Plan Review Notes
Plan Review Notes For Permit 06110497
Permit Number 06110497
Review Stop M
Sequence Number 1
Notes
Date Text
2006-11-28 16:01:42*** DENIED ***
 1) DUE TO THE 1000 GAL. FUEL TANK THE PLANS NEED TO BE
 APPROVED BY THE FL. DEPT. OF ENVIRONMENTAL PROTECTION
 (2300 N. JOG RD. W.P.B. (561) 233-2400) BEFORE APPLYING
 FOR PERMIT.
  
 2) INFORMATIONAL ONLY. PER 2004 FBC, FUEL GAS -
 POWERED
 EQUIPMENT - PERMANENTLY INSTALLED
 EQUIPMENT POWERED BY INTERNAL COMBUSTION
 ENGINES SHALL BE INSTALLED IN ACCORDANCE
 WITH MANUFACTURER'S INSTALLATION
 INSTRUCTIONS AND NFPA 37.
  
 NFPA 37 INSTALLATION & USE OF STATIONARY COMBUSTION
 ENGINES & GAS TURBINES:
 4.1.4ENGINES (GENERATORS) LOCATED
 OUTDOORS SHALL BE MINIMUM OF 5 FT FROM
 OPENINGS IN WALLS & AT LEAST 5 FT FROM
 STRUCTURES HAVING COMBUSTIBLE WALLS.A
 MINIMUM CLEARANCE IS NOT REQUIRED WHEN
 (1) THE ADJACENT WALL HAS A MINIMUM FIRE RESISTANCE
 RATING OF 1 HOUR OR (2) THE WEATHERPROOF ENCLOSURE IS
 CONSTRUCTED OF NON-COMBUSTIBLE MATERIALS, AND IT HAS
 BEEN DEMONSTRATED THAT A FIRE WITHIN THE
 ENCLOSURE WILL NOT IGNITE COMBUSTIBLE
 MATERIALS OUTSIDE THE ENCLOSURE.
 INFORMATIVE: A.8.2.3.1EXHAUST SYSTEMS
 SHOULD NOT TERMINATE UNDER STRUCTURES OR
 WHERE THE EXHAUST MIGHT BE DRAWN INTO
 THE VENTILATION INTAKES.
  
 GENERATORS SHALL MAINTAIN THE REQUIRED ABOVE
 MENTIONED CLEARANCES TO THE ADJACENT
 PROPERTY STRUCTURES, I.E. FENCE,
 BUILDING, WINDOWS, DOORS, OR OPENINGS.
  
 FUEL STORAGE TANK MUST BE A MINIMUM DISTANCE OF 5 FEET
 FROM BUILDING, SEE NFPA 30 CH. 4, 4.3.2.1.1.
  
 FOLLOW MANUFACTURER'S RECOMMENDED
 CLEARANCES AROUND EQUIPMENT FOR
 SERVICING,AND PROVIDE MANUFACTURER'S
 INSTALLATION INSTRUCTIONS AT THE JOBSITE
 FOR THE FIELD INSPECTOR.
  
 MECHANICAL PLAN REVIEW BY;
 TOM GORDON (561) 805-6729.