2007-01-02 09:00:02 | *** DENIED *** |
| 1) ENERGY CALCULATIONS NEED TO BE SIGNED BY OWNER/AGENT |
| ALSO, PER 2004 FBC 13-600.3.ABC.2. |
| |
| 2) PLEASE SUBMIT TWO COPY'S OF THE ENERGY CALCULATIONS |
| AND MANUAL J CAL'S. |
| |
| 3) PLEASE SHOW LOCATION OF CLOTHES DRYER VENT |
| TERMINATION ON MECHANICAL PLANS, INFORMATIONAL VENT MAY |
| NOT DISCHARGE NEAR THE A/C CONDENSER UNIT, PER 2004 |
| FBC/M 501.2 . |
| |
| 4) DOOR TO LAUNDRY ROOM NEEDS TO BE LOUVERED OR A GRILL |
| NEEDS TO BE INSTALLED FOR RETURN AIR, PLEASE SHOW ON |
| MECHANICAL PLANS. |
| |
| 5) RETURN AIR TRANSFER DUCT TO MASTER SUITE NEEDS TO BE |
| LARGER THAN 12". BALANCED RETURN AIR MAY BE ACHIEVED |
| BY. |
| (A)TRANSFER DUCTS MAY ACHIEVE THIS BY |
| INCREASING THE RETURN TRANSFER ONE AND |
| ONE HALF TIMES THE CROSS SECTIONAL AREA |
| (SQUARE INCHES) OF THE SUPPLY DUCT |
| ENTERING THE ROOM OR SPACE IT'S SERVING |
| AND THE DOOR HAVING AT LEAST AN |
| UNRESTRICTED 1 INCHUNDERCUT TO ACHIEVE |
| PROPER RETURN AIR BALANCE. |
| (C)HABITABLE ROOMS ONLY SHALL BE |
| REQUIRED TO MEET THESE REQUIREMENTS FOR |
| PROPER BALANCED RETURN AIR EXCLUDING |
| BATHROOMS, CLOSETS, STORAGE ROOMS AND |
| LAUNDRY ROOMS, EXCEPT THAT ALL SUPPLY |
| AIR INTO THE MASTER SUITE SHALL BE |
| INCLUDED. PER 2004 FBC/R M1602.4 . |
| |
| MECHANICAL PLAN REVIEW BY; |
| TOM GORDON (561) 805-6729. |