2007-07-24 10:31:06 | ***FAILED**** PLEASE PROVIDE THE FOLLOWING: |
| |
| 1. PLEASE PROVIDE A COPY OF NOTICE OF INTENT (NOI). |
| PLEASE APPLY AT FDEP, NPDES STORMWATER SECTION FOR |
| NOI. |
| YOU CAN GET NOI INFO FROM |
| WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/ |
| NOTICE OF INTENT DEP FORM 62-621.300(4)(B), |
| EFFECTIVE MAY 1, 2003 |
| 2. FIRST FLOOR ELEVATION, CENTER LINE OF ROAD , |
| SIDEWALK ELEVATION MUST MEET FLOOD ZONE AREA OF YOUR |
| SITE, & 5,10, 25, 100 YEAR FLOOD CRITERIATO DETERMINE |
| THE FIRST FLOOR ELEVATION, HOW DID YOU COME UP THE |
| FIRST FLOOR ELEVATION,PLEASE SHOW THATIN YOUR STORM |
| WATER CALCULATION.WE COULD NOT FIND WATER QUALITY |
| CALS THAT YOU SAID YOU HAVE SUBMITTED. WE NEED A |
| SEPARATE COPY OF WATER QUALITY CALS FOR THIS PROJECT TO |
| KEEP IN THIS FILE. |
| 3. MAKE SURE THESE SITE AREAS SHOWN ON DRAWINGS MUST |
| MATCH WITH AREAS USED IN STORM WATER QUALITY |
| CALCULATIONS. |
| 4.WE COULD NOT FIND A COPY OF SFWMD PERMIT & A WATER |
| QUALITY CALS THAT YOU SAID YOU SUBMITTED THIS TIME. WE |
| SAW YOUR GEO TECH REPORT BUT WE COULD NOT FIND SOIL |
| CONDUCTIVITY USED IN EXFILTRATION TRENCH. PLEASE |
| RESUBMIT REVISED GEO TECH REPORT. |
| 5. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVED |
| 6. PLEASE PROVIDE LATEST COPY OF SET OF CIVIL DRAWINGS |
| WHEN YOU RESUBMIT. |
| |
| PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| PERMITTING PROCESS |
| |
| RASIK CHOKSHI805-6723 |