Plan Review Notes
Plan Review Notes For Permit 07061019
Permit Number 07061019
Review Stop E
Sequence Number 1
Notes
Date Text
2007-07-16 08:07:25 
  
  
 NONCOMPLIANT
  
 PLEASE MAKE THE FOLLOWING CORRECTIONS
 FOR CODE COMPLIANCE AND RESUBMIT FOR
 REVIEW.
  
 1} THE VALUE ON THE APPLICATION MUST
 INCLUDE THE TOTAL COST OF LABOR AND
 MATERIAL FOR THE GENERATOR, EQUIPMENT
 (TRANSFER SWITCHES, PANELS ETC.)
 AND PAD PER 108.3 FBC AS AMENDED.
 INCREASE THE VALUE AT THE COUNTER WHEN RESUBMITTING,
 AND GET A RECEIPT FROM THE
 PERMIT CLERK.
  
 2} PROVIDE MANUFACTURERS SPECIFICATIONS
 INDICATING RECOMMENDED SETBACKS AND
 ELECTRICAL SPEC'S FOR THE GENERATOR AND
 TRANSFER SWITCH.
  
 3} PROVIDE A RISER DIAGRAM PER 215.5
 INCLUDING GENERATOR AND RELATED
 EQUIPMENT. THE METER IS NOT SHOWN ON THE PLAN
  
 4} PLEASE NOTE A DISCONNECT IS REQUIRED
 PER 225.31 AND 32. INDICATE LOCATION ON
 THE RISER AND SITE PLAN. THE TRANSFER
 SWITCH MAY NOT MEET THIS REQUIREMENT,
 SEE SPECS BEFORE SUBMITTING.
  
 5} PROVIDE A LOAD CALCULATION FOR THE
 LOAD INTENDED TO BE SERVED. 215.5.PER ARTICLE 220 PART
 III, STANDARD OR PART IV OPTIONAL, INDICATE METHOD
 USED.
  
 IF THERE ARE ANY QUESTIONS PLEASE CALL.
  
 BILL TROBAUGH
 ELECTRICAL PLAN REVIEW
 561/805-6718
 [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved