2007-03-23 19:07:13 | ****** UNSAT ****** |
| |
| ** PLEASE KNOW THAT AS SOME INFORMATION HAS NOTYET |
| BEEN SUBMITTED FOR REVIEW YET THERE MAY VERY WELL BE |
| NEW COMMENTS ON THE NEXT REVIEW. |
| |
| ** PLEASE KNOW THAT ANY REFERENCE TO THE FBC CHAPTER 1 |
| IN THE PLAN REVIEW COMMENTS CAN BE FOUND IN THE |
| ADMINISTRATIVE SECTION OF THE 2004 FBC AS ADOPTED BY |
| THE CITY OF WEST PALM BEACH. |
| |
| |
| 1) NOTE: PLEASE KNOW THAT ANY PERMIT APPLICATIONS WHICH |
| ARE SUBMITTED AFTER DECEMBER 8TH, 2006 PLACES PROJECTS |
| UNDER THE NEW CODES ADOPTED BY THE STATE. |
| PLEASE SEE THAT THIS SHALL INCLUDE 2006 REVISIONS TO |
| THE 2004 FBC FOR ALL TRADES AND THE 2005 NFPA-70. |
| PLEASE KNOW THERE ARE CHANGES IN THE FBC WHICH MAY |
| AFFECT DESIGNS FOR ALL TRADES. |
| PLEASE LIST THE FOLLOWING ON ELECTRICAL SHEETS FOR THIS |
| REVIEWER AT A MINIMUM. |
| 2004 FBC W/ 2006 REVISIONS. |
| 2005 NFPA-70 |
| 2002 NFPA-72 |
| 2003 NFPA-101 |
| 2003 NFPA-20 |
| 2002 NFPA-110 |
| ** SOME OF THESE CODES MAY BE PRESENT ON PLANS HOWEVER |
| PLEASE VERIFY THE CODES AND SEE COMMENTS FROM OTHER |
| TRADES WHICH MAY AFFECT THIS NOTE. |
| ** PLEASE SEE COMMENTS IN REVIEW WITH RESPECT TO SOME |
| AREAS OF PLANS WHICH REFLECT THE SOUTH FLORIDA BUILDING |
| CODE SFBC. THIS HAS NOT BEEN IN EFFECT SINCE 3/1/02. |
| |
| 2) NOTE: PLEASE SEE THE *S* SHEETS WHICH IS MISSING |
| INFORMATION ON TITLE BLOCKS FOR FIRM. PLEASE SEE |
| MISSING THE CERTIFICATE OF AUTHORIZATION NUMBER AS |
| REQUIRED PER FAC 61G15-23.002, AND FS 471.023. THIS IS |
| REQUIRED WHETHER OR NOT COMMENT IS MADE BY OTHER |
| REVIEWER(S). |
| |
| 3) NOTE: PLEASE SEE TITLE BLOCK FOR GARTEK ENGINEERING |
| IS SMALL AND INFORMATION IS NOT CLEAR. PLEASE SEE TITLE |
| BLOCK AND ADJUST FONT/PRINTING. |
| |
| 4) NOTE: PLEASE PROVIDE PHOTO-METRICS FOR STAIR TOWERS |
| WHICH INDICATE THE MINIMUM OF 10FT CANDLES UNDER NORMAL |
| AND 1FT CANDLE UNDER EMERGENCY CONDITIONS. |
| PLEASE ALSO SEE THE FIXTURES AS SHOWN DO NOT PROVIDE |
| ENOUGH INFORMATION FOR TYPE OF FIXTURE. PLEASE SEE A |
| BATTERY BACK UP FIXTURE WILL BE REQUIRED FOR THE |
| MINIMUM LEVELS FOR EGRESS UNDER EMERGENCY CONDITIONS. |
| PLEASE SEE LS 101 7.8, 7.9, 7.8.1.3, 7.9.2.2. PLEASE |
| SEE THAT THE FAILING OF A SINGLE DEVICE, OCP, SWITCH |
| ETC SHALL NOT LEAVE ANY ONE EGRESS AREA IN TOTAL |
| DARKNESS. |
| PLEASE INDICATE ON PLANS IF THE EXISTING GENERATOR |
| ROOM, FIRE PUMP ROOM AND MAIN ELECTRICAL ROOM CONTAIN |
| EMERGENCY BATTERY BACK UP FIXTURES OF SOME TYPE. IF |
| EXISTING PLEASE SHOW, IF NOT, PLEASE KNOW THESE WILL BE |
| REQUIRED. |
