ORIGINAL REVIEW COMMENT NUMBER, |
| WITH A DESCRIPTION OF THE REVISION |
| MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| PAGE WHERE THE CHANGES CAN BE FOUND |
| WILL HELP TO EXPEDITE YOUR PERMIT. REMOVE |
| ALL VOID SHEETS FROM ALL PLANS AND PLACE ONE |
| SET OF THEM LOOSELY ON TOP OF THE COLLATED |
| PLANS TO BE REVIEWED. THANK YOU FOR YOUR ANTICIPATED |
| COOPERATION. |
| |
| REVIEW BY KEN STEVENS |
| (561) 805-6721 |
| FAX (561) 805-6731 |
| E-MAIL [email protected] |