2007-01-26 09:34:51 | PLEASE PROVIDE FOLLOWING INFO: |
| |
| 1. PLEASE SHOW STANDARDS NOTES OF CITY OF WPB ON |
| DRAWINGSFOR SIDEWALK WIDTH , ITS SLOPE, DRIVEWAY, |
| PARKING, HANDICAP PARKING, PAINTPER CITY CODES ETC.,, |
| MUST MEET PER ADA,,ETC., |
| 2. PLEASE SHOW ON DRAWINGSDUMPSTER & ITS ENCLOSURE |
| DETAILS PER CITY OF WPB, &LOCATION ON DWG, LOCATION |
| MUST BE ACCESSIBLE FOR PICKUP TRUCK. |
| 3. FIRST FLOOR ELEVATION, CENTER LINE OF ROAD , |
| SIDEWALK ELEVATION MUST MEET FL BLDG CODE, PLEASE SHOW |
| ON THE DRAWINGS. |
| 4. PLEASE PROVIDE A COPY OF SFWMD PERMIT,GEOTECH |
| REPORT |
| 5.PLEASE SHOW STORM WATER CALCULATIONS, WHAT CRITERIA |
| YOU ASSUMEDFOR RUNOFF CAL.,, LIKE 1" OVER ENTIRE SITE |
| OR2.5"CRITERIA, ?PERVIOUS AREA, LIKE GREEN, |
| LAKES, ETC,IMPERVIOUS AREA CAL., |
| 6. WHAT IS THE SITE AREA, YOU ARE DEVELOPING FOR THIS |
| PROJECT ONLY ? SO, WE CAN CHECK PERVIOUS, IMPERVIOUS |
| CAL. |
| 7. HOW YOU CONNECT TO THE STORM WATER PIPES IN YOUR |
| SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER PIPES |
| AROUND YOUR SITE SO, WE CANSEE THE BEST PIPE TO |
| CONNECT WITH THE STORM WATERFROM ALL OTHER STORM |
| WATER PIPES. PLEASE SHOW DETAIL OF THE CONTROL |
| STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING |
| ELEVATION, ETC CALS OF EXFILTRATION TRENCH LENGTH? |
| 8. POLLUTION PREVENTION DETAILS,CLOTHES USED FOR SILT |
| ETC., PLANS SHOWING SILT FENCE AROUND THE SITE |
| 9. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVED |
| 10. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND |
| YOUR SITE FOR STORM WATER DRAIN. |
| |
| PLEASE RESPOND EACH ITEM IN DETAIL IN A MEMO & ON |
| DRAWINGS WITH REVISIONS TO EXPEDITE YOUR PERMITTING |
| PROCESS |
| |
| RASIK CHOKSHI805-6723 |