| NEC 700.12E, 700.16, NFPA-101101 7.8, 7.9, NFPA-110 |
| 7.3.1 |
| |
| 5) NOTE: PLEASE SEE THE FA SHEETS AS THESE INDICATE THE |
| HORN AND STROBE DEVICES FROM THE SFBC AND OTHER CODES |
| WHICH ARE NO LONGER IN EFFECT. |
| PLEASE SEE THE MINIMUM LEVELS FOR THESE DEVICES SHALL |
| BE STATED PER FBC 2004 11-4.28.1,.2 AND .3(4). |
| |
| 6) NOTE: PLEASE SEE THE *CODED NOTES* FOR THE PARKING |
| BOOTHS DO NOT PROVIDE THE MINIMUM CIRCUITING FOR THE |
| NEW ELECTRICAL WHICH IS BEING INSTALLED AT BOOTHS. DO |
| THEY INCREASE IN LOAD? ARE THESE GOING TO BE NEW UNITS |
| WHICH WILL CONTAIN ALL NEW ELECTRICAL AND PANELS? |
| PLEASE PROVIDE MORE INFORMATION. |
| FBC 106.1.2 |
| |
| 7) NOTE: PLEASE SUBMIT A COMPLETE FIXTURE LEGEND OF ALL |
| FIXTURES AND CORRELATE WITH PLANS. |
| PLEASE ALSO SEE THE 2004 FBC W/ 2006 REVISIONS TO |
| CHAPTER 13 FOR THE POWER ALLOWANCES PERMITTED AND |
| PERFORMANCE CALCULATIONS PER 13-415.2. |
| PLEASE PROVIDE WORST CASE VOLTAGE DROP PER |
| 13-413.1ABC.1 FOR BRANCH CIRCUITS INSTALLED AS NEW. |
| PLEASE SEE ALL OF CHAPTER 13 FOR LIGHTING AND |
| CONTROLS. |
| PLEASE SEE THAT NOT ENOUGH INFORMATION IS PROVIDED FOR |
| LIGHTING CONTROLS, PANELS, SCHEDULING ETC. |
| FBC 106.1.2 |
| |
| 8) NOTE: PLEASE SUBMIT WIND LOADS FOR ROOF TOP LIGHTING |
| POLES SHOWING THE MINIMUM LOADS FOR POLES AND FIXTURES |
| WITH THEIR EFFECTIVE PROJECTED AREAS (EFA) TO MEET THE |
| MINIMUM OF THE FBC 140 MPH WIND LOADS. |
| THIS INFORMATION WILL BE REVIEWED BY THE STRUCTURAL |
| PLANS EXAMINER. |
| FBC 106.1.2 |
| |
| 9) NOTE: PLEASE SUBMIT COMPLETE MANUFACTURE'S SPECS/CUT |
| SHEETS FOR ALL NEW EQUIPMENT BEING INSTALLED FOR THE |
| GENERATOR, FIRE PUMP, FIRE PUMP CONTROLLER, AND ATS(S) |
| . |
| PLEASE SEE THERE ARE SEVERAL ITEMS WHICH NEED TO BE |
| REVIEWED FOR CODE COMPLIANCE WHICH CAN NOT BE DONE AT |
| THIS TIME. |
| PLEASE ALSO BE SURE ALL INFORMATION SUBMITTED CONTAINS |
| LISTINGS FROM ANRTL. |
| 110.3, 90.7. |
| |
| 10) NOTE: PLEASE PROVIDE NOTES ON RISER FOR SIGNAGE AS |
| REQUIRED PER 230.2E, 700.8, 701.9 ETC. |
| |
| 11) NOTE: PLEASE SEE THAT IT IS UNCLEAR WHAT IS BEING |
| DONE WITH THE GENERATOR. IS THIS UNIT GOING TO BE NEW |
| OR EXISTING TO REMAIN? |
| PLEASE SEE THE RISER SEEMS TO SHOW UNIT AS GAS AND |
| DIESEL? PLEASE CLARIFY IS THIS NATURAL GAS? OR |
| GASOLINE? PLEASE VERIFY. |
| PLEASE SUBMIT THE FUEL CONSUMPTION RATE FOR THE |
| GENERATOR AT FULL LOAD INCLUDING THE LOAD OF THE FIRE |
| PUMP AT 100%. |
| PLEASE SEE NFPA-20 9.6.2.2. |
| PLEASE SEE 701.11B3 |
| |
| 12) NOTE: PLEASE SUBMIT ONLY ONE ELECTRICAL RISER WHICH |
| WILL BE ON THE PERMITTED RECORD SET OF PLANS. IF THE |
| OTHER OPTION (1 OR 2) IS DONE INSTEAD THEN REVISED |
| PLANS WILL BE REQUIRED THAT TIME. THE RECORD SET OF |
| PLANS MUST CONTAIN ONE OPTION. |
| PLEASE KNOW THE REVIEW WILL BE DONE ON THE ONE |
| SUBMITTED. |
| |
| 13) NOTE: PLEASE SEE RISER AS IT APPEARS TO SHOW THE |
| SERVICE ENTRANCE CONDUCTORS BEING RUN OVER HEAD TO THE |
| FIRE PUMP/FPC. |
| PLEASE SEE NFPA-70 695.6A AS THESE WILL BE REQUIRE DOT |
| BE RUN OVER HEAD IF THIS IS THE CASE. |
| PLEASE ALSO SEE NFPA-20 9.3.1* |
| |
| 14) NOTE: PLEASE BE SURE INFORMATION IS PROVIDED ON |
| PLANS FOR THE LOCKED ROTOR OVER CURRENT PROTECTION ON |
| THE PRIMARY SIDE OF THE FIRE PUMP. |
| PLEASE SEE 695.4B1, NFPA-20 9.3.2.2.3.2 |
| PLEASE ALSO SEE OTHER SECTIONS UNDER 9.3 FOR THE FPC. |
| |
| 15) NOTE: PLEASE SEE THE CONDUCTORS TO THE FPC FROM FPL |
| AS THESE ARE NOT SHOWING A NEUTRAL CONDUCTOR TO THE |
| FIRST MEANS OF DISCONNECT WHICH IS REQUIRED. THIS |
| CONDUCTOR IS REQUIRED TO TERMINATE IN THIS FPC. PLEASE |
| ALSO KNOW THAT THERE MAY VERY WELL BE THE NEED FOR THE |
| NEUTRAL IN THE FPC. THE MANUFACTURE MAY REQUIRE FOR |
| CONTROLS. |
| PLEASE SEE THAT THE GENERATOR IS BEING NOTED AS A |
| SEPARATELY DERIVED SYSTEM AS REQUIRED, PLEASE VERIFY IF |
| THE NEUTRAL WILL BEBROUGHT FROM THE GENERATOR AS IF |
| THIS IS A SD GENERATOR THEN THIS FPC WILL CONTAIN A |
| FOUR POLE ATS. |
| PLEASE SEE THE FOLLOWING COMMENT. |
| PLEASE SEE RISER IS CURRENTLY SHOWING *EQUIPMENT |
| GROUNDING CONDUCTOR* FROM THE FPL TRANSFORMER ETC. |
| PLEASE SEE 250.6 FOR OBJECTIONABLE CURRENTS AS THE |
| NEUTRAL IS REQUIRED TO BE BONDED AT THE FIRST MEANS OF |
| DISCONNECT. 250.24. |
| 250.30, 250.20 ETC. |
| PLEASE SEE THE FPC SEEMS TO SHOW A GROUNDING ELECTRODE |
| BY ITSELF WITHOUT ANY CONNECTIONTO A MINIMUM |
| SYSTEM(S) PER 250.50 OR BONDING TO THE OTHER SERVICES? |
| PLEASE VERIFY THIS. |
| 250.92, 250.94, 250.66 |
| PLEASE PROVIDE MORE INFORMATION. |
| FBC 106.1.2 |
| |
| 16) NOTE: PLEASE SEE ALTHOUGH GF PROTECTION IS NOT |
| REQUIRED ON THE EMERGENCY SIDE OF THE EMERGENCY SYSTEM |
| AND LEGALLY REQUIRED SYSTEMS, PROPER GROUND FAULT |
| SENSING IS REQUIRED. |
| PLEASE SEE NFPA-110 6.2.15** ISOLATION OF NEUTRAL |
| CONDUCTORS. PROVISIONS SHALL BE INCLUDED FOR ENSURING |
| CONTINUITY, TRANSFER, AND ISOLATION OF THE PRIMARY AND |
| THE EPS NEUTRAL CONDUCTORS WHEREVER THEY ARE SEPARATELY |
| GROUNDED TO ACHIEVE GROUND-FAULT SENSING. |
| PLEASE SEE AN ATTACHED BRIEF EXPLANATION FROM *ASCO* |
| WHITE PAPER: WHERE GROUND FAULT PROTECTION IS TRIGGERED |
| BY THE CODE AND AN ALTERNATE POWER SUPPLY IS INCLUDED, |
| SWITCHING OF THE NEUTRAL BECOMES NECESSARY. THE CIRCUIT |
| SHOWN ABOVE ILLUSTRATES SUCH A CIRCUMSTANCE. THE |
| SERVICE IS LARGER THAN 1,000 AMPS. CONSEQUENTLY, GROUND |
| FAULT PROTECTION IS REQUIRED AT THE MAIN SERVICE |
| DISCONNECT AT A MINIMUM. IF IT IS INSTALLED THERE AND |
| THE GENERATOR NEUTRAL GROUNDING WAS THROUGH A SOLID |
| CONNECTION TO THE MAIN SERVICE NEUTRAL, A GROUND FAULT |
| WHEN THE GENERATOR IS FEEDING THE LOAD WILL CAUSE THE |
| MAIN SERVICE DISCONNECT TO OPEN. THIS WILL NOT |
| DISCONNECT THE ARCING FAULT FROM THE GENERATOR. |
| COORDINATION IS THUS LOST." |
| PLEASE KNOW BASED ON THE INFORMATION FROM SEVERAL OTHER |
| MANUFACTURES ALSO AND THE CODE PLEASE BE SURE THE |
| MANUFACTURES SPECS TO BE SUBMITTED ARE INDEED 4POLE ATS |
| DEVICES AS NOTED FOR EACH RISER MENTIONS. |
| PLEASE VERIFY THE FPC/ATS. |
| PLEASE ALSO SEE GENERATOR GROUNDING DETAIL WILL BE |
| REQUIRED TO BE REVISED. |
| PLEASE SEE 250.20, 250.30, 250.66, 240.13, 230.95, |
| 700.7D, 700.26 |
| |
| 17) NOTE: PLEASE CORRELATE PLANS AS THE ELECTRICAL |
| PLANS INDICATE A 150HP 480V FIRE PUMP AND THE FIRE |
| PROTECTION SHEETS INDICATE A 125HP 480V PUMP. PLEASE |
| KNOW AT THIS TIME REVIEW OF THE RISER CONDUCTORS CAN |
| NOT BE DONE AS IT IS NOT KNOWN WHICH ONE IS BEING |
| INSTALLED. |
| FBC 106.1.2 |
| |
| 18) NOTE: PLEASE SHOW ALL CONTINUOUS LOADS AT 125%. |
| PLEASE INCLUDE LOAD CALCULATIONS FOR INCREASED LOADS IN |
| A LOAD SUMMARY. |
| 215.5,215.3, 230.42. AND 220. |
| FBC 106.3.5.1.2 |
| |
| 19) NOTE: PLEASE SEE OPTION #2 AS IT STILL INDICATES |
| 400AMP OCP ON THE 400AMP FEEDERS TO THE 200AMP ATS?? |
| AND 200AMP DISCONNECT ETC. |
| PLEASE VERIFY AND COORDINATE. |
| |
| ** IMPORTANT** |
| ONCE ALL REVIEWS ARE DONE AND PLANS ARE |
| PICKED UP FOR CORRECTIONS, PLEASE BE |
| SURE TO COMPLETELY REMOVE ALL OLD/VOIDED |
| SHEETS AND ONLY INSERT NEW REVISED |
| SHEETS INTO TWO COMPLETE SETS FOR REVIEW |
| AND STAMPING. DO NOT LEAVE ANY |
| OLD/VOIDED SHEETS IN SETS. |
| PLEASE KNOW ONLY ONE SET OF THE |
| OLD/VOIDED SHEETS SHOULD BE SUBMITTED |
| FOR REFERENCE. |
| THIS WILL HELP IN THE REVIEW PROCESS AND |
| AVOID ANY DELAYS. |
| |
| ** PLEASE BE SURE TO CALL IF THERE ARE ANY QUESTIONS OR |
| COMMENTS WITH RESPECT TO THE TYPED COMMENTS ABOVE. IF |
| THERE ARE ANY COMMENTS WHICH ARE NOT CLEAR IN ANY WAY, |
| NOT UNDERSTOOD OR NOT TYPED IN A CLEAR MANOR, PLEASE DO |
| NOT HESITATE IN CONTACTING THIS OFFICE AND THIS |
| REVIEWER. |
| |
| DEWEY PALMER |
| ELECTRICAL PLAN REVIEW II |
| CONSTRUCTION SERVICES DEPT. |
| CITY OF WEST PALM BEACH |
| 561-805-6717 